Outage Coordination Outage Coordination

Outage Coordination - PowerPoint Presentation

ellena-manuel
ellena-manuel . @ellena-manuel
Follow
417 views
Uploaded On 2016-11-27

Outage Coordination - PPT Presentation

Process and New Equipment 1 Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal processes 2 Objectives At the completion of this course ID: 493916

equipment outage planned days outage equipment days planned outages coordination nomcr start ercot transmission restran questions hours removed model

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Outage Coordination" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Outage Coordination

Process and New Equipment

1Slide2

Introduction

This presentation is intended to increase knowledge of outage coordination and NOMCR submittal processes

2Slide3

Objectives

At the completion of this course of instruction

you will:

Identify the ERCOT Outage Coordination timelines

Identify the timeline requirement for a maintenance level outage

Identify the maximum size of a group outage

Identify the correct process order for new equipment in the ERCOT system

3Slide4

Definitions

NOMCR – Network Operations Model Change Request

ResTran

RES

ource

Owned TRANsmission Equipment

4Slide5

Outage Coordination

Planned Transmission TimelineRequest for Approval*ERCOT must Approve or Reject*

More than 90 days

75 days

46–90 days

30 days

9–45 days

4 days

4–8 days

No later than 1800 hours 3 days

3 days

No later than 1800 hours 2 days

*Prior to Planned Start Date/Time

5Slide6

Outage Coordination

Planned Resource TimelineQSE Request for ApprovalERCOT Approval or RejectionThree days1800 hours, two days prior to start of proposed OutageFour to eight days

1800 hours, three days prior

to start of proposed Outage

Nine to 45 days

Five

Business days after submission. Outages are automatically accepted if not rejected at the end of the fifth Business Day following receipt of request.

Greater than 45 days

ERCOT must accept, but may discuss reliability and scheduling

to minimize cost.

6Slide7

Timelines for Reliability Resource Planned Outages(RMR and Black Start) Note: ERCOT may, at its discretion, relax the 30 day Notice requirement.Request for Approval

ERCOT Approval or RejectionNot less than 30 days

15 days before start of proposed Outage

More than 45 days

30 days before the start of proposed Outage

7

Outage Coordination

Planned Resource Timeline

7Slide8

Outage Coordination

Maintenance TimelineDefinition: Initiated manuallyto remove equipment fromservice to perform work on components than could be postponed briefly but is required to prevent potential forced outage and cannot be postponed until the next planned outage.

Level 1:

Applies to equipment which must be removed from service within 24 hours. (M1)

Level 2:

Identifies equipment which must be removed from service within 7 days. (M2)

Level 3:

Applies to equipment which must be removed from service within 30 days. (M3)

8Slide9

ResTran

Forms are available on

resquest

Email forms to

ResTranOutages@ercot.com

Different forms for Forced Outages

9Slide10

ResTran

- Planned or Maintenance

10Slide11

ResTran

- Planned or Maintenance

11Slide12

ResTran

- Forced Outages12Slide13

d

ResTran

- Forced Outages

13Slide14

ResTran

- Outage Form

14Slide15

ResTran

- Outage Form15Slide16

ALWAYS review the outages after they were submitted by ERCOT on your behalf to make sure that the outage does exactly what you want it to do when you want it to.

To update an outage email the most up-to-date form with the new updated information added.

ResTran

Outage Form

16Slide17

Outage Coordination

Approvals

Approved Outages can be withdrawn any time before it is completed.

Planned transmission outages are always studied.

Approved -> Done by coordinators

Accepted -> Automatic

17Slide18

Outage Coordination

AvailabilityShort Term: M-F 6AM-6PM, Sa-Su 6AM – 2PMRotating Shifts*Long Term: M-F 6AM-5PMUse OC Blast AccountsEmail: OPSOutageCoordination@ERCOT.comPhone: (512) 248 – 6841No Voicemail*18Slide19

New Equipment

Create plan for switching from old to

n

ew equipment

May require

p

seudo equipment

i.e. Breakers to switch between equipment…Submit a NOMCR for all new and pseudo equipment

19Slide20

New Equipment

Pseudo Equipment

Pseudo Breaker

Breaker

New Breaker

Old Breaker

20Slide21

NOMCRs

A

21Slide22

22

NOMCRsSlide23

NOMCRs

23Slide24

NOMCRs

24Slide25

NOMCRs

A

25Slide26

New Equipment Outages

After the NOMCR has been processed and the equipment has been added to the OS Database

Planned End Date is the Energization Date

NOMCR >> OS >> Model

26Slide27

**BONUS**

Extending an outage

New Planned End Date

Unlimited extensions

FR->FE || (PL,M1,M2,M3)->UE

Adding Requestor Notes

1000 Characters

Only once per group outage

The maximum Group Outage size is 30 pieces of equipment

27Slide28

**BONUS MIS**28Outage Approved/AcceptedOutage Rejected

Removed from MIS2 Hrs. After Actual End EnteredOutage WithdrawnPlanned End > 1 Yr. OldPlanned End > 1 Yr. Old

*All reports are automatically updated every hour on the hour

*When an outage is added to one report it is removed from the previous report

Or Outage Canceled

Outage Canceled

Outage Submitted

Rejected Transmission Outages

Withdrawal of Approved and Accepted Transmission Outages

Approved and Accepted Transmission Outages

Proposed Transmission OutagesSlide29

Questions

?

?

29Slide30

Questions

The last day to enter a Planned Transmission Outage is ________ before the Planned Start Date.

1 Day

3 Days

8

Days

45 Days

30Slide31

Questions

Planned Resource Outages must be accepted

when entered ______ before the

P

lanned Start Date.

>3 Days

>9 Days >30 Days

>45 Days

31Slide32

Questions

A level 2 maintenance outage (M2) means that the outaged equipment must be removed _______ to prevent a forced outage.

<7 Days

<30 Days

<7 Hours

<1 Hour

32Slide33

Questions

The maximum size of a group outage is _______.

10 pieces of equipment

Unlimited

30 pieces of equipment

2 megabytes

of equipment

33Slide34

Questions

What is the correct process order for new equipment in the ERCOT system?

NOMCR >> OS >> Model

NOMCR

>> Model >>

OS

OS

>> Model >> NOMCR

Model >> NOMCR

>>

OS

34