Download The PPT/PDF document "Energy Company Obligation ECO2e" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Energy Company Obligation ECO2e
NORTH EAST ASSOCIATION FOR LOCAL AUTHORITY ENERGY OFFICERS
Denise Rogers16th June 2017
1
Slide2Energy Company Progress toward overall ECO2 Obligations.
ECO2 eligible measures
Potential Project process
Project Compliance.
Questions.
AGENDA
Slide3Energy company progress towards overall ECO2 obligations:
HHCRO
This chart shows energy company progress for all measures notified to the end of March 2017 and approved by the end of April 2017 as a percentage of ECO2. All surplus actions from ECO1 to ECO2 have been approved and are included in the chart
.
Slide4Energy Company progress towards overall ECO2 obligations:- CERO
This chart shows energy company progress for all measures notified to the end of March 2017 and approved by the end of April 2017 as a percentage of ECO2. All surplus actions from ECO1 to ECO2 have been approved and are included in the chart
.
Slide5Energy Company progress towards overall ECO2 obligations:- Provisional Solid Wall Minimum Requirement
This chart shows energy company progress for all measures notified to the end of March 2017 and approved by the end of April 2017 as a percentage of ECO2. All surplus actions from ECO1 to ECO2 have been approved and are included in the chart
.
Slide6ECO2t Which measures?
ECO2t
Measures Table can be found on the
ofgem
website;-https
://www.ofgem.gov.uk/system/files/docs/2017/05/eco2t_measures_table_-_
may_2017_v5.pdf
The ECO2t Measures Table provides information on eligible energy efficiency measures which suppliers can use to meet their obligations for measures installed from 1 April 2017 until 30 September2018. The table includes the following information for each listed measure:•measure category•measure type•eligibility under ECO2t obligations CERO and HHCRO•in-use factor•standard lifetime•relevant PAS annex•measure name: format for notification to Ofgem.
Additional information has also been provided for some measures. The list of measures is non-exhaustive.Please note that the measure types listed are those which are present in the deemed scores matrix. District heating systems have also been included, but these must be scored with SAP/RdSAP
.
Other
measures may qualify, subject to review by us on a case-by-case basis.
Slide7What measures?
Solid Wall insulation/External Wall insulation
…..
Slide8What measures?
Insulation
…..
Slide9What measures?
Heating
….
Slide10Potential Projects
Potential ECO project
Discussions
around project potential
Project, carbon and funding levels reviewed by Npower and enter the Npower pipeline
Approval from npower received, a
funding offer will be made
Finer details of project are drawn up and contract development begins.
Contracts signed, Pre start meetings & work
commences
.
Slide11All ECO Insulation measures must follow the contract for supporting evidence provided and meet the most
recent
criteria specified by
Ofgem
and the latest edition of PAS2030.
Mandatory
RequirementsStandards of installation: PAS certification and installation by a person of appropriate skill and experience –
From 1 June PAS2030:2017, including Pre-installation Building Inspection (PRIB)Deemed score input document including floor plan and photos as necessary
Land
reg
extract or equivalent to confirm the premises are not social housing *
DWP matched reference to confirm the occupier is a member of the Help to Heat Group *
Lower Super Output Area (LSOA) Post code checker for CERO Rural if applicable
Multiple premises such as tower blocks – Social landlord consent / fair processing and privacy
Installation in accordance with Building regulation i.e., British Board of
Agrément
Certificates (BBA) /
European
Technical Approval (ETA)
Appropriate Guarantees for all wall measures to support lifetime of measure
Declaration of conformity and completed installation
Insulation of SWI to include age of the building and the type of walls treated (i.e. brick or non-brick)
Percentage of measure installed (POMI) where <100 per cent – evidence to include reasons and photos
Percentage of Property Treated (POPT) required for score calculation - additional guide to follow
Data set to be completed in the validation spreadsheet (ISS)
Technical Monitoring to verify installation standards and compliance to ECO eligibility criteria
* Not applicable to CERO installations
Always mindful of the
Ofgem
rules
for compliant measures
!
Slide12Compliance, a
b
rief overview…..
PAS
2030:2017: Summary
Key
points:
Following changes since the launch of Green Deal the PAS2030:2017 standard is adapting to market feedback, and while the main goal is to still set out requirements for the installation of
Energy Efficiency Measures (EEM), more emphasis has been given to the design specification
, inspections and the Pre-installation building inspection.
1
. Design
Specification – The 2017 update provides that installers need to be satisfied that the information given on the system design is adequate before proceeding with install. Installers are encouraged to challenge the system designer or require further information if they feel it is required. The aim of this change is to give clarity to customers as to who is at fault should there be an issue with the EEM, whether it is the installer or manufacturer.
