/
Outage Scheduler Outage Scheduler

Outage Scheduler - PowerPoint Presentation

test
test . @test
Follow
422 views
Uploaded On 2017-10-02

Outage Scheduler - PPT Presentation

Matt Carter amp Victor Vaughn Garland Power amp Light 2017 ERCOT Operator Training Seminar Learning Objectives Identify new features of the Outage Scheduler Application Describe how Outages ID: 592474

transmission outage planned resource outage transmission resource planned ercot outages scheduler amp days forced equipment service submitted types start

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Outage Scheduler" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Outage Scheduler

Matt Carter & Victor Vaughn

Garland Power & Light

2017 ERCOT Operator Training SeminarSlide2

Learning Objectives

Identify new features of the

Outage Scheduler ApplicationDescribe how Outages impact Market OperationsDemonstrate information required for submitting: Transmission Facility OutagesResource Outages

2Slide3

Outage Scheduler Worksheet

To meet assessment goals you are provided with an Outage Scheduler Worksheet.

Follow along and fill in the blanks or answer the questions to get your credit for this session.Hint: Look for bolded text!Make sure your name is clearly printed!3Slide4

What is the definition of an Outage?

The condition of a Transmission Facility or a portion of a Facility, Generation Resource or Load Resource that is

:part of the ERCOT Transmission Griddefined in the Network Operations Modelremoved from its normal serviceexcludes the operations of Transmission Facilities associated with the start-up and shutdown of Generation Resources

4Slide5

Additional important ERCOT Definitions

5

Transmission Facilities:Transmission Lines, Substations and associated Facilities operated at or above 60 kV.Transmission Elements - Part of a physical Transmission Facility that are:An Electrical Bus, Transmission Line, Transformer,Generator, Load, Breaker, Switch, Capacitor, Reactor, Phase Shifter, etc.Part of the ERCOT Transmission GridDefined in the ERCOT Network Operations Model.Slide6

Additional important ERCOT Definitions

6

ResourceThe term is used to refer to both a Generation Resource and a Load Resource. Generation ResourceA generator capable of providing energy or Ancillary Service to the ERCOT System and is registered with ERCOT as a Generation Resource. Load ResourceA Load capable of providing Ancillary Service to the ERCOT System and/or energy in the form of Demand response and registered with ERCOT as a Load Resource.Slide7

Resource & Transmission Facilities Example

7Slide8

What then is the Outage Scheduler?

The ERCOT Outage Scheduler is a web-based database and scheduling

application which allows Market Participants to create, submit, view and edit outage requests for:Transmission FacilitiesResources (both Generation & Load)The Outage Scheduler allows

ERCOT to study the impact of

multiple outage

requests

spanning varying time periods while meeting the

outage coordination

response times and goals

described in

the Protocols

8Slide9

Let’s Talk about the Different Types of Outages

The Outage Request Menu’s Look like this:

9TSP Create New Transmission Outage Menu

QSE Create New Resource Outage Menu

QSE Create New Transmission Outage Menu.

QSEs have all of the same Transmission Outage categories and rules as TSPs – no differencesSlide10

Outage Types – Planned Transmission Outages

10

Planned Transmission Outage - An Outage that is planned and scheduled in advance with ERCOT, other than a Maintenance Outage or Opportunity Outage. For Planned Transmission Outages, ERCOT will Approve or Reject the request in accordance with the following: Submittal (Prior to Planned Start)ERCOT ApprovalGreater than 90 days

75 days

Between 46 to 90 days

30 days

Between 9 to 45 days

4 days

Between 4 to 8 days

3 days

3 days

2 daysSlide11

Outage Types – Planned Non-Reliability Resource Outages

11

Planned Resource Outage – Any major Resource Facility Outage (other than a defined Maintenance Outage) that is Planned and Scheduled in AdvanceFor Planned Resource Outages, ERCOT will approve or reject the request in accordance with the following: Submittal(Prior to Planned Start)ERCOT

Approval

Greater than 45 days

Automatically Accepted.

Will notify Submitter

Within 5 Business Days of any Conflicts

Between 9 to 45 days

Automatically Accepted by end of 5

th

Business Day if not Approved or Rejected

Between 4 to 8 days

By 1800 3 days Prior

3 days

By 1800 2 days PriorSlide12

Outage Types – Transmission & Resource Maintenance Outages

12

An outage initiated manually to remove equipment from service to perform work on that is required to prevent a potential Forced Outage and cannot wait until the next Planned Outage. There are three levels of Maintenance Outages.Level 1: equipment must be removed from service within 24 hours Level 2: equipment must be removed from service within 7 days Level 3: equipment must be removed from service within 30 daysNote: For all 3 Levels – QSEs must Update their COP within 1 hour and notify ERCOT verbally.Slide13

