WaterSewer Debbie Watkins February 11 2017 WaterSewer Initiatives Water System Improvement Aka Second Source Waste Water Management System Second Source Village Well in Frontenac is 45 years old ID: 559366

source water test state water source state test sewer gallons 2015 system management waste development 2016 village agreement 2017

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "State of the Village" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

State of the Village Water/Sewer

Debbie Watkins

February 11, 2017Slide2

Water/Sewer InitiativesWater System Improvement

Aka Second Source

Waste Water Management SystemSlide3

Second SourceVillage Well in Frontenac is 45 years old

Hoffmire

Well current second source is not adequate

Department of Health has cited Village for 18 years

Many false startsSlide4

Second Source 2014Received MOU from State to continue well developmentDrilled 3 test wellsCompleted development of first test well – 350 gallons per minute - Target is 500 g/min

Passed resolution for 4.4 million dollars

Authorized development of next test wellSlide5

Second Source 2015Successful test wells completed

Petitioned State in March for Park easements

Received the agreement late December

Went out to bid and delayed awards due to late receipt of State agreementSlide6

2015 Continued

Agreement with State on Easement/Leasehold

$2 Million Grant to offset costs

0% Interest Rate on Loan BalanceSlide7

2016 Second SourceDistribution lines installedPump houses constructed

Construction commenced early April Slide8

2017Punch lists on pump housesLaboratory testing COMPLETION!!!Slide9

Waste ManagementState guideline changes for metric reportingDEC notification of changes required

2014 - 2015 Engineering Plan

2015 and 2016 EFC Funding application

2016 ConstructionSlide10

NEXT STEPSLandscaping/PavingPossible Press replacementAwaiting EFC grant ruling

New operational management

Training to support new facilitiesSlide11

FOR YOUR INFORMATIONNo increases are currently planned for 2017-2018 rates.

Water and Sewer expenses are not funded by your taxes. They are a direct result of the utilization.

You can help prolong the longevity of the waste water plant. The sewer system is NOT a receptacle for diapers, rags, depends, and especially disposable wipes. They are not biodegradable even if they say disposable. They can clog the works. Slide12

SAVE MONEYLow Flow ToiletsCan save a family of four up to 16,500 gallons a yearA drip a second can be 5 gallons a day

Reuse towels

Keep your shower under 5 minutes and save 1000 gallons a month

Soak pots and pans rather running water as you scrape

While you wait for hot water, collect running water to water plants

http://wateruseitwisely.com/100-ways-to-conserve/Slide13

Department OF pUBLIC WORKS

Ground Maintenance

Building Maintenance

Mulching

Sidewalks

Water Main Breaks

Snow Removal

Paving prep

Community support requests –

ie

. Festival of Lights, banner hanging

APPRECIATE A DPW WORKER TODAY!Slide14