/
A new ILD assembly timeline A new ILD assembly timeline

A new ILD assembly timeline - PowerPoint Presentation

pressio
pressio . @pressio
Follow
343 views
Uploaded On 2020-06-30

A new ILD assembly timeline - PPT Presentation

2016126 Yasuhiro Sugimoto LCWS2016 1 Boundary conditions Detector assembly and commissioning should be completed in 9 years Assembly Hall AH on surface becomes available in Q3 Aug of Y3 ID: 790825

yoke assembly detector step assembly yoke step detector platform swiveling install coil yb0 solenoid timeline muon ild ovt cal

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "A new ILD assembly timeline" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

A new ILD assembly timeline

2016/12/6Yasuhiro Sugimoto@LCWS2016

1

Slide2

Boundary conditions

Detector assembly and commissioning should be completed in 9 years

Assembly Hall (AH) on surface becomes available in Q3 (Aug.) of Y3

Platform over vertical shaft in AH becomes available in Q2 of

Y4Detector Hall (DH) underground becomes available in Q3 (Aug.) of Y7SiD is lowered to DH in Y7-Q3 to Y8-Q1 ILD is lowered to DH in Y8-Q2 to Y8-Q3 after SiD(New assumptions)Magnet full current test should be done before barrel calorimeter installationSolenoid outer vacuum tank (OVT) is built outside YB0 yoke, and inserted to YB0 as a cylinder (Richard’s plan)

2

Slide3

New assumption (1)

Full-current test of detector magnet should be done before barrel CAL installationIf some problem is found in solenoid after CAL installation, we might have to uninstall CAL to repair solenoid

 Risk of large loss of time

To make it possible, iron yokes should be ready earlier than previous plan

3

Slide4

New assumption (2)

Solenoid outer vacuum tank (OVT) is assembled independently from iron yoke

CMS design

Central part of OVT is used as a assembly tool (

Ferris wheel) of central iron yoke (YB0)Solenoid cryostat cannot be removed from YB0ILD design by Richard StromhagenOVT is assembled as a cylinder independently from YB0Solenoid cryostat containing coil is fixed to YB0 by bolts and nuts, and can be removed from YB0, if necessary

4

Slide5

CMS assembly

5

Slide6

ILD assembly

6

Slide7

A possible solution

7

Slide8

Comparison with previous plan

Shorter yoke construction period

Earlier start of Muon/Endcap CAL installation

Shorter Solenoid construction

period on site8

Previous timeline

New

timeline

Slide9

Timeline for solenoid

OVT and coil are assembled and installed using swiveling platform successively (

CMS:OVT

was assembled directly on the YB0)IVT is assembled aside the swiveling platform, and moved to the swiveling platform for installationPeriod for coil assembly on-site is shortened from 30 mo to 16 moStarts 10 mo later due to tool preparation/test (ignored before) and OVT construction and installationCompleted 4 mo earlier to make magnet full current test possible before barrel CAL installationThe timeline is somewhat tight, but still looser (?) than that of CMS

CMS: 5 modules, ILD: 3+

4(DID)

modules (?)

9

Slide10

Longer term timeline

Feasibility of the plan has to be confirmed by a manufacturer

 We asked Toshiba to do this together with feasibility study of DID

10

Visit to Toshiba

Slide11

Garage in AH

11

YB0 in garage

After

Before

15m

25m

10m

15m

Size of the garage (alcove) of Assembly hall should be enlarged

Swiveling platform requires large space during

swiveling

Position

of the swiveling platform is shifted

One more yoke ring exists before Coil/IVT installation

 YB0

with OVT has to be stored in the garage

to keep enough space for

other

yoke assembly and detector installation

Space for cryogenic system on surface

Slide12

Swiveling platform

12

~14m

~14m

~4m

(In case of ILD)

Slide13

Swiveling platform

13

Slide14

Swiveling platform

14

Slide15

Summary

A new ILD assembly timeline has been considered under new assumptions

It seems ILD assembly in 9 years is possible

But there are still many open questions

Iron yoke rings should be assembled in ~6 months/ringIs it feasible?What is the size of pre-assembly hall needed for construction of iron blocks?DID options (No DID or integrated into 3 solenoid modules is favorable from mechanical point of view)Feasibility of DID manufacturingIs the timeline for solenoid (+DID) construction acceptable for manufacturer? Toshiba will study

Space and time requirements for the cryogenic system for solenoid in

Assembly Hall

on surface

Installation method for endcap muon detector (particularly bottom part)

Do we need a pit for installation in AH (and DH)?

Time requirement for land development in IR surface

3Q (assumption) or >2 years (by Tokiko

Onuki

)

In latter case ILD (and ILC) cannot be get ready for collision in 10 years

15

Slide16

Backup slides

16

Slide17

Timeline for each ring

17

Slide18

Step-1

Platform constructionYB0 Yoke assembly

OVT assembly

18

Slide19

Step-2

YE+ Yoke assemblyOVT install

19

Slide20

Step-3

YE+ Yoke assemblyYB0 Muon detector install

Coil assembly

IVT assembly

20

Slide21

Step-4

YE- Yoke assemblyYE+ Muon detector installYB0

M

uon detector cabling

Coil assemblyIVT assembly21

Slide22

Step-5

YE- Yoke assemblyYE+ HCAL installCoil assembly

IVT assembly

22

Slide23

Step-6

YB+ Yoke assemblyYE+ ECAL installYE- Muon detector install

Coil assembly

IVT assembly

23

Slide24

Step-7

YB+ Yoke assemblyYE+ Muon detector cabling

YE- HCAL install

Coil assembly

IVT assembly24

Slide25

Step-8

YB- Yoke assemblyYE- Muon detector cabling

YE+ HCAL,ECAL cabling

YB0 Coil install

25

Slide26

Step-9

YB- Yoke assemblyYE- HCAL cablingYB0 IVT install

26

Slide27

Step-10

27

Disassemble swiveling platform

Shuffle yoke rings

Cryogenic system construction in garage

Cryo

.

Cryo

.

Cryo

.

Slide28

Step-11

YE- ECAL installYB0 Cryogenics install

Coil cooling

28

Cryogenics

Slide29

Step-12

Close detectorMagnet full current test

29

Cryogenics

Slide30

Step-13

Open detectorYB+ Muon detector install

YB0 CAL install

YE- ECAL cabling

30

Cryogenics

Slide31

Step-14

YB- Muon detector installYB0 CAL install

31

Cryogenics

Slide32

Step-15

Close detectorField mapping

32

Cryogenics