/
Outage Leading Outage Leading

Outage Leading - PowerPoint Presentation

celsa-spraggs
celsa-spraggs . @celsa-spraggs
Follow
405 views
Uploaded On 2017-05-25

Outage Leading - PPT Presentation

Indicators Nuclear Work Control CFAM Rick Green Duke Energy Nuclear information Corporate Office Charlotte North Carolina USA 2 Plant Units Location Type Turbine MWeUnit Brunswick ID: 551896

scope outage production dose outage scope dose production box duration cost amp budget day work projected usa indicators duke

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Outage Leading" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Outage Leading

Indicators

Nuclear Work

Control

CFAM: Rick GreenSlide2

Duke Energy Nuclear information

Corporate Office: Charlotte, North Carolina, USA

2

Plant

Units

Location

Type

Turbine

MWe/Unit

Brunswick

2

Southport,

NC, USA

GE Mark 4 BWR

GE

945

Catawba

2

York,

SC, USA

4 loop Westinghouse PWR

Ice

Condenser

GE

1145

Harris

1

Cary,

NC, USA

3 loop

Westinghouse PWR

Westinghouse

928

McGuire

2

Huntersville,

NC, USA

4 loop Westinghouse PWR

Ice

Condenser

Westinghouse

1145

Oconee

3

Seneca,

SC, USA

2 loop

B&W PWR

GE

850

Robinson

1

Hartsville,

SC, USA

3 loop

Westinghouse PWR

Westinghouse

741Slide3

Outage Goal

Execute predictable outages that support top quartile fleet capacity factors and top quartile

cost without sacrificing Personal, Radiological or Nuclear Safety

3Slide4

The Issue

We were frequently finding misalignment between outage scope and goals at our T-3 Readiness Reviews.

Executive awareness of this misalignment was not profound until ~T-2Recovery efforts were often disruptive and counter-productive.Actual outage results were frequently short of goals4Slide5

Solution

Identify variables that are meaningful, measureable, and forecastable.

Integrate these variables and the requirement to forecast them into outage processesEstablish visible and transparent monitoring of these variablesEstablish criteria for grading the variables and responding to unfavorable trends5Slide6

The Outage Box

The objective of the Outage Box is to institute a fleet standard approach to budgeting, scheduling and assigning O&M

and capital work in outages6Budget Duration Top Quartile Goals

-Capacity Factor -Flat O&M budget

-Achievable production

rates

-Top Q Dose

Activities/Day

DoseSlide7

Outage Leading Indicators

7Slide8

Outage Leading Indicator Basis

Production

RED

Historical Norm

321

Predicted (before T-6)

Target (after T-6)

367

In Escalation

Date to return Green

8/10/2015

GREEN

– No known or predicted gap and confidence is high that the goal can be achieved with the current scope.

YELLOW

– A gap exists but can be managed to within normal processes without need for a recover plan:

"Normal processes" apply to the scope selection process from T-14 to T-10

After T-10, yellow may be used only when there are small gaps and this will require Outage CFAM approval.

RED

– A recovery plan is needed to drive improvement efforts, reduce or eliminate scope, or to request a formal change to the impacted goal.

A YELLOW status requires a supporting item on the Pre-Outage Focus List with an owner and due date for the improvement effort.

A RED status requires a supporting item on the Pre-Outage Focus List with an associated recovery plan.

The intent is for there to be no RED indicators after scope freeze.

Any RED indictors after scope freeze shall result in escalation.

8Slide9

The Outage Box: Allocation

Projected

Duration < Approved AllocationProjected Duration = Schedule duration + 4 days marginAllocation template durations are 26 or 29 days (outages are on a short-long repeating pattern)37 extra days are available each year to increase allocations for larger projectsGoal is top quartile Capacity Factor9Slide10

The Outage Box: Budget

Projected Cost ($M)

< Approved Outage Budget ($M)Projected Cost = Cost estimate + $1.5M marginGoal is to freeze outage costs at starting at 2014 levels for at least the next 5 yearsGoal is to have approved outage budgets before the start of scoping for the first outage of the year.10Slide11

The Outage Box: Budget

Established

a “flat” fleet outage annual budget Allocate funds fairly based on template durations rather than total approved allocation (SODA typically added for impacts due to capital projects)Develop a methodology that provides predictable and consistent base outage budgets11Slide12

