Service Across Multiple Transmission Systems Service Across Multiple Transmission Systems

Service Across Multiple Transmission Systems - PowerPoint Presentation

conchita-marotz
conchita-marotz . @conchita-marotz
Follow
409 views
Uploaded On 2017-11-16

Service Across Multiple Transmission Systems - PPT Presentation

This presentation shows the steps that a Customer must take on OASIS to establish and coordinate requests on multiple transmission systems The following slides show how to Submit a Coordinated Request CR ID: 605800

transmission status customer coordinated status transmission coordinated customer systems screen information multiple service duke request crs update change confirmed

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Service Across Multiple Transmission Sys..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Service Across Multiple Transmission Systems

This presentation shows the steps that a Customer must take on OASIS to establish and coordinate requests on multiple transmission systems.

The following slides show how to

Submit a Coordinated Request (CR)

Document the other requests in the Coordinated Group (CG)

Attest that all of the Coordinated Group information meets the NAESB requirements

Update the status of other CRs in the CG

Approve, Adjust or Withdraw the CRSlide2

Service Across Multiple Transmission Systems

A new Coordinated Request (CR)

Must

be Preconfirmed

Must set CG Status = PROPOSEDSlide3

Service Across Multiple Transmission Systems

After the CR is submitted, the TSR Detail screen will show:

The CG

Status

will display the “PROPOSED

” hyperlink

The CG Deadline will be the Queue Time + 24 hours.Slide4

Service Across Multiple Transmission Systems

Before the 24-hour deadline, the Customer must enter on OASIS the information about all of the Coordinated Requests and/or Reservations in the Coordinated Group (CG) that are made on other Transmission systems.

Click on the

“PROPOSED”

hyperlink in the TSR Detail screen to bring up the “Update Coordinated Group” screen.

Enter information on each of the other requests and/or reservations.

DO NOT ENTER information on the DEC CR (in example do not enter info on request #70424910).

For Each CR or reservation, enter the following information:

Transmission Provider, CR Disposition, CR Assignment Ref, CR Increment, CR TS Type.

A popup list of Assignment Refs is available for CRs or reservations that are on another transmission system supported by OATI. When available, much of the information is filled in when the Assignment Ref is selected.

Be sure to check that all required information is provided.Slide5

Service Across Multiple Transmission Systems

After

providing the information on all the requests and reservations in the Coordinated Group in the “Update Coordinated Group” screen, the Customer must

attest that all of the Coordinated Group information meets the NAESB requirements

.

If the attestation is not done by the CG Deadline, the status of the CR will be set to INVALID.

To begin this process, open the TSR Detail screen and click the “Customer Update” button at the top of the screen.Slide6

Service Across Multiple Transmission Systems

To

attest that all of the Coordinated Group information meets the NAESB requirements

Change the CG Status to “ATTESTED”

Click on the Submit Changes button at the top of the screenSlide7

Service Across Multiple Transmission Systems

The Customer must monitor the status of each Coordinated Request on other transmission systems and update the information in the “Update Coordinated Group” screen.

Click on the

“ATTESTED”

hyperlink in the TSR Detail screen to bring up the “Update Coordinated Group” screen

.

Set the (CR)

Disposition

Set the (CR) Disposition Time equal to the Date and Time the request status was changed.

Disposition

Time auto fills for CRs

on

another transmission system supported by

OATI.

TSR Status

(CR)

Disposition

CR_ACCEPTED

FULL

CR_COUNTEROFFER

PARTIAL

WITHDRAWN

prior to TP changing status

WITHDRAWN

Any other status

NONESlide8

Service Across Multiple Transmission Systems

Finalizing the Coordinated Request

The Customer may confirm a CR that has a status of CR_ACCEPTED or CR_COUNTEROFFER at any time. Once the Customer sets the status to CONFIRMED no further action will be available to modify capacity.

The Customer may

withdraw

a CR that has a status of

CR_COUNTEROFFER at any time. Once

the Customer sets the status to

WITHDARAWN

no further action will be available to modify capacity

.

The Customer may wait to finalize the status of the CR until all the CRs in the CG have been acted on by their respective Transmission Providers.Slide9

Service Across Multiple Transmission Systems

Finalizing the Coordinated Request

When all Transmission Providers have responded to the CRs and all (CR) Dispositions have been changed from PENDING in the “Update Coordinated Group” screen a Response deadline will be calculated and posted on the CR on the Duke system.

If any of all of the CRs in the CG were accepted in full as requested, the Customer is to change the status of the CR on the Duke system to CONFIRMED. If the status in not changed by the Response deadline, OASIS will change the status to CONFIRMED.

If any of the CRs in the CG were not accepted in full as requested, the Customer has the option to lower the capacity granted by Duke.

If Duke set the status to CR_ACCEPTED, the Customer may change the status to CONFIRMED, REBID or WITHDRAWN. All rebids to lower capacity will be approved by Duke.

If Duke set the status to CR_COUNTEROFFER, the Customer may change the status to CONFIRMED, REBID or WITHDRAWN. All rebids to lower capacity will be approved by Duke.

If the Customer fails to respond by the Response deadline OASIS will take the following actions:

Change the status to CONFIRMED for a CR with the status of CR_ACCEPTED

Change the status to RETRACTED for a CR with the status of CR_COUNTEROFFER