121.04.06 – Beam Commissioning 121.04.06 – Beam Commissioning

121.04.06 – Beam Commissioning - PowerPoint Presentation

tawny-fly
tawny-fly . @tawny-fly
Follow
342 views
Uploaded On 2019-11-24

121.04.06 – Beam Commissioning - PPT Presentation

1210406 Beam Commissioning 1210407 Accelerator Physics Eduard Pozdeyev BOE External Review 45 March 2019 Outline Introduction ScopeWBS Dictionary ScopeDeliverables Requirements Schedule ID: 767863

beam commissioning infrastructure 121 commissioning beam 121 infrastructure march test leibfritz linac pip2 2019 shielding inst accelerator analysis physics

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "121.04.06 – Beam Commissioning" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

121.04.06 – Beam Commissioning121.04.07 – Accelerator Physics Eduard Pozdeyev BOE External Review 4-5 March 2019

OutlineIntroductionScope/WBS Dictionary Scope/DeliverablesRequirementsScheduleCost March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 2

About Me:PIP2 Project Scientist, joined Fermilab in 11/2018 (3.5 month ago) L3 Manager Beam Commissioning of PIP2IT and PIP2 Additional ResponsibilitiesCoordination Contac for PIP2 activitiesPositions Previously Held at FRIB9 years at FRIB, started prior to CD1 reviewFRIB Front End Dept. manager and CAM FRIB Accelerator Operations Dept Manager March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 3

Scope 121.04.06 Beam CommissioningWBS Dictionary March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 4 121.04.06 Inst - Beam Commissioning ( Comm ) Beam commissioning of the accelerator sections (WFE, SCL, BTL/BAL), including beam commissioning of booster. Final deliverable is a machine achieving KPPs that is handed off to operations. 121.04.06.01 Inst - Comm - Project Management and Coordination (PM) Project management for commissioning including the oversight and coordination of the technical effort, project planning and scheduling, cost estimating, risk and contingency analysis, and reporting. Includes travel costs for management, technical coordination, and vendor visits. 121.04.06.02 Inst - Comm - PIP2IT Development of the beam commissioning plan and conduct beam commissioning of the WFE/HWR/protoSSR1 at PIP2IT. 121.04.06.03 Inst - Comm - PIP-II Development of beam commissioning plan of the PIP-II (WFE SCL BAL BTL). Includes the planning, development and optimization of the high level applications to be used during beam commissioning. It also includes costs associated with the setup of control room at PIP-II Linac Gallery, assembly of the diagnostic carts, installation of temporary shielding within the beamline enclosure to support staged beam commissioning. It also includes beam commissioning of booster until reach KPP.

Scope 121.04.07 Accelerator PhysicsWBS Dictionary March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 5 121.04.07 Inst - Accelerator Physics Work associated with the Accelerator Physics design, analysis, reports, and commissioning efforts. It includes the development of the Conceptual Design Report, Technical Design Report, and analysis of ongoing beam efforts and measurements. 121.04.07.01 Inst - AP - Project Management and Coordination (PM) Project management for the Accelerator Physics efforts including the oversight and coordination of the technical effort, project planning and scheduling, cost estimating, risk and contingency analysis, and reporting. Includes travel costs for management, technical coordination, and vendor visits. 121.04.07.02 Inst - AP - Accelerator Physics Studies Accelerator Physics Studies work is associated with development and maintenance of the linac beam lattice, perform beam simulations and post beam analysis. It also includes effort associated with development of project technical reports. 121.04.07.03 Inst - AP - Shielding Assessment (Shld) Analysis of hazards associated with beam and equipment induced radiation, development of requirements for shielding and other mitigations, effort to prepare reports of such studies, communication to the Radiation Shielding Assessment Panel, RSO, and other Safety Regulators to approve shielding design.

Scope of Beam Commissioning: PIP2IT March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 6 Full scale PIP-II 2.1 MeV normal conducting front-end – already commissioned HWR and SSR1 CM commissioning with beam Source LEBT RFQ MEBT HWR SSR1 30 keV 2.1 MeV 10 MeV HEBT 25 MeV After FY20 will be repurposed to PIP-II CM test facility Beam Commissioning Apr 2020 – Sep 2020

Priorities and Requirements for PIP2IT Highest Priority is to demonstrate Critical TechnologiesPerformance of SRF cryomodulesPerformance of cavities in cryomodulesLLRF: phase and voltage stability Accelerate beamMeasure and demonstrate parameters Gain experience with installation and commissioning procedures March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 7

121.04.06.02 BOE Covers Development of the beam commissioning planBeam commissioning of the WFE/HWR/protoSSR1 at PIP2ITLabor covers resources to prepare the commissioning plan and beam commissioning procedures, resources required to conduct the beam commissioning, and resources to operate and support PIP2IT systems during beam commissioning. M&S covers cost of cryogens and consumables (no electrical power) required to commission PIP2IT. March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 8

Scope of Beam Commissioning: PIP2 March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 9 800 MeV H− linac Warm Front End SRF section 2 mA, pulsed 1% DF 17 kW average beam power Linac -to-Booster transfer line 3-way beam split Upgraded Booster 20 Hz, 800 MeV injection New injection area

