Until the end of Run17 Week Access Requests Work at IR2 CeC Activities March 20 3 hours Drive laser alignment Low energy beamline commissioning 704 MHz commissioning March 27 full day maintenance ID: 631217
Download Presentation The PPT/PDF document "Tentative CeC Schedule" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Tentative CeC Schedule
Until the end of Run17Slide2
Week
Access Requests
Work at IR2CeC ActivitiesMarch 203 hoursDrive laser alignmentLow energy beamline commissioning, 704 MHz commissioningMarch 27full day maintenanceStart preparation for He conditioning,finish drive laser alignmentLow energy beamline commissioning, 500 MHz turn onApril 32 hoursNew cathode insertionLow energy beamline commissioningApril 10full day maintenanceNew garage,Finish preparation for He conditioningStart 704 MHz cavity conditioning
Earlier start of helium conditioning might extend conditioning time and help to avoid the lengthy gun tuningSlide3
Week
Access Requests
Work at IR2CeC ActivitiesApril 173 hoursIf needed to fix He systemEnd 704 MHz commissioning, finalize hadron energyApril 243 days of access to IR2 (night runs)New garage with cathodes, re-tune gun cavityRe-commissioning gunMay 14 8-hour shifts of no protons in RHICPropagate beam to high power dump, measure beam optics in the common sectionCommissioning of entire accelerator, ramp developmentMay 8full day maintenancetwo 8-hour shifts
New garage with
cathodes, close undulator gapDeliver beam to HP dump after gap closure
Earlier start of helium conditioning might extend conditioning time and help to avoid the lengthy gun tuningSlide4
Week
Access Requests
Work at IR2CeC ActivitiesMay 154 hoursRadiation survey with 1-100 W beamCommissioning MPS, beam optimization May 22full day maintenance4 hoursNew garage,Radiation survey with 100-8000 W beamFull power beam operationMay 29Six 8-hour shiftsRepairs/adjustments of IR diagnosticsIR diagnostics commissioning, FEL commissioningSlide5
Week
Access Requests
Work at IR2CeC ActivitiesJune 5Six 8-hour shifts, MaintenanceNew garageHadron and e-beam set-upJune 1214 8-hour shiftsCooling experimentsJune 19End of the Run 17