Step IV Construction Step IV Construction

Step IV Construction - PowerPoint Presentation

celsa-spraggs
celsa-spraggs . @celsa-spraggs
Follow
383 views
Uploaded On 2016-03-12

Step IV Construction - PPT Presentation

North Side Walls and End Walls 2027 May 2015 Stephen Plate Brookhaven National Laboratory Anchoring the upper shield plate to the framework at the west end 2 Installing one of four Lmounting brackets to the side walls at the west end ID: 252531

west walls crossbars side walls west side crossbars step plates brackets installed drawings mezzanine plate north loads iew react

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Step IV Construction" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Step IV Construction

North Side Walls and End Walls

20-27 May 2015

Stephen Plate, Brookhaven National LaboratorySlide2

Anchoring the upper shield plate to the framework at the west end

2Slide3

Installing one of four L-mounting brackets to the side walls at the west end.

Brackets support the Virostek plates at each end and provide a continuous flux path into the side walls while

accomodating

tolerances.

3Slide4

West end,

lower wall plate

Adjustable cams react thrust loads from end walls

C

rossbar support brackets under mezzanine

Crossbars react north and south sides against each other to reduce tension loads on floor anchors

4Slide5

V

iew from northwest corner of mezzanine

5Slide6

V

iew from east mezzanine

Upper center section installed for fit-check only at this time

6Slide7

Installing first crossbar

transfer drill at assembly;

each of 7 crossbars is unique.

7Slide8

Present Status

east and west end walls were installed, then removed to give access for installation of the spectrometer waveguides as planned

all crossbars are now installed

yet to be installed are the draw wires for measuring deflection under magnetic forces

draw wire stanchions

8Slide9

Step V DesignSlide10

V

iewed from north side

(3) one-piece center plates

2 removable sections

for RF maintenance

10Slide11

Step IV leg spacing

Downstream

PRY expansion

11Slide12

Step V Status

12 detail drawings essentially complete, but will need:

positions of crossbars (J.

Tarrant input)access holes fro RF couplers1 detail drawing needs to be completed

6 assembly drawings need to be completed

assy

drawings will not hold up the fabrication

Steel plates from Japan arrive

Phila

., PA around 11 July

12