2. Inspections
- There is an increased requirement (levels to be determined) on the number of inspections that will take place on the installer at each stage of the process. This means that there is more emphasis on record keeping by installers around suitability of the EEM.
Slide13Compliance
PAS 2030:2017
: Summary
3
. Pre-installation Building Inspection (PRIBI)
This
is an enhanced requirement of the Pre-installation building survey and puts more emphasis on the building fabric and general suitability of a property to have the EEM.
Minimal requirements that a PIBI covers are specified per specific measure as well as general requirements around: •The suitability and completeness of the design specification; •The suitability and completeness of the installation method statement;
•Confirmation that the specified EEM can be safely and effectively installed at the designated location; •Potential for moisture build-up as a result of the installation;
•Confirmation of the adequacy of ventilation prior to and after installation;
•Potential instances of thermal bridging and planned actions for amelioration;
•Risk to functionality and/or safety of installed services;
•The status of pre-existing safety alarms and;
•The presence of protected species
.
Slide14Deemed
scores are fixed scores for each measure type that can be determined using three or
four
variables.
• To
determine the appropriate deemed score for a measure, installers must first select the
appropriate measure type. They must then identify the basic attributes of the property in which the measure has been installed. • All deemed scores accounting for all property attributes are stated within the Ofgem deemed scores matrix. • For insulation measures, these attributes are split into three main variables: - the type of property the
number of bedrooms in the property,and the main heating source of the property. • The percentage of measure installed (POMI) and percentage of property treated (POPT) must also be determined in order to calculate the correct score.
•
A
basic guide on how to read the scores is presented in the ‘User Guide’ tab of the Deemed Scores Matrix.
Deemed
Scores Guidance
Slide15Percentage
of measure installed (POMI) and percentage of property
treated
(
POPT) both need to be determined and notified for each ECO measure scored
using
a deemed score. However, only the percentage of property treated should be used to determine the score. The POMI of an ECO measure must be 100% unless there are reasonable groundsfor not doing so. The deemed scores assume that the measure type installed treats 100% of the property. For instance a cavity wall insulation (CWI) score will assume that all walls
of the property are cavity walls and all of them are treated. A gas boiler score assumes that the entire property will be heated by the gas boiler.
Percentage of measure installed
(POMI) and
percentage of property treated
(POPT)
Slide16This is the document that enables the customer and installer to sign for handover of the measure, and
make
a declaration against a range of energy company requirements. It meets the
Ofgem
requirements for:-
Handover to customer (can be signed by someone acting on behalf of the occupant /landlord as long as they are not the installer, supplier or any other party in the supply chain). The PAS2030:2014 declaration of conformity or PAS2030:2017 claim of conformity. The declaration of completed installation. POMI % and POPT % Records the reason why 100 per cent of a measure was not installed and/ or where 100% of the property has not been insulated for the deemed score. The declaration of conformity confirms the following points:- This declaration is completed per measure type
Handover should take place within 4 weeks of finishing work on each measure Handover date should agree with the completed cell in the validation spreadsheet or ISS That
relevant documents, instructions and warranties have been provided to the customer
Exception where multiple premises are owned by the same landlord, i.e., tower blocks or flats when handover of all measures installed of that type may have the same handover date and should be within 4 weeks of finishing work on the last measure:-
Accompanied
by a spread sheet listing all the properties in that one handover
The
variants for the measure type for deemed scores should be recorded on the accompanying s/sheet
Any
variations of per cent installed for measure / property should be recorded on the accompanying s/sheet
Declaration of Conformity and Completed Installation
Slide17Technical
Monitoring requirements
:
Technical
Monitoring at a 5% minimum level must be conducted on each measure type based on the
number
of notified measures during the quarter. The actual measures to be monitored are randomly selected by the Technical Monitoring Agent (TMA). The selected measures need to be representative (by at least 3%) of the actual PAS2030 accredited company that installed the measure during the quarter. Where the number of measures of a particular type or installed by a particular installer is less than 100 for a specific period, monitoring should be
conducted on at least one measure installed by each installer. The inspector must meet the competency requirements as outlined in the Ofgem guidance. Technical
Monitoring (post installation) needs to take place within a specific time frame based on
the
measure
notification deadline.
Monitoring
targets must be met by the end of each TM monitoring period
TMA’s
must notify npower directly in instances of non-access
TM questions split into 4 areas:
Score
monitoring
Technical
Monitoring – Core TM questions
Best
Practice (optional)
Health
& Safety Monitoring – Energy UK safety questions (optional)
57
ECO2 Technical Monitoring - Insulation
Slide18Thanks You & Questions