Download Presentation The PPT/PDF document "Outage Coordination" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Outage Coordination
Process and New Equipment
1Slide2
Introduction
This presentation is intended to increase knowledge of outage coordination and NOMCR submittal processes
2Slide3
Objectives
At the completion of this course of instruction
you will:
Identify the ERCOT Outage Coordination timelines
Identify the timeline requirement for a maintenance level outage
Identify the maximum size of a group outage
Identify the correct process order for new equipment in the ERCOT system
3Slide4
Definitions
NOMCR – Network Operations Model Change Request
ResTran
–
RES
ource
Owned TRANsmission Equipment
4Slide5
Outage Coordination
Planned Transmission TimelineRequest for Approval*ERCOT must Approve or Reject*
More than 90 days
75 days
46–90 days
30 days
9–45 days
4 days
4–8 days
No later than 1800 hours 3 days
3 days
No later than 1800 hours 2 days
*Prior to Planned Start Date/Time
5Slide6
Outage Coordination
Planned Resource TimelineQSE Request for ApprovalERCOT Approval or RejectionThree days1800 hours, two days prior to start of proposed OutageFour to eight days
1800 hours, three days prior
to start of proposed Outage
Nine to 45 days
Five
Business days after submission. Outages are automatically accepted if not rejected at the end of the fifth Business Day following receipt of request.
Greater than 45 days
ERCOT must accept, but may discuss reliability and scheduling
to minimize cost.
6Slide7
Timelines for Reliability Resource Planned Outages(RMR and Black Start) Note: ERCOT may, at its discretion, relax the 30 day Notice requirement.Request for Approval
ERCOT Approval or RejectionNot less than 30 days
15 days before start of proposed Outage
More than 45 days
30 days before the start of proposed Outage
7
Outage Coordination
Planned Resource Timeline
7Slide8
Outage Coordination
Maintenance TimelineDefinition: Initiated manuallyto remove equipment fromservice to perform work on components than could be postponed briefly but is required to prevent potential forced outage and cannot be postponed until the next planned outage.
Level 1:
Applies to equipment which must be removed from service within 24 hours. (M1)
Level 2:
Identifies equipment which must be removed from service within 7 days. (M2)
Level 3:
Applies to equipment which must be removed from service within 30 days. (M3)
8Slide9
ResTran
Forms are available on
resquest
Email forms to
ResTranOutages@ercot.com
Different forms for Forced Outages
9Slide10
ResTran
- Planned or Maintenance
10Slide11
ResTran
- Planned or Maintenance
11Slide12
ResTran
- Forced Outages12Slide13
d
ResTran
- Forced Outages
13Slide14
ResTran
- Outage Form
14Slide15
ResTran
- Outage Form15Slide16
ALWAYS review the outages after they were submitted by ERCOT on your behalf to make sure that the outage does exactly what you want it to do when you want it to.
To update an outage email the most up-to-date form with the new updated information added.
ResTran
Outage Form
16Slide17
Outage Coordination
Approvals
Approved Outages can be withdrawn any time before it is completed.
Planned transmission outages are always studied.
Approved -> Done by coordinators
Accepted -> Automatic
17Slide18
Outage Coordination
AvailabilityShort Term: M-F 6AM-6PM, Sa-Su 6AM – 2PMRotating Shifts*Long Term: M-F 6AM-5PMUse OC Blast AccountsEmail: OPSOutageCoordination@ERCOT.comPhone: (512) 248 – 6841No Voicemail*18Slide19
New Equipment
Create plan for switching from old to
n
ew equipment
May require
p
seudo equipment
i.e. Breakers to switch between equipment…Submit a NOMCR for all new and pseudo equipment
19Slide20
New Equipment
Pseudo Equipment
Pseudo Breaker
Breaker
New Breaker
Old Breaker
20Slide21
NOMCRs
A
21Slide22
22
NOMCRsSlide23
NOMCRs
23Slide24
NOMCRs
24Slide25
NOMCRs
A
25Slide26
New Equipment Outages
After the NOMCR has been processed and the equipment has been added to the OS Database
Planned End Date is the Energization Date
NOMCR >> OS >> Model
26Slide27
**BONUS**
Extending an outage
New Planned End Date
Unlimited extensions
FR->FE || (PL,M1,M2,M3)->UE
Adding Requestor Notes
1000 Characters
Only once per group outage
The maximum Group Outage size is 30 pieces of equipment
27Slide28
**BONUS MIS**28Outage Approved/AcceptedOutage Rejected
Removed from MIS2 Hrs. After Actual End EnteredOutage WithdrawnPlanned End > 1 Yr. OldPlanned End > 1 Yr. Old
*All reports are automatically updated every hour on the hour
*When an outage is added to one report it is removed from the previous report
Or Outage Canceled
Outage Canceled
Outage Submitted
Rejected Transmission Outages
Withdrawal of Approved and Accepted Transmission Outages
Approved and Accepted Transmission Outages
Proposed Transmission OutagesSlide29
Questions
?
?
29Slide30
Questions
The last day to enter a Planned Transmission Outage is ________ before the Planned Start Date.
1 Day
3 Days
8
Days
45 Days
30Slide31
Questions
Planned Resource Outages must be accepted
when entered ______ before the
P
lanned Start Date.
>3 Days
>9 Days >30 Days
>45 Days
31Slide32
Questions
A level 2 maintenance outage (M2) means that the outaged equipment must be removed _______ to prevent a forced outage.
<7 Days
<30 Days
<7 Hours
<1 Hour
32Slide33
Questions
The maximum size of a group outage is _______.
10 pieces of equipment
Unlimited
30 pieces of equipment
2 megabytes
of equipment
33Slide34
Questions
What is the correct process order for new equipment in the ERCOT system?
NOMCR >> OS >> Model
NOMCR
>> Model >>
OS
OS
>> Model >> NOMCR
Model >> NOMCR
>>
OS
34