Hughes v.  Talen  Energy Mktg., LLC Hughes v.  Talen  Energy Mktg., LLC

Hughes v. Talen Energy Mktg., LLC - PowerPoint Presentation

tawny-fly
tawny-fly . @tawny-fly
Follow
365 views
Uploaded On 2018-03-17

Hughes v. Talen Energy Mktg., LLC - PPT Presentation

136 SCt 1288 April 19 2016 Seth Hollander Assistant Attorney General Connecticut Office of the Attorney General The views expressed here are not necessarily the views of the Connecticut Office of the Attorney General ID: 653946

capacity price clearing contract price capacity contract clearing month auction general difference generator ratepayers attorney edc payment pjm quantity

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Hughes v. Talen Energy Mktg., LLC" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Hughes v. Talen Energy Mktg., LLC,136 S.Ct. 1288 (April 19, 2016)

Seth HollanderAssistant Attorney General ,Connecticut Office of the Attorney General

* The views expressed here are not necessarily the views of the Connecticut Office of the Attorney GeneralSlide2

What Was Maryland Up To?Slide3
Slide4
Slide5
Slide6

Contract Capacity Price

Capacity Auction Clearing Price

$10/kW Month

$4.50/kW Month

$10 – $4.50 = $5.50

$5.50 * Quantity = Contract Payment from EDC/ratepayers

to

generator

Difference Between Contract Capacity Price

and PJM Capacity Auction Clearing PriceSlide7

Contract Capacity Price

Capacity Auction Clearing Price

$10/kW Month

$7/kW Month

$10 – $7 = $3

$3 * Quantity = Contract Payment from EDC/ratepayers

to

generator

Difference Between Contract Capacity Price

and PJM Capacity Auction Clearing PriceSlide8

Contract Capacity Price

Capacity Auction Clearing Price

$10/kW Month

$15/kW Month

$10 – $15 = $-5

$-5 * Quantity = Contract Payment from generator

to

EDC/ratepayers

Difference Between Contract Capacity Price

and PJM Capacity Auction Clearing PriceSlide9
Slide10

Setting Wholesale RatesSlide11

What About State Exercise of Allocated Authority Under the FPA?Slide12

Difference Between Bilateral Contracts and Contracts-for-Differences

Solicitor General

Hughes

CourtSlide13