/
DEEP FOUNDATIONS (PILE FOUNDATION) DEEP FOUNDATIONS (PILE FOUNDATION)

DEEP FOUNDATIONS (PILE FOUNDATION) - PowerPoint Presentation

cozync
cozync . @cozync
Follow
347 views
Uploaded On 2020-08-28

DEEP FOUNDATIONS (PILE FOUNDATION) - PPT Presentation

FOR BRIDGES G S YADAV Professor Bridge 2 BASIC PARAMETERS Design discharge Design discharge for foundations and protection works Depth of scour Maximum depth of scour Depth of foundation ID: 807498

pile piles test load piles pile load test dia bearing min depth design scour capacity driven soil initial method

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "DEEP FOUNDATIONS (PILE FOUNDATION)" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

DEEP FOUNDATIONS

(PILE FOUNDATION)

FOR BRIDGES

G S YADAV

Professor

Bridge

2

Slide2

BASIC PARAMETERS

Design discharge

Design discharge for foundations and protection works

Depth of scour

Maximum depth of scour

Depth of foundation

(

1.33 times the maximum depth of scour )

Slide3

DESIGN DICHARGE

Five Methods :

From stream flow records( yearly peak discharges) available for the desired recurrence interval or more

Statistical analysis

Unit hydrograph drawn on basis of limited observations of rainfall and discharge

Synthetic unit hydrograph

From stage discharge relationships established from gauging of the stream

Slide4

DESIGN DISCHARGE FOR FOUNDATION

Design discharge for foundations , protection works and training works except free board , shall be shall be computed by increasing Q as below

Catchment Area(

Sqkm

)

Percentage Increase

Upto

500

30%

500

upto

5,000

30% to 20%

5000 to 25,000

20%

to 10%

More than 25,000

Less than 10% ( at the discretion of chief engineer)

Slide5

NORMAL DEPTH

OF

SCOUR (D)

In case of natural channels flowing in alluvial beds where width of waterway provided is not less than

Lacey’s

regime width

D = 0.473 (

Q

f

/ f)

1/3

Where

D is scour depth in meters

Q

f

is design discharge for foundation in cusecs

f is

L

acey’s

silt

factor

(

f = 1.76 √m

)

m is weighted mean diameter of the bed material

particles

in mm

Slide6

NORMAL DEPTH

OF SCOUR (D)

If width of waterway provided is less than

Lacey’s

regime width for Q ( not

Q

f

) or where it is narrow and deep as in incised rivers and has sandy bed , the normal depth of scour is given by

1/3

Where

q

f is the discharge intensity in cumec per meter width

 

Slide7

MAXIMUM DEPTH OF SCOUR

Normal depth of scour D is increased to obtain maximum depth of scour for design of foundations, protection works and training works :

Nature of river/ location

Depth of scour

In a straight reach

1.25D

At the moderate bend conditions e.g.

along apron of guide bund

1.5D

At a

s

evere bend1.75DAt a right angle bend or nose of pier2.0DIn severe swirls e.g. against mole head of a guide bund

2.5D to 2.75D

Slide8

‘D’

in CLAYEY BEDS

In clayey beds, wherever possible , maximum depth of scour shall be assessed from actual observations at site

Slide9

CLASSIFICATION OF PILES

BROAD CALSSIFICATION

DRIVEN (DISPLACEMENT PILES)

BORED (REPLACEMENT PILE)

ON THE BASIS OF MATERIAL

TIMBER

STEEL

PCC

RCC

PSC

COMPOSITE

Slide10

CLASSIFICATION OF PILES

METHOD OF CONSTRUCTION

DRIVEN PRECAST PILES

DRIVEN CAST IN SITU PILES

BORED PRECAST PILES

BORED CAST IN SITU

PILES

MODE OF LOAD

TRANSMISSION

END BEARING PILES

FRICTION PILES

FRICTION CUM END BEARING PILES

Slide11

CLASSIFICATION OF PILES

SECTIONAL AREA

CIRCULAR

SQUARE

TUBULAR

OCTAGONAL

H-SECTION

SIZE

MICRO (MINI) PILES (<150 mm)

SMALL DIAMETER PILE (>150 mm < 600 mm)

