Resource Integration Topics ERCOT Jay Teixeira October 28 2019 Quarterly Stability Assessment QSA Planning Guide 59 Next Deadline for QSA If a GINR is not included in QSA its Initial Synchronization date will be automatically delayed to the next quarter ID: 809698

nov resource ros qsa resource nov qsa ros stability quarterly integration 1end interconnection data generation meet day initial releases

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "Resource Integration Workshop" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Resource Integration Workshop

Resource Integration Topics

ERCOT

Jay Teixeira

October 28,

2019

Slide2

Quarterly Stability Assessment (QSA)

Planning Guide 5.9

Next Deadline for QSAIf a GINR is not included in QSA, its Initial Synchronization date will be automatically delayed to the next quarter

2

All-Inclusive Generation Resource Initial Synchronization DateLast Day for an IE to meet prerequisites as listed in paragraph (4) belowCompletion of Quarterly Stability AssessmentUpcoming January, February, MarchPrior August 1End of OctoberUpcoming April, May, JunePrior November 1End of JanuaryUpcoming July, August, SeptemberPrior February 1End of AprilUpcoming October, November, DecemberPrior May 1End of July

Slide3

Quarterly Stability Assessment (QSA)

Planning Guide

5.9, Quarterly Stability AssessmentIssue’s seen in the QSA that had May 1, 2018 deadline10 day comment period for FISNeeds to be complete before QSA deadlineTSPs need to plan for itDynamic data validation Dependent on FIS Stability study

Need to meet PG 6.9 15 to 30 days prior to QSA deadline

3

Slide4

Resource Integration and Ongoing Operations – Interconnection Services (RIOO-IS) – Releases

No new releases

4

Slide5

Active PGRR’s

PGRR071

- Update Interconnection Process Timetables to Align with NPRR926 – Goes to ROS on Nov. 7th for Impact Analysis.

NPRR973 – PRS Nov 13, PGRR074 – ROS Nov 7, NOGRR196 – ROS Nov 7, RRGRR022 – ROS Nov 7 –

Add Definitions for Generator Step-Up and Main Power Transformer.PGRR076 – Improvements to Generation Resource Interconnection or Change Request (GINR) Process, ROS Nov. 7.5

Slide6

Other Topics

6

Site Control clarification – Suzi McClellanRIOO-RS data export to document – Mike Juricek

Slide7

Other contact information

ResourceIntegrationDepartment@ercot.com

is distribution list for Resource Integration department7

Slide8

Questions?