Outage Types – Transmission & Resource Forced

13

Transmission Forced Outage - Initiated by protective relay (or manually, in response to an observation by personnel that the condition of equipment could lead to potential event) that poses a threat to people, equipment, or public safety.Resource Forced Outage - requires immediate removal, either through controlled or uncontrolled actions, of all or a portion of the capacity of the Resource from service through automated or manual means. TSPs & QSEs must:Verbally communicate the outage to ERCOT immediately.Submit into the Outage Scheduler as soon as Practicable.QSEs must update their COPSlide14

Outage Types – Opportunity Outage

14

Resource Opportunity Outage:May be accepted by ERCOT when a specific Resource experiences a Forced Outage and Resource had been previously Approved or Accepted for a Planned Outage during the next eight days

Transmission Opportunity Outage

May be approved by ERCOT when a specified Resource will be outaged

and

TSP has an outage “Received at ERCOT” for Transmission Elements associated with the specified Resource

Slide15

Outage Types – Remedial Switching Action

15

Remedial Switching Actions:Considered to be a type of Forced OutageSubmitted for real-time switching devices that will be opened to relieve or prevent an overload

condition

Must

start within three

days

Must have

a maximum restoration

time of

four

hours

Cannot

exceed 72 hours in duration.Slide16

Outage Types – Simple Outages

16

Simple Transmission Outage A Planned Outage or Maintenance Outage such that when the Transmission Element is removed from its normal service, the Outage does not cause:A topology change in the LMP calculation and Cannot cause any LMPs to change with or without the Transmission Element that is suffering the Outage. Maximum Restoration Time cannot exceed 1 Hour.Slide17

What Are the Two Types of Outage Extensions?

17

Unavoidable Extensions:Apply to Planned, Maintenance & Simple OutagesForced Extensions:Apply to Forced Outages OnlyFor both Types of Extensions:New Planned End may be submitted multiple times for up to two hours after the Planned EndNew Forced Outage required after Planned End time plus two hours

Supporting Information is Required in the Notes area.Slide18

So, What Processes use Outage Scheduler Data?

18

Because of Forced Outages and other unexpected events.Real-Time processes Do Not use the Outage Scheduler – Why?Slide19

Outage Type Review

19

As we can see the type and the date when the Outage was submitted does affect several of the models and applications which ERCOT uses to conduct business. Question time…What are some of the outages that can affect CRRs? (Planned, Forced, Maintenance, Remedial Switching & Simple)(What about an extension?)What types of outages affect Real-Time? (Unavoidable & Forced Extensions, Maintenance Level 1)

What about

the Day-Ahead

?

(Forced, Maintenance

,

Remedial

, Simple)Slide20

Outage Scheduler Enhancements Project

Fall 2016 – Spring 2017Slide21

Enhancement – Added Capability for QSEs to submit Transmission Facility Outages.

Created the ability for QSEs to submit and be responsible for Outage Coordination of the Transmission Facilities associated with the Resources which they operate.

Resource Entity-Owned Transmission Facilities shall meet the same timeline for submittal and outage reporting requirements as TSP Transmission Facilities for:21Planned OutagesForced OutagesMaintenance Levels 1, 2 & 3Remedial Switching Actions

Simple Outages

Opportunity OutagesSlide22

Enhancement – Added Capability for QSEs to submit Transmission Facility Outages. (

Con’t)

Due to the different ERCOT Approval, Acceptance and Rejections timelines between Resource and Transmission Facility requests, QSEs shall not be allowed to submit Group Outages containing Resource and Transmission Facilities.22Slide23

Enhancement – New Planned End

23

New Planned End:Appears after Actual Start has been entered.May be Revised multiple times for up to Two Hours past the Planned End.

After Planned End plus Two Hours, if the Outage needs to continue, a Forced Outage must be submittedSlide24

Enhancement – Outage History Records

24

HistoryOutage History will report the date and time, and Requestor Name of every action related to when an outage is:

Created

Submitted

Approved/Accepted or Rejected

Extended

Modified

Cancelled or Withdrawn

Completed (Actual End Submitted)

 

All Requestor Notes and related-ERCOT Reviewer Notes will be included. Slide25

Enhancement – Outage History Records (

Con’t)

25HistoryOutage History Retrieval Rules

Access via Outage Scheduler User Interface Only

TSPs may access all Outage History records

QSEs may access records for the Transmission and Resource facilities they operate.

Use Custom Filter to locate the desired

Detailed

Outage Request.