LARGE DIAMETER PILE (>600 mm)

Slide12

CLASSIFICATION OF PILES

INCLINATION

VERTICAL PILES

RAKER (BATTER PILES)

Slide13

END BEARING PILE

Slide14

FRICTION PILES

Slide15

Slide16

SELECTION OF TYPE OF PILE

Availability of Space : Driven Piles require large areas and head room since it needs larger and heavier driving rigs

Proximity to Structures : driving cause vibrations in ground which may cause damage to nearby structures

Reliability : Precast driven piles ensure good quality of material, uniform section of piles

Compaction of cohesion less soils affected if driven piles are used

Cast in situ piles can be formed to any desired length and no cutting of pile or addition to length required

Slide17

SOCKETTING IN ROCK

FOR THE END BEARING PILES

SOUND RELATIVELY HOMOGENOUS ROCK INCLUDING GRANITE AND GNEISS --

1

TO 2D

MODERATELY WEATHERED CLOSELY FORMED INCLUDING SCHIST & SLATE ----

2 TO 3D

SOFT ROCK ---

3

TO 4D

Slide18

SPACING OF PILES

FOR END BEARING PILES

GOVERNED BY

COSISTENCY

OF BEARING STRATA

NOT LESS THAN

2.5 D

FOR FRICTION PILES

SUFFICIENTLY APART TO AVOID OVERLAPPING ZONES

NOT LESS THAN

3

DMAX SPACING 4 D

Slide19

INSTALLATION OF PILEs

( BORED CAST in SITU)

Pile installation in stiff soil strata not requiring side stabilisation :

Wide range of piling rigs are now available. Type of rig to be used depends upon type of soil strata and depth of drilling

Power driven rotary augur drills are suitable for installing piles in clay soils

Piles can be installed from 300 mm

dia

to over 5000 mm

dia

and depths

upto

100 m

Slide20

INSTALLATION OF PILEs

( BORED CAST in SITU)

Pile installation in soil strata requiring side stabilisation :

One option could be to drive MS casing

upto

full depth.

Mud circulation method

Continuous Flight Augers method

Slide21

TREMIE CONCRETING

Slide22

LOAD CARRYING CAPACITY OF PILE

Ultimate load carrying capacity of a Pile may be assessed by :

(

i

)

Dynamic pile formula, using data obtained during driving of piles, or by

(ii) Static formula on the basis of soil test results, or by

(iii) Load Test ……only after 4 weeks of installation of pile

For Non cohesive soils

Hiley’s

Formula is more reliable than other formulae ( Appendix B of IS 2911

pt 1/sec1)Hiley’s Formula not reliable in cohesive soilsWhere scour is anticipated , resistance due to skin friction will be available only below scour level

Slide23

LOAD CARRYING CAPACITY OF PILE

When pile is installed through compressive fill or sensitive clay into underlying hard stratum, a downward drag down force is generated in the fill. This must be added to the load

The drag force can be roughly estimated as cohesion of the remolded clay multiplied by the surface area of pile shaft

Slide24

FACTORS INFLUENCING PILE CAPACITY

SURROUNDING SOIL

INSTALLATION TECHNIQUE

SPACING OF PILES

SYMMETRY OF THE GROUP

LOCATION OF PILE CAP

DRAINAGE

CONDITIONS IN SOIL

Slide25

(

Appendix B IS2911pt1/sec2

)

Slide26

Slide27

Slide28

(Appendix

B

IS2911pt1/sec2)

Slide29

Slide30

BEARING CAPACITY OF A PILE GROUP

MAY BE

EQUAL TO THE

BC OF SINGLE PILE X NO. OF PILES

LESS/MORE

THAN THE ABOVE

FRICTION PILES, CAST OR DRIVEN INTO PROGRESSIVELY STIFFER MATERIALS & END BEARING PILES – EQUAL

FRICTION PILES INSTALLED IN SOFT AND CLAYEY SOILS – LESS

DRIVEN PILES IN LOOSE SANDY SOILS – MORE DUE TO EFFECT OF COMPACTION

Slide31

BEARING CAPACITY OF A PILE

GROUP

(para 2.6 of well& pile foundation code)

