/
MDI towards technical design MDI towards technical design

MDI towards technical design - PowerPoint Presentation

genesantander
genesantander . @genesantander
Follow
342 views
Uploaded On 2020-06-17

MDI towards technical design - PPT Presentation

Lau Gatignon Very preliminary To trigger discussions QD0 quadrupoles Support tubes MACHINE DETECTOR INTERFACE Vacuum IP Feedback Beamcal Lumical Antisolenoid Stabilization prealignment ID: 780558

design qd0 stabilization integration qd0 design integration stabilization pre support finalize feedback solenoid detector full gerwig vacuum bds safety

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "MDI towards technical design" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

MDI towards technical design

Lau Gatignon

Slide2

Very preliminary !

To trigger discussions

Slide3

QD0 quadrupoles

Support

tubes

MACHINE DETECTOR INTERFACE

Vacuum

IP Feedback

Beamcal

+

Lumical

Anti-solenoid

+Stabilization +

prealignment

Plus others ………..

Slide4

CONTENTS

Introduction

QD0 MagnetStabilization

QD0 support & pre-isolation

Pre-alignment

IP-Feedback

Anti-solenoid

Instrumentation

Vacuum

Overall integration

SafetyBackgroundsOther issues

Slide5

R.Stapnes

@ ACE meeting 2 February 2011

Slide6

Slide7

Slide8

Slide9

Slide10

MDI MEMBERS

R.Appleby,

A.Apyan, B.Bartalesi,

M.Battaglia

,

E.Bravin

,

H.Burkhardt

, P.N.Burrows,

F.Butin, B.Dalena, K.Elsener

, A.Gaddi, M.Gastal, L.Gatignon

, H.Gerwig, C.Grefe, E.Gschwendtner, M.Guinchard, A.Hervé

, A.Jérémie, Th.Lefèvre, L.Linssen, H.Mainaud-Durand, S.Mallows,

M.Modena, J.Osborne

, Th.Otto, C.Perry

, F.Ramos,

J.Resta Lopez, A.Sailer, H.Schmickler

, D.Schulte, N.Siegrist, J.Snuverink, E.Solodko,

R.Tomas Garcia, D.Tommasini, R.Veness, J.Vollaire,

A.Vorozhtsov, V.Ziemann, F.Zimmermann

Slide11

QD0 Magnet

M.Modena

,

A.Vorozhtsov

,

A.Bartalesi

,

E.Solodko

et al

Slide12

QD0 Magnet

Construct and test short prototype

Gradient, field quality, vibration modes, radiation hardness, impact of external fields

Finalize design, construct and test full length models of QD0 and QF1

Gradient, field quality, stability

Design and build field measurement device for long and small apertures with required precision

Tests some prototype in beam line (ATF2, CERN-NA or other)

In collaboration with stabilization team

Slide13

SS

QD0

Stabilisation

A.Jeremie

et al (LAPP/Annecy)

Slide14

Stabilization

Finalize choice of sensors (relative and absolute) and actuators

Analyze vibrational modes of final QD0 magnet and optimize stabilization strategy accordingly

Design and validate design of stabilization foot

Finalize integration in support tube

Simulation and test in realistic environment of stabilization performance

Cooperation with other luminosity stabilization systems

including data communication with other systems

Stabilisation

for L* = 6 m solution

Slide15

QD0 Support and Pre-isolator

A.Gaddi

,

H.Gerwig

,

F.Ramos

et al

Slide16

QD0 support and pre-isolation

Finalize analysis and tests with pre-isolator prototypeBased on these results, finalize design of full-scale pre-isolator

Finalize design of QD0 support tubes, taking into account constraints from integration

Construct and test one pre-isolator + support tube assembly and validate performance

Combined test with stabilized QD0

Slide17

P

Pre-alignment (including QD0)

H.Mainaud

-Durand et al

Slide18

Pre-alignment

Execute agreed work packages with NIKHEF

Complete/update CDR chapter accordinglyTest and validate rigidity of CAM mover system and demonstrate compatibility with stabilization requirements

As a result make full simulation of RASNIK system with realistic light transport channels through detector

Validate stretched wire approach for 500 m length

Full design of stretched wire system, compatible with integration and push-pull constraints.

Slide19

IP-Feedback

Ph.Burrows

,

J.Resta

Lopez et al

Slide20

IP Feedback

Continue tests and design to optimize latencyOptimize feedback algorithms

One or two sides, sensitivity to background (using detector MC)

Continue full simulations, including other feedback and feed-forward systems and isolation + stabilization

Studies of radiation hardness and B-field tolerance

Final engineering, taking into account integration constraints

Solution for L*= 6 m

implementation of QD0

Slide21

Anti-solenoid

B.Dalena

,

A.Bartalesi

,

A.Sailer

,

A.Gaddi

,

H.Gerwig et al

Slide22

Anti-solenoid

Complete a realistic design

Confirm choice of super-conducting technology

Good main solenoid compensation

Take into account effect of permendur on field configuration

Minimize deformation of main solenoid field

Integration with detector layout and

Q

D0 support

Validate that luminosity performance is adequate

Coupling of anti-solenoid and main solenoid Protection of QD0 (permendur, permanent magnