Overarching Commissioning Plan Overarching Commissioning Plan

Overarching Commissioning Plan - PowerPoint Presentation

danika-pritchard
danika-pritchard . @danika-pritchard
Follow
355 views
Uploaded On 2019-11-07

Overarching Commissioning Plan - PPT Presentation

Overarching Commissioning Plan Ritendra Bhattacharya LCLSII Commissioning Workshop December 4 amp 5 2018 Outline Introduction Commissioning responsibility Commissioning readiness Precommissioning ID: 764092

amp commissioning months cold commissioning amp cold months workshop lcls 2018 dec pre check system readiness connected subsystem commissioning

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Overarching Commissioning Plan" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Overarching Commissioning Plan Ritendra Bhattacharya LCLS-II Commissioning Workshop December 4 & 5, 2018

Outline Introduction Commissioning responsibility Commissioning readinessPre-commissioningSequence of commissioningOverarching schedulePredecessor 2 LCLS-II Commissioning Workshop, Dec 4 & 5, 2018

3 Introduction LCLS-II Commissioning Workshop, Dec 4 & 5, 2018 Installation scope: Identifying activities and completion timelines in support of commissioning readiness for the cryoplant subsystems. Pre-commissioning: Dealing with mechanical and electrical check out and system cleanups Commissioning: Dealing with commissioning and performance of the following sub-systems Auxiliaries Helium compression 4.5 K Cold box 2 K Cold Box Operation: Dealing with operation of subsystems post handoff during commissioning of rest of the subsystem. Example, operation of rest of the cryoplant subsystems during commissioning of 2 K cold box.

4 Commissioning Responsibility for Cryoplant JLAB Engineering, Pre-Commissioning & Commissioning S upport JLAB Vendor Support SLAC Engineering , Pre-Commissioning & Commissioning SupportSLAC Installation Support SRR ERR SRR ERR System Readiness Review Equipment Readiness Review AuxiliariesCompressors4.5 K Cold Box2 K Cold Box LCLS-II Commissioning Workshop, Dec 4 & 5, 2018

5 Cryoplant Commissioning Readiness System Pressure Tested and Leak Tested Loop check Continuity (up-to Terminal block ) Circuit filled with Air or N2 Cold Compressor / Turbines Cartridges installed Automatic valves and safety valves installed Charcoal filling complete Accessibility ensured Pressure Safety System (pressure tests, relief valve/device test/check) Leak testsElectrical checkoutControl & Communication checkout Electric power (Lock out/tag out)Tower Cooling WaterHelium Gas contract/requisition Liquid Nitrogen contract/requisitionControl room establishedMeasure to safeguard Co-occupancy of CP2 Installation and CP1 Commissioning. Resources (JLab\SLAC\Vendor)ODH classification and detection, alarms establishedSafety reviewed & ensuredTooling\Consumable\SparesDocumentation / Procedures LCLS-II Commissioning Workshop, Dec 4 & 5, 2018 Commissioning Readiness: NOTE: *including General contractor’s and reassembly contractor’s scope of work

6 Pre-commissioning LCLS-II Commissioning Workshop, Dec 4 & 5, 2018 Piping and U-tubes properly connected with subsystem Vent/drain connected Safety valves properly connected Utility availability check Vacuum system with cold trap connected Lock out/tag out complete Power is connected Breakers have properly rated fuses and trip set points Electrical motor checkout Instrumentation signal loop checkup Instrument calibration check Valves (pneumatic & electric ) functionality check Control network and communication checkout Local and remote control system checkout Alarms properly activated Purge/Fill cycles* Adsorber cleanupHe filling/pressurization He Circulation / FlushingNOTE:*Longer activity for He Gas Tanks, LN2 Dewar cleanup and moisture removal

7 Idealized Sequencing of Subsystem CommissioningLCLS-II Commissioning Workshop, Dec 4 & 5, 2018 NOTE: Including subsystem interconnecting warm and cold piping as appropriate

8 Overarching Schedule – CP1 LCLS-II Commissioning Workshop, Dec 4 & 5, 2018 CP1 - In Summary: Pre-commissioning………..7 months Aux Commissioning……….3 months Helium Compression………4.5 months 4 K Cold Box………………..4 months 2 K Cold Box………………..2 months Total (with overlapping)……13.5 months

9 Overarching Schedule – CP2 LCLS-II Commissioning Workshop, Dec 4 & 5, 2018CP2 - In Summary: Pre-commissioning………..7 months Aux Commissioning……….1 months Helium Compression………4.5 months 4 K Cold Box………………..4 months 2 K Cold Box………………..2 months Total(with overlapping )……. 11.5 months

10 Installation contractor delivery sequence by subsystem LCLS-II Commissioning Workshop, Dec 4 & 5, 2018 We need to address the followingInstallation completion dates as schedule predecessor for Auxiliary commissioning Helium Compressor commissioning 4.5 K CB Commissioning 2.0 K CB Commissioning Date 1? Date 2? Date 3? Date 4?

11 THANK YOU FOR KIND ATTENTION LCLS-II Commissioning Workshop, Dec 4 & 5, 2018