STRATA

TYPE OF PILE

BC PF PILE GROUP

1. DENSE SAND NOT UNDERLAIN BY WEAK DEPOSITS

DRIVEN

NO. OF PILES X

SPC*

2. LOOSE SANDY

SOILS½ (NO. OF PILES X SPC*)3. SAND NOT UNDERLAIN BY WEAK DEPOSITSBORED⅔ (NO. OF PILES X SPC*)

*SPC

– SINGLE PILE CAPACITY

Slide32

PERMISIBLE TOLERANCE FOR PILES

ALIGNMENT CONTROL

VERTICAL PILES – DEVIATION OF 1.5%

RAKER PILES – DEVIATION OF 4%

SHIFT

FOR PILES LESS THAN OR EQUAL TO 600 MM DIA

NOT MORE THAN 75 MM OR D/4 WHICHEVER IS LESS

FOR MORE THAN 600 MM. DIA. PILES

75 MM OR D/10 WHICHEVER IS MORE

EXCESS DEVIATION BEYOND DESIGN LIMITS –PILE TO BE REPLACED OR SUPPLEMENTED BY ADDITIONAL PILES

Slide33

PILE LOAD

TEST

Two types of tests for each type of loading (

ie

vertical, lateral, pullout )

Initial test, &

Routine test

Slide34

PILE LOAD TESTING

(IS-2911 PART-IV)

Initial

Test

For small size projects ( total piles less than 1000) , a minimum of two tests.

For large projects ( piles more than 1000), a minimum of two tests for first 1000 piles and additional one test for every additional 1000 piles and part thereof.

Initial test piles should be installed by the same technique, same type of equipment as that proposed for working piles.

Purpose

To check safe load calculated by static or dynamic formulae

Arrive at safe

load

Slide35

PILE LOAD TESTING

(IS-2911 PART-IV)

Routine Test

On 0.5

percent of

total number piles subject to a minimum one test,

can be increased to 2% depending

on nature of strata.

Purpose

It is carried out on a working pile with a view to check whether pile is capable of taking the working load assigned to it

Detection of any unusual performance contrary to the finding of initial test.

Workmanship

Slide36

PILE LOAD TESTING METHODS

Maintained Load Method

: applicable for both initial and routine test

Cyclic Method

: this method is used in case of initial test to find out separately skin friction and point bearing load on single piles

CRP Method

: this method is used for initial test only

Slide37

MAINTAINED LOAD METHOD

Test should be carried out by applying a series of vertical downward incremental load, each increment being about 20 percent of safe estimated load on pile

Each stage of loading shall be maintained till the rate of movement of the pile top is not more than 0.2mm/h or until 2h have elapsed, whichever is earlier subject to a minimum of 1 h

The test load is maintained for 24 hours

Slide38

MAINTAINED LOAD METHOD

Vertical loading on single pile shall be continued till one of the following takes place :

(a)

In case of Initial Load Test:

Applied load reaches 2.5 times the safe estimated load; or

Max settlement of pile exceeds a value of 10 percent of pile diameter in case of uniform

dia

piles and 7.5 percent in case of bulb

dia

of under-reamed piles.

Slide39

MAINTAINED LOAD METHOD

In case of routine load test :

Applied load reaches 1.5 times the working load ; or

Max settlement of pile exceeds a value of

12 mm for piles

dia

up to and including 600mm and 18 mm or maximum of 2 percent of pile

dia

whichever is less for piles of

dia

more than 600 mm.

Slide40

MAINTAINED LOAD METHOD

Vertical loading on

group of piles

shall be continued till one of the following takes place

:

(a)

In case of initial load test:

Applied load reaches 2.5 times the safe estimated load ;or

Maximum settlement of pile exceeds a value of 40 mm

(b) In case of routine load test :

Applied load reaches the working load

Maximum settlement of pile exceeds a value of 25 mm

Slide41

SAFE LOAD-INITIAL

TEST

THE SAFE LOAD ON A SINGLE PILE WILL BE LEAST OF THE

FOLLOWING

(A) FOR PILES UPTO 600 MM DIA :

Two third of the final load at which total displacement attains a value of 12 mm

50 % of the final load at which the total

displacemnt

equals 10 % of the dia. Of pile for uniform

dia

piles and 7.5 percent of bulb

dia for under-reamed piles.

Slide42

SAFE LOAD-INITIAL TEST

(B)

FOR PILES UPTO 600 MM DIA

:

Two-thirds of the final load at which the

totakl

displacement attains a value of 18mm or maximum of 2 percent pile diameter whichever is less.

50 % of the final load at which the total

displacemnt

equals 10 % of the dia. Of pile for uniform

dia

piles and 7.5 percent of bulb dia for under-reamed piles.

Slide43

SAFE LOAD – INITIAL TEST

THE SAFE LOAD FOR GROUP OF PILES

FINAL LOAD AT WHICH TOTAL DISPLACEMENT IS 25 MM

TWO THIRD OF FINAL LOAD AT WHICH DISPLACEMENT IS 40 MM

Slide44

Selection of piles for Routine Test :

Abnormal variation in concrete consumption

Sudden drop in concrete level during construction of pile

Problems encountered during boring and

tremie

operation

Significant variation in depth of pile with respect to other adjoin piles and boring record

Slide45

The

routine test

shall be carried out for a test load of at least

1.5 times the working load

; the maximum settlement at the load being

not greater than 12 mm for piles up to 600 mm

dia

and

18 mm or 2 percent of pile

dia

whichlever less for piles of dia more than 600mm

Slide46

OVERLOADING OF PILES

10% of the pile capacity may be allowed on each pile

Max overloading on a group shall be restricted to 40% of the allowable load on a single pile

Shall not be allowed at initial design stage

Slide47

LOAD TEST – ROUTINE TEST

TEST LOAD WILL BE ATLEAST 1.5 TIMES THE WORKING LOAD

MAX. SETTLEMENT SHOULD NOT > 12 MM

FOR GROUP OF PILES MAX. SETTLEMENT SHOULD NOT > 25 MM

Slide48

STATIC LOAD

TEST ( Maintained Load Method)

Slide49

PILE LOAD TEST

(

KENTELEDGE ARRANGEMENT

)

Slide50

PILE LOAD TEST

(

WITH ANCHOR PILES)

Slide51

DEFECTS IN CAST IN SITU PILES

HONEY COMBING DUE TO INADEQUATE VIBRATIONS

SEGREGATION DUE TO IMPROPER CONCRETE PLACEMENT METHODS

WASHOUT OF CEMENT DUE TO GROUNDWATER FLOW

CRACKS IN PILE SHAFT DUE TO SHRINKAGE

INCLUSION OF FOREIGN MATERIAL

NECKING DUE TO COLLAPSE OF SIDE WALLS DURING WITHDRAWAL OF TEMPORARY CASING

Slide52

NECKING IN PILE

Slide53

NECKING IN PILE

Slide54

DESIGN OF PILES

Slide55

RELEVENT STANDARDS

Manual on the Design and Construction of well and pile Foundations issued by RDSO

IS 2911- Part I

Section I – Driven cast in situ piles

Section II- Bored cast in situ piles

Section III- Driven precast concrete piles

IS 2911- Part IV- Load test

Slide56

RELEVENT STANDARDS

Concrete Bridge code- For structural design

IRC- 78- For Road bridge foundations, can be referred for guidance

Slide57

STEPS OF DESIGN

From soil data, depth of scour – fix length of pile

Based on thumb rules, fix dia of pile

Calculate load carrying capacity of single pile using static formulae

Do rough design for selected group of piles. Spacing to be based on thumb rules

Check design for load carrying capacity, settlement, depth etc.

Revise design if required

Conduct load test to confirm capacity of pile

Slide58

THANK YOU

Slide59

IMP. CODAL PROVISIONS

DIA. OF PILE

Bridge Manual- > normally 1 m

IRC-78

Bored piles on land- min. 1 m

Bored pile in river bridge- min. 1.2 m

IS 2911- Part I, Section 2

Provisions are for max. dia of 2.5 m

For Railway bridges dia. Of 1 m to 1.5 m be normally adopted

Slide60

IMP. CODAL PROVISIONS

SPACING OF PILE

IRC-78

Friction- min. 3 D

End bearing- Can be reduced to clear distance= D that is c/c 2D

IS 2911- Part I, Section 2

End bearing- hard soil- Min. 2.5 D

End bearing- hard rock- Min. 2.0 D

Friction- Min 3.0 D

RDSO Manual

Friction – min. 3 D

End bearing- Min. 2.5 DMax. 4 DFor Railway bridges spacing of 2.5 D to 3.5D be normally adopted

Slide61

IMP. CODAL PROVISIONS

GROUP BEHAVIOR

IRC-78

End bearing- If spacing > 2.5 D, no reduction

Friction- If spacing > 3 D, no reduction

Check for block failure

Settlement of group/single pile given for different width of group/pile dia

IS 2911- Part I, Section 2

Bored piles- end bearing- No reduction

Other cases – descriptive guidelines given

RDSO Manual

Dense sand not underlying by weak soil – driven pile – No reductionLoose sand soil – 50% reductionSand not underlying by weak soil – bored- reduction 33%

Slide62

IMP. CODAL PROVISIONS

PILE CAP

IRC-78

Min. thickness 0.6 m or 1.5 times dia of pile, whichever is more

max offset of 150 mm beyond outer face

Pile to project 50 mm into pile cap

IS 2911- Part I, Section 2

Offset of 100-150 mm beyond outer face

Pile to project 50 mm into pile cap

Should be rigid enough

Can be designed by taking dispersion at 45 degrees both from substructure and pile upto centre line

RDSO ManualNIL

Slide63

IMP. CODAL PROVISIONS

CONCRETE AND STEEL

IRC-78

M 35, Min. cement 400 kg/m3, Max. W/C 0.4, slump 50mm (150-200 for tremie)

Min. long reinforcement 0.4%, links min. 8 mm @ 150 mm c/c.

Min cover 75 mm.

IS 2911- Part I, Section 2

M 20, Min. cement 400 kg/m3, 10% extra cement when under water, slump 100- 180 mm (150-180 for tremie)

Min. long reinforcement 0.4%, Min. spacing 100mm, links min 6 mm @ 150 mm c/c.

Min cover 40 mm.

RDSO Manual

NILCBC to be followed based on environment condition

Slide64

IMP. CODAL PROVISIONS

FOS

IRC-78

2.5 if derived from static formulae for soil. 5 for end bearing on rock and 10 for socket resistance.

IS 2911- Part I, Section 2

Appendix given for calculating strength with static formulae

RDSO Manual

3 if derived from static formulae.

2 if derived from load test

Slide65

LAYOUT

Accuracy of prime importance

Should always be cross checked by at least two independent surveys

Permanent theodolite stations with the base line on the bank will be established to mark reference points

Slide66

CAISSONS

In case where the velocity of water in the river is high making it difficult to construct either an island or cofferdam to construct a well, caisson type construction has been used.

The caisson is pre cast at the shore with the bottom which is generally provided with openings which are plugged, and toed to the required position by tugs and then plugs are removed to permit the caisson to reach the bottom of the ocean bed.

Sinking can also be by concreting in pockets

Slide67

Example of caisson foundation in India are -

Ganga bridge at Mokameh,

Brahmaputra bridge in Assam

Mahanadi Bridge at Cuttack

CAISSONS

Slide68

Well v/s Pile

Wells have a large cross sectional area and hence more bearing capacity of soil.

q=5.4 N

2

B

+ 16(100+N

2

)D

Well are hallow and most of the material is at periphery. This provides a large section modulus.

Useful in controlling deflection against high horizontal force

it is possible to sink a well through soil having boulders, logs of wood, whereas Piles can not be driven

Slide69

In case of wells, it is possible to visually examine the strata through which sinking is done and material on which it is finally resting, hence the bearing capacity of a well is certain. On other hand bearing capacity of pile is generally uncertain

Concreting in the staining of wells is done under dry conditions and the quality of concrete is much better than in case of cast in situ piles.

Well v/s Pile

Slide70

Size of well foundation cannot be reduced indefinitely and hence it uneconomical to use well foundation for very small loads, pile foundations are more suitable.

Well v/s Pile

Slide71

THANK YOU