PIP2 KPPs March 4-5, 2019J. Leibfritz | 121.04.03-Test Infrastructure 10 # Scope Threshold KPP Objective KPP 1 SRF Linac Beam Energy 600  MeV 800  MeV 2 Linac Beam Beam delivered to the Beamline Dump 5.4E12 particles per pulse (H-) at 20 Hz beam delivered to the Beamline Dump 3 Booster/Recycler/Main Injector upgrades Booster injection region, Recycler RF upgrades, and Main Injector RF upgrades, hardware installed and tested without beam in respective machines. Linac beam injected and circulated in the Booster  4 Cryogenic Infrastructure Cryogenic plant and associated distribution system are installed and capable to support cavities operation at 2 K Cryogenic system installed and is capable to support Linac operation in CW mode

Commissioning Split In Four Stages WFEPhase 1: SSR1, 35 MeVPhase 2: SSR2, 185 MeVPhase 3: Linac 800 MeV, BTL, BoosterTemporary Instrumentation cart/line will be used for commissioning March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 11 WFE Phase 1 Phase 3 Phase 3 to Booster

PIP2 Commissioning Schedule March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 12 Tunnel BOD - 31-Jan-23 Linac Gallery BOD - 31-Oct-23 BTL–Booster CF Phase 2 Complete – 1-May-26 BTL Absorber installed, 22-Jul- 26 Needs to be updated after latest changes

Assumptions Work on Transition To Operations Plan is in ProgressIt is assumed that Operators are covered by AD OperationsPIP2 pays for cryoplant: Beam Commissioning pays during commissioning and installation pays between commissioning periods March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 13

121.04.06.03 BOE Covers Prepare the commissioning plan and commissioning proceduresPrepare for and conduct accelerator reediness reviews (ARRs)Conduct the beam commissioningOperate and support PIP2 technical systems during beam commissioning.Develop High Level Applications (HLAs) for beam commissioning M&S required to support commissioning (cryogens, consumables (no electricity), and miscellaneous parts) Labor and M&S required to develop and procure the temporary diagnostics cart/line for phased linac commissioning Labor and material to setup the PIP2 control room in the PIP2 high bay for WFE, Linac , and BTL commissioning Develop Final Transition To Operations Plan March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 14

Scope of Accelerator Physics121.04.07.02 BOE Covers Accelerator Physics Studies to develop PIP2 physics design, support design effort for other PIP2 systems, and ensure integration of the PIP2 linac with other Fermilab machines (4350h) Development of commissioning plans and techniques for beam commissioning of PIP2 linac (2450h)Development of physics algorithms for High Level Applications and communication with controls department (6660h)Support of beam commissioning for PIP through off-line data analysis and improvement of commissioning procedures and software (8393h) March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 15

Scope of Shielding Analysis121.04.07.03 BOE Covers [1] Conduct shielding and other radiation hazard analysis for PIP2 linac and BTL (4256h). The activity will results a complete report of the shielding analysis Final shielding assessment review of the as-built PIP2 Linac enclosure (617h) and update of SAD and other relevant documentation Conduct shielding and other radiation hazard analysis for Booster (2027h). Final shielding assessment review of the as-built PIP2 Linac enclosure (445h) and update of SAD and other relevant documentation March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 16

Shielding Assessment Will Be Conducted by MARS Group The estimate assumes that the shielding analysis will be conducted by the MARS group with assistance from dedicated PIP2 personnel. Preliminary agreement from MARS group receivedThe estimate for the analysis effort was provided by the MARS group and was based on experience with the analyses conducted by the group in support of ESS. The estimate for other activities (reviews, communication to Safety) was based on existing experience in Fermilab . March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 17

Cost Summary March 4-5, 2019J. Leibfritz | 121.04.03-Test Infrastructure 18 WBS FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 Total 121.04.06.01 Inst - Comm - Project Management and Coordination $88,890 $245,685 $99,074 $106,811 $232,916 $734,609 $835,942 $1,016,566 $497,625 $3,858,118 121.04.06.02 Inst - Comm - PIP2IT $17,383 $ 1,452,881 $ $ $ $ $ $ $ $1,470,264 121.04.06.03 Inst - Comm - PIP-II $ $ $107,861 $341,440 $1,449,559 $1,066,283 $1,015,724 $4,084,282 $1,293,526 $9,358,675 121.04.07.01 Inst - AP - Project Management and Coordination (PM) $ 27,325 $36,195 $85,150 $87,755 $90,208 $93,210 $96,062 $45,350 $ $561,255 121.04.07.02 Inst - AP - Accelerator Physics Studies $703,423 $471,717 $570,221 $420,336 $433,786 $424,853 $920,865 $953,557 $144,760 $5,043,518 121.04.07.03 Inst - AP - Shielding Assessment (Shld) $ 282,864 $552,234 $483,749 $27,960 $ $149,061 $ $114,632 $ $1,610,500

Thank You! March 4-5, 2019 J. Leibfritz | 121.04.03-Test Infrastructure 19