/
Flamboro Wells Project CAP Update Flamboro Wells Project CAP Update

Flamboro Wells Project CAP Update - PowerPoint Presentation

celsa-spraggs
celsa-spraggs . @celsa-spraggs
Follow
366 views
Uploaded On 2018-03-13

Flamboro Wells Project CAP Update - PPT Presentation

June 23 2014 20140620 Strength Flamboro Wells Project Summary Reminder The Flamboro Quarry Neighbour Wells Project is a proactive initiative undertaken by Dufferin Aggregates in preparation for extraction ID: 650105

pump wells test neighbours wells pump neighbours test dfa neighbour masl flamboro sump project current 2014 installed treatment depth

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Flamboro Wells Project CAP Update" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Flamboro Wells Project

CAP Update

June 23, 2014

2014-06-20

Strength.Slide2

Flamboro Wells Project Summary

Reminder

The Flamboro Quarry Neighbour Wells Project is a proactive initiative undertaken by Dufferin Aggregates in preparation for extraction in the second bench

The purpose of extracting the lower bench is NOT to increase the quarry annual tonnage;

but rather we are

acting within our current license, we are licensed to extract to a depth of 230 mASl

2014-06-20

2Slide3

Flamboro Wells Project Summary

3

20 new wells and 23 water treatment systems were provided to neighbours

Typical treatment system for new wells include Sulfur filter, Holding tank, repressurization pump, sediment filter, UV, softener, Reverse Osmosis

Follow up visits to ensure

neighbour satisfaction

are still needed at 5 locations (underway)

Current Floor ≈ 240mASL

252 – 255mASL

MNR Approval to 230mASL

≈ 6.6Mt Resources to 225mASL

Old Wells

New Wells

(≈ 190mASL)Slide4

Plan for Deepening

A phased approach / pump test will be needed to systematically evaluate impact to GW and neighbour wells that were left as is:Lower sump water level ±1m at a time, wait a few days to see impacts in monitoring wells then continue

E&P to work with CRA to give green light for each stagePump will not be lowered on a Thursday or Friday : ideally, DFA

will lower pump each Monday and CRA will download loggers each Thursday

Significant rainfall amount will immediately effect results and delay interpretation and pump test process

Current Level =

233

mASL / Final Level = approx. 228 mASL. Timeline for pump test =

MINIMUM 5 WEEKS

Sump depth must be lowered to below 228 mASL (current depth = ~232 mASL)

Example timeline: Pump test could run until July 25 OR LATER

Preparations for the Extraction of the 2nd Bench are Underway4Slide5

During the Pump test a Network of Wells will be Monitored Weekly to Determine Drawdown / Effects on Water Levels

5

DFA monitoring well:

Neighbour well:

Dataloggers have been

installed at some of the neighbour’s homes to monitor drawdown when DFA lowers the sump

3 dataloggers

installed

in

total (1 resident already had a logger installed)Slide6

Communication strategy with Neighbours

DFA to ensure neighbours are home during pump testThere are 3 neighbours on 5

th Line who have wells with unknown depths. DFA to stay in communication with neighbours who did not receive a well replacement

Assessment indicated low likelihood of impact based on GW flows and neighbour locations / well depths

Emergency

Provisions

Temporary supplies can be made immediately available via

500 gallon holding tank, etc. OWWE&P to ensure contractors are available to drill wells and install treatment if necessary

Hold sump until issue is resolved

E&P will Communicate Pump Test Dates to Neighbours of Concern as Well as Contractors

6Slide7