The Outage Box: Budget

Budget dollars

are first allocated on a fixed amount per template outage day (either 26 day short or 29 day long)A fixed amount (“kicker”) is added to each outage budget to cover some smaller O&M projects (less than $1M)The remaining dollars are distributed to specific outages on a priority bases to cover larger O&M projects12Slide13

The Outage Box: Production

Historical Production Norms vs. Projected Production requirements

Production is measured as average number of activities completed per day from shutdown to Mode 4 up (Mode 2 for BWR).Goal is to align bulk work with proven ability to perform work to minimize bow waves, schedule impacts, and cost.No credit will be given for “promise of better production”. Production targets will only be increased when actual net production has been proven to increase13Slide14

The Outage Box: Production

14Slide15

The Outage Box: Production

A “Production Predictor” spreadsheet has been developed to allow forecasting based on the number of work orders in scope.

7 variables are needed to predict:Number of non work order activities predicted Current number of work orders in scopeTasks/work orderNumber of activities up to the day before breaker openedNumber of activities from day after Mode 4 through end of the outage projectScheduled outage period in whole days from day of shutdown to day Mode 4 reachedHistorical Norm - Net Production (activities/day)15Slide16

Production Predictor

16Slide17

The Outage Box: Dose

Target Dose vs. Projected Dose

Goal is alignment with 5 Year ALARA Plan, obtain full INPO points, and reach top quartile.The target dose should be based on the preliminary dose goal (developed per milestone M-7). The goal should support the site 5 year ALARA plan.17Slide18

The Outage Box: Dose

The projected dose should be the estimate based on the current projected scope of work and historical norms.

If the projected dose does not support full INPO points during the following cycle, then the indicator should be turned RED.18Slide19

Insights

Production is currently the usual limiting variable for outage scoping.

Budget projections are currently not accurate and may be a hidden limit for some sites until shortly before the outage starts.The data is telling us that most sites have allowed base scope to increase outside of template durationsUpon introduction of the leading indicators and the outage box in the Summer of 2015 (especially limitation of scope to max production levels), outage performance has drastically improved.19Slide20

20

Duke Outage

ResultsDuke 2015 Spring Outage Results (Pre-Leading Indicators)Outage

Personal Safety

Personal Safety

Incidents

Incidents

Dose

Dose

Duration

Duration

O&M Cost

O&M Cost

Scope Comp.

Scope Comp.

2015

Brunswick

B222

0

1

0

0

150.00

167.40

36

44.08

48.8

52.6

95

97.3

Catawba C2EOC20

0

2

0

0

65.20

67.80

31

36.40

46.6

43.6

95

97.0

Harris H119

0

0

0

0

53.00

56.80

34

43.65

46

60.7

95

97.1

Robinson R229

0

3

0

1

50.00

52.66

29

44.31

37.5

38.78

95

95.2Slide21

21

Duke Outage

ResultsDuke 2015 Fall Outage Results (Post Leading Indicators)Outage

Personal Safety

Personal Safety

Incidents

Incidents

Dose

Dose

Duration

Duration

O&M Cost

O&M Cost

Scope Comp.

Scope Comp.

2015

McGuire

M2EOC23

0

0

0

0

42.00

36.36

30

27.70

38.5

34

95

98.0

Oconee

O2EOC27

0

0

0

0

65.00

58.70

30

26.29

40.7

34.7

95

98.7

Catawba C1EOC22

0

0

0

0

39.30

35.40

31

26.96

37.2

33.4

95

97.3Slide22

22

Duke Outage

ResultsDuke 2016 Outage Results (Post Leading Indicators)Outage

Personal Safety

Personal Safety

Incidents

Incidents

Dose

Dose

Duration

Duration

O&M Cost

O&M Cost

Scope Comp.

Scope Comp.

2016

Brunswick B121

0

0

0

0

126.00

118.55

28

27.10

36.7

36

95

99.1

McGuire M1EOC24

0

1

0

0

58.60

53.79

29

29

34.9

33

95

98.8

Oconee

O3EOC28

0

0

0

0

48.00

39.76

34

23.67

35.2

29.5

95

98.5

Catawba C2EOC21

0

2

0

0

67.00

69.40

32

28.92

43.7

43.1

95

98.9

Harris H120

0

10048.87462624..25*35.132.9*9599.9 Oconee O1EOC29000136.0023.453422.4438.0528.99599.7

*H120 outage had emergent reactor head repairs performed by

Areva

. Overall duration and cost could have met goals in absence of this.

Duration: 34.29d-10.04d=24.25 days

Cost:

$38.0 - $5.1 = $

32.9Slide23

Questions

23