Download The PPT/PDF document "THE TRES AMIGAS SUPERSTATION" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
THE TRES AMIGAS SUPERSTATION
WORLD WIDE EMERGING DEVELOPMENT IN HVDC 2013
UNITING THE NATION’S ELECTRIC POWER GRID
Slide2Common Interconnected AC System Problems
Long Distance TransmissionLine lossesSystem Voltage Stability/LevelsReactive Power LoadingSteady state Transient Stability Subsynchronous Oscillations
Latency issues (ie Spinning Reserves)Inductive and Capacitive limitation factors
InterconnectionsUncontrolled Load flow problems and bottlenecksCongestion IssuesInter Area loop flowCascading BlackoutsOscillation Stability
Frequency control
Voltage Stability
Physical interactions between power systems
Diminishing Returns with large interconnected AC Systems
Slide3Common Interconnected AC System Problems
High Cost of InterconnectionsReliability Costs: NERC, RC, RelayingN-1 criteria often creates underutilization of transmission linesComplex coordinating arrangements (RTOs, IA, JOAs, etc.)Need for sophisticated and costly system impact studiesParticipation agreement complications with multiple impacted entities
Regional/Subregional perturbations/phenomena difficult and costly to analyze and manage Deterministic planning practices do not capture the true economic value of transmission additions/upgrades
Slide4China
Plans for Point to Point HVDC
Slide5“a pan-European transmission
network facilitating the integration
of
large-scale renewable
energy and the balancing
and transportation
of electricity, with the
aim of
improving the European market”.
Friends of the
Super Grid
Slide6“Sun
and wind: SEMCs have limitless wind and solar energy potential. The MSP, launched in November 2008, aims to install 20 Gigawatts (GW) of new generation capacity by 2020.”
MedGrid
– Opening New lines for Sustainable Electicity
Slide7Under Planning:
Colombia – Panama
600 MW – 400 kV
Under Planning:
Central - North
1000 MW – 500 kV
Under Planning:
Central - South
2000 MW – 500 kV
Under Planning:
Chile - Argentina
2000 MW – 500 kV
South American HVDC projects in operation, construction or planned
Under Planning
Manaus -
Roraima
–
Venezuela
600 MW – 400 kV
Under Planning:
B Monte Tapajos
2x 4000 MW 800 kV
Under Construction:
Rio Madeira
2x 3150 MW 600 kV
Under Construction:
Melo
500 MW
BtB
Under Planning:
Brazil – Uruguay
500 MW
BtB
In operation:
Itaipu
2x 3150 MW 600 kV
In
Oeperation
:
Garabi
2x 1000 MW
BtB
In
Oeperation
:
Rivera
70 MW
BtB
Slide8"
Supergrid" is the future electricity system that will enable Europe to undertake a once-off transition to sustainability.“The full significance of a switchable HVDC innovation has not yet been appreciated by policy makers or by the business community. It is clear that a network incorporating a HVDC grid with the redundancy and reliability of current AC grids is now a reality and that the limits of what is technologically possible have been greatly expanded.”
“HVDC technology will open markets, strengthen security of supply and create another global opportunity for European companies to export sustainable energy technology. The technology underpinning the
Supergrid will give competitive advantage to the companies involved with its specification and design. This type of integrated AC/DC grid will be a template for what will be needed in other global markets including the US and China.”
Friends of the Super Grid Quote:
Slide9Alstom
Grid HVDC MaxSine Technology
Voltage Sourced Converter (VSC) technology
Modular multi-level converter designControl of real and reactive power flow into AC gridsHarmonic free output voltage
Ideal for use on weak AC grids
+ V
- V
+ V
- V
= chain link module
VSC HVDC scheme
Slide10Folded Back-to-Back Convertor Layout
Provides for AC and DC HTS bus
interconnections
DC Bus Connections
A
C Bus Connections
Slide11First Phase Scope of Construction
Slide12Design
Slide13Products & Services
- How Will Customers Use TA Services?
Slide14Products & Services
- Operations Services
Tres
Amigas Operations can be mapped against a generic electricity market structure, illustrating TA Operations core functions – system operations, spot market operations and information services. Tres
Amigas will most likely engage an established
clearinghouse to support forward trading and clearing.
Slide15Products &
Services - Transmission
Transmission
service will be sold in blocks ranging from one to 20 years in duration, as well as on a seasonal, monthly, weekly, daily and hourly basis.
Three
distinct mechanisms will be used to sell transmission service:
Negotiated, long-term ‘Anchor Tenant Agreements’
Competitive ‘open seasons’, mostly for annual service, but also including an initial ‘Anchor Tenant Auction’ for terms up to 20
years.
Web-based real-time portal, for non-firm and shorter-term firm capacity, with a duration less than one year (e.g. monthly, weekly, daily, hourly
).
Additionally, the real-time portal will facilitate a secondary market for Tres Amigas customers to trade transmission capacity purchased previously
.
Anchor Tenant Agreements
Spot Sales
(via Portal)
FIRM SALES
NON-FIRM SALES
Up to
50% of firm capacity
remaining available firm capacity after Anchor Tenant Agreements
remaining
available firm capacity
after Anchor Tennant Agreements and Anchor Tennant Auction
Any available long-term firm capacity
Additional short-term firm capacity
All non-firm capacity
Secondary trading of previously purchased capacity
Open Season
AT Auction
Annual Auction
20 years
Annual
Monthly
Daily
Hourly
Slide16Startup:
research, regulatory and local filings, ROW, preliminary engineering, environmental, economics and business plan.
Startup
8M
Preconstruction
12M
Phase I
500 M
Preconstruction:
detailed engineering, vendor selection/contracts, product development, additional filings and detailed business plans.
Phase I:
construction & operations, East/West transmission node, including HVDC converters, buildings and business infrastructure, EMS Operations
Funding – Tres Amigas Merchant Transmission
Unlike traditional
transmission facilities, merchant transmission project owners
assume all market
risk
. Tres Amigas has been successful in receiving significant capital through investors and private placements.
Phase II – III
1.5B
Phase II-III:
construction
& operations, Texas node, additional HVDC converters, facilities, and business infrastructure
2013
2010
2012
2015
Concept
2M
2008
Slide17Tres Amigas SuperStation….
Uniting the Electric Grid