Files are downloaded in .

xlxs

FormatSlide26

Enhancement – Multiple Overlapping

Derates

26QSEs are now able to submit multiple, overlapping Resource Derates in multiple Outage Types (Planned, Forced and/or Maintenance)For Resource Derates, all ERCOT processes shall use: The Lowest HSL submitted, andThe LSL associated with the Lowest HSL.QSEs are solely responsible for the submission and accuracy of all Derate Outages. Slide27

Enhancement - Nature of Work, Reasons for Cancellation and Grouped Outages

The following were added to the Nature of Work types and Reasons for Cancellation as shown:

27Nature of WorkCancellationsBreaker/Repair ReplaceWeather ConditionsTelcom WorkMaterials UnavailableThird Party Request

Labor/Crew Unavailable

Emergency

Operations

Maximum number of Transmission Elements in a Grouped Outage is now 60 Pieces of EquipmentSlide28

Summary Screen Enhancements

28

28

Width of Outage Summary Screen reformats to fit Tablet, Laptop and large-screen monitors.

Select to Expand and Collapse Group Outages

View feature allows 25, 50, 100 or 200 Rows per page

TSPs have the ability to see:

All Transmission Outages

All Resource Outages

QSEs may see:

Only the Resource and Transmission Outages which they submitted.

Outage Summary is the only place a QSE can view them together.

Removes Completed and Cancelled Outages from the Summary View.

Remembers Desired settings between SessionsSlide29

Enhancement –

Custom Filter

Enhancements include:Searches may be submitted on Single or Multiple Criteria.Display Transmission and Resource Outages together.Return up to 7000 resultsAdded ability to Search by Station or Nature of Work only.Typing data into a search field narrows the selection choices.29TSP Custom Filter

QSE Custom FilterSlide30

Enhancement –

Custom Filter

At least one of the following selections is required:Outage IDGroup IDRequesting Company

Operating Company

Station

If Requesting Company or Operating Company is the

only

search criteria selected, an Effective From/To date range is

Required.

30

TSP Custom Filter

QSE Custom FilterSlide31

High Impact Outage Project

Fall 2017 – Spring 2018Slide32

High Impact

Outage-related Definitions

Transmission Element (Previously Shown) A physical Transmission Facility that is either an Electrical Bus, line, transformer, generator, Load, breaker, switch, capacitor, reactor, phase shifter, or other similar device that is part of the ERCOT Transmission Grid and defined in the ERCOT Network Operations Model. High Impact Transmission Element (HITE) A Transmission Element that may, in certain conditions, result in high congestion risk when taken out-of-serviceHigh Impact Outage (HIO) A Planned Outage that interrupts flow on a High Impact Transmission Element (HITE). 32Slide33

Which leads us to a new Outage Type!

Rescheduled

High Impact Outage An Approved Planned Transmission Outage with: One or more High Impact Transmission Elements (HITEs)Submitted greater than 90-days’ prior to the Planned StartAnd, subject to withdrawal of approval by ERCOTOnly ERCOT shall be able to convert a High Impact Outage into a Rescheduled Outage after discussion with the Requestor.Rescheduled Outage training will be conducted prior to implementation Fall 2017/Spring 2018

33Slide34

Outage Scheduler

Data Requirements

2017 ERCOT Operator Training SeminarSlide35

Outage Scheduler - Data Requirements

General Information is required for all Transmission & Resource Requests

35General Information is pre-populated from Digital CertificatePrimary and Secondary phone numbers may be changed by submitting a “Notice of Change of Information” form

Remembers

the

Name and Phone Number

entered from previous session

. These fields are required data.

Enter the Number

you would want an ERCOT Outage Coordinator or System Operator to contact you at

!

Requestor Name will be captured in External Web Services and Outage History ReportsSlide36

Outage Scheduler - Data Requirements

Transmission Outage Data Fields

36All Four Date/Time Fields Outage Analysis uses Planned Start & Planned End..Earliest Start & Latest End used for alternate evaluation only!

Emergency Restoration - Cannot be longer than the Outage Duration

Project Name

Not

a Required Field

Used by Requestor to reference ProjectsSlide37

Outage Scheduler - Data Requirements

Resource Outage Data Fields

37Outage Analysis uses Planned Start & Planned End..Earliest Start & Earliest End used for alternate evaluation only!Slide38

Outage Scheduler - Data Requirements

Transmission

& ResourceNatureofWork38

Nature of Work Pull-Down

Required Field

Pre-Populated with Generic Transmission or Resource types of work

TRANSMISSION OUTAGES

Associated

Equipment Outage

Breaker Maintenance

Breaker Repair/Replace

Line Maintenance

Line Rebuild/Upgrade

Relay Work

Repair Hot Spot

Repair/Replace Damaged Equipment

Replace Equipment

Switch Maintenance

Switch Repair/Replace

Telcom Work

Third Party Request

Transformer Maintenance

Transformer Repair/Replace

Transformer Testing

New Equipment Energization

Retirement of Old Equipment

Other

Unknown

 

RESOURCE OUTAGES

Black

Start Test

Boroscope

Combustion Inspection and Repair

Cooling Water Problems/Repairs

Exhaust Problems/Repairs

Feedwater Problems/Repairs

Fuel Limitation/Lack of Fuel Availability

Fuel Problems/Repairs

Gas Company Pipeline Work

Inlet Air Problems/Repairs

Lack of Steam Load Availability

Mothballed

Overhaul

Steam Turbine Limited/Unavailable

Tube Leak

Turbine/Generator Vibration/Repair

New Equipment Energization

Retirement of Old Equipment

Other

Unknown

 Slide39

Outage Scheduler - Data Requirements

39

Operating Company defaults to Digital CertificateTop down Hierarchy

Select

Station first to pre-populate lower fields

Select

additional equipment to create Group Outages

Higher

selections clear lower fields

Transmission Equipment

Definition

CB

Circuit Breaker

LN

Line

DSC

Disconnect

XF

Transformer

SC

Series Compensator

LD

Load

SVC (Capacitors & Reactors)

Static Var Compensation Devices

Resource Equipment

Definition

UN

Unit

LR

Load Resource

Equipment

Name

In Service

– Date equipment added to the Network Model

Out Service

– Date Equipment removed from the Network Model

Transmission & Resource - Selecting EquipmentSlide40

Outage Scheduler - Data Requirements

Transmission & Resource

– Actual Start Field40Actual StartEntry field not available until the Outage has been Approved or AcceptedMay

be edited for two hours

.

Actual End and New Planned End entry fields will not appear until after Actual Start has been submittedSlide41

Outage Scheduler - Data Requirements

Transmission & Resource

– Actual End Field41Actual End:Appears after Actual Start Submitted.Can

be edited For two hours

.

New

Planned End:

Appears

after Actual Start has been entered

.

May be Revised

multiple

times for up to Two Hours past the Planned End.

After Planned End plus Two Hours, if the Outage is to continue, a new Forced Outage must be submittedSlide42

Outage Scheduler - Data Requirements

Transmission & Resource

– Notes42Requestor NotesMust enter reason when using “Other” or “Unknown” for Nature of Work

Requestor should enter any supplemental information which will aid ERCOT during outage analysis (the more info the better

!)

RAP or

RAS Notes

(Note: SPS changing to “Remedial Action Scheme”)

Required

if disabling or impacting a Remedial Action Plan or Special Protection

System

Supporting Information

Explanation of how an

Outage

qualifies as a

Forced Outage

Required before the following can be designated as “Complete”

Forced Outages

Forced Extensions

Unavoidable Extensions

Remedial Switching ActionsSlide43

Scenario 1

43

B4B5B6

B1

B2

B3

CD02

SD01

L01

L02

L03

Line

04

S010

S020

S030

S040

C

200

S

100

CT02

ST01

XT02

XT01

MT02

MT01

CD03

C

300

CT03

MT03

C4

C5

C6

C

1

C2

C3

L11

L10

L08

S010

C020

C030

C040

There is a Planned Transmission Outage on Line 04.

During switching, line switch C020 binds up halfway open.

What’s the first thing you do?

How is this entered in the Outage Scheduler?

The Field Crew calls 20 minutes after the Planned End time and tells the Requestor that it will take another two hours for the repair. What does the Requestor do?Slide44

Scenario 2

44

B4B5B6

B1

B2

B3

CD02

SD01

L01

L02

L03

Line

04

S010

S020

S030

S040

C

200

S

100

CT02

ST01

XT02

XT01

MT02

MT01

CD03

C

300

CT03

MT03

C4

C5

C6

C

1

C2

C3

L11

L10

L08

S010

C020

C030

C040

All

Units

are On-Line.

An insulator on

switch SD01

fails, causing

a fault

in unit ST01 to trip

.

During the initial visual inspection, it is noted that there is a small amount of damage to switch CD02.

The Resource Entity decides to

Derate

CT02 by 20 MW for 3 days – until ST01 repairs can be completed.

What outages need to be submitted for Unit ST01 and who submits them?

What needs to be done for CT02?Slide45

Scenario 3

45

Your company is adding new equipment in a substation expansion. All the distribution load will be picked up in the field. The Transmission contractor is going to install a bypass around the station to keep the transmission interruptions to a minimum while building the substation.The email from ERCOT below shows your approved NOMCR.Slide46

Scenario 3

46

Equipment (1101_CS) out of service date 1/11/17 12:00 AMEquipment (DSW_8014) out of service date 1/11/17 12:00 AMEquipment (DSW_8027) out of service date 1/11/17 12:00 AMEquipment (SWIND_1) out of service date 1/11/17 12:00 AMYou go into the outage scheduler to extend the outage

as requested by the Transmission Contractor.

When you try to submit the request, you get the warnings shown in Red.

1

) What does this mean?

2

) How would you enter the extension?