/
FCC Civil  Engineering John Osborne & FCC Civil  Engineering John Osborne &

FCC Civil Engineering John Osborne & - PowerPoint Presentation

botgreat
botgreat . @botgreat
Follow
342 views
Uploaded On 2020-06-29

FCC Civil Engineering John Osborne & - PPT Presentation

Jo Stanyard SMB Site Engineering FAS Section FCC Workshop FIMLCERN 3rd May 2017 Summary from 7 th March meeting John Osborne Joanna Stanyard CERNSMBSE Baseline layout 9775 km single tunnel design experiments located at point L A B and G 4 larger magnet delivery sha ID: 788492

tunnel cern osborne john cern tunnel john osborne smb stanyard joanna access shaft inclined layout tunnels water magnet duct

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "FCC Civil Engineering John Osborne &..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

FCC Civil Engineering

John Osborne & Jo Stanyard (SMB - Site Engineering - FAS Section)FCC Workshop FIML-CERN3rd May 2017

Slide2

Summary from 7

th March meeting

John Osborne, Joanna Stanyard (CERN-SMB-SE)

Baseline layout – 97.75 km single tunnel design, experiments located at point L, A, B and G, 4 larger magnet delivery shafts.

Double tunnel layout – 5 m ID and 3 m ID tunnels replace the single 6 m ID.

Baseline location including shaft depths – maximum 450 m deep.

Inclined access study including potential locations.

Shallow option

False floor study

Slide3

Updated schematic

John Osborne, Joanna Stanyard (CERN-SMB-SE)

Slide4

Layout position development

John Osborne, Joanna Stanyard (CERN-SMB-SE)

New layout design

4 variations produced with small differences in the short arcs.

Slide5

Layout position development

John Osborne, Joanna Stanyard (CERN-SMB-SE)

Draft Position

Inclined alternatives:

14.9 % slope = 2560m

6% slope =

4800m

Slide6

Spoil Volume

John Osborne, Joanna Stanyard (CERN-SMB-SE)

Approximately 8 million m

3

of spoil from single tunnel option (unexpanded quantity).

Typical proportions along tunnel length:

91%

molasse

– sedimentary rock, potential use: general fill below road construction layers.

6% limestone – potential use: concrete.

3% moraines – fluvial deposits, minimal use.

Future study to provide the time and location of quantities of each type of spoil delivered to the surface.

Slide7

Baseline Schedule -

DRAFT

John Osborne, Joanna Stanyard (CERN-SMB-SE)

1

2

3

4

5

6

7

Single tunnel, no inclined access tunnels.

Some potential for optimisation.

First sectors delivered in approximately 6 year, 10 months.

Construction complete in 7.5 years.

Slide8

Optimised Schedule -

DRAFT

John Osborne, Joanna Stanyard (CERN-SMB-SE)

1

2

3

4

5

6

Single tunnel, with inclined access tunnels in sectors I-J, J-K & K-L.

First 2 adjacent sectors delivered in approximately 4 year, 8 months.

Construction complete in 6 years, 8 month.

Slide9

FCC Tunnel 6m diameter fani.valchkova@cern.ch

Machine cryostat DN 1480QRL DN 1200

Warm He recovery DN 250

He DN 100

Compressed air DN 80

Demineralized water filling DN 65

SC link DN 250

Cable trays

(

Fiber

optics, LV distribution, control cable)

Survey

Smoke/He Extraction

Demineralized water DN250

HV transmission

Cable trays

(General services/secured network,

MV distribution)

Radiating cable

Raw water/firefighting

First aid eqpt.

Electrical box

Transport vehicle

Fresh air duct

Drain

Slide10

fani.valchkova@cern.chFCC Tunnel and Alcove

Top view User racks: 28 m²UPS and Secure systems:

31 m²CV equipment: 18.1 m²

MV to LV switchgear: 31

Transformer

02/05/2017

Slide11

fani.valchkova@cern.ch

FCC Shaft 12.5mVentilation Duct Machine Area DN1200(In)Ventilation Duct UAsUnderground Cavern(In/Out)Pressurization Duct Shaft and Lift CageEmergency Extraction Ducts

DN1200QRL Pipes:DN 100 - Helium ring lineDN 250 - Warm recovery line

DN 400 – Quench buffer line

QRL Vertical transfer line

DN 1000

Transmission Line

&

Cable Trays

Pipes:

DN 200 - Primary water coolingDN 240 - Chilled waterDN

150 - Fire fightingDN200 - Make up waterDN80 - Compressed airDN80 - Demineralized waterDN100 - Waste water

DN200 - Clear

water

drain

Ventilation Duct Dump DN 500

DN 1000 Ventilation Duct

Collimation (In/Out)

Open Space

02/05/2017

Slide12

fani.valchkova@cern.chFCC Shaft 12.5m

02/05/2017

Slide13

PREVIOUS SLIDES13

Slide14

Baseline layout – 97.75 km

John Osborne, Joanna Stanyard (CERN-SMB-SE)

Slide15

Baseline layout - Dimensions

A

B

C

D

E

F

G

H

I

J

K

L

Approximate Sector lengths:

Section

Total Length (m)

A-B

5400

B-C

8800

C-D

10300

D-E

10300

E-F

8900

F-G

5300

G-H

5300

H-I

8900

I-J

10300

J-K

10300

K-L

8900

L-A

5300

John Osborne, Joanna Stanyard (CERN-SMB-SE)

18

m Ø shaft for magnet delivery.

18

m Ø shaft for magnet delivery.

18

m Ø shaft for magnet delivery.

18

m Ø shaft for magnet delivery.

Slide16

Basic structure dimensions

Pre-Alps Mountains

John Osborne, Joanna Stanyard (CERN-SMB-SE)

Structure Type

Points

Basic

internal dimensions

Standard

Service Shafts

D,F,H,J

Diameter 12 mMagnet lowering service shaftsC,E,I,KDiameter 18 mExperimental ShaftsL,A,B,GDiameter 15 mStandard Service

caverns

D,F,H,J

15(w) x 15(h) x 100(l)

Magnet lowering service caverns

C,E,I,K

22(w) x 15(h) x 100(l)

Service caverns at experimental points

L,A,B,G

20(w) x 15(h) x 120(l)

Experimental caverns

L,A,B,G

30(w) x 35(h) x 70(l)

Beam tunnel

-

Diameter 6

m

Slide17

Double Tunnel

John Osborne, Joanna Stanyard (CERN-SMB-SE)

A

B

C

D

E

F

G

H

I

J

K

L

Structure

Dimension

Machine

tunnel

5 m ID

Safety tunnel

3 m ID

Connection tunnel and alcove layout:

Slide18

Geology of chosen layout for Phase 1 Cost & Schedule study

Length = 97.75 kmMinimises length of tunnel in the limestone, apart from the unavoidable location between H & I, only a small length of tunnel in Jura limestone.

Avoids any tunnel length being in the moraines

John Osborne (CERN-SMB-SE)

John Osborne, Joanna Stanyard (CERN-SMB-SE)

Slide19

Possible TBM launch locations

John Osborne (CERN-SMB-SE)

John Osborne, Joanna Stanyard (CERN-SMB-SE)

Excavation proposal:

2 sectors Drill & Blast (H-I and K-L)

8

TBMs for the remaining 10 sectors

Mined excavation for remaining by-passes and auxiliary tunnels.

Slide20

Inclined Access Study

Pre-Alps Mountains

John Osborne, Joanna Stanyard (CERN-SMB-SE)

Inclined access tunnels could replace service shafts or be used in addition to the shaft to accelerate the construction programme.

Could be located at the access points to replace shaft or in addition to shafts.

Possibility to locate between shafts to accelerate construction, particularly on long sections.

Feasibility has been confirmed for 6.0 m ID ring and access tunnel.

Machine ring

Inclined tunnel

Slide21

Inclined Access Tunnels at access points

John Osborne, Joanna Stanyard (CERN-SMB-SE)

Slide22

Inclined Access Tunnels between access points

John Osborne, Joanna Stanyard (CERN-SMB-SE)

Examples with maximum 15% slope:

1

2

3

1:

2

:

3:

Slide23

Lake Crossing: Tunnelling Considerations

Open Shield TBM

Slurry TBM

Immersed Tube Tunnel

Superficial sediments

Moraine

Molasse

Medway Tunnel Immersed Tube Tunnel

Slide24

Moraines Shallow Option

John Osborne, Joanna Stanyard (CERN-SMB-SE)

Shallow option passes through moraine under lake and at point E.

Total shaft depth reduced by 744 m compared to baseline.

Possibility for a further shallower option with a submerged tube tunnel under the late.

Slide25

False Floor Option

John Osborne, Joanna Stanyard (CERN-SMB-SE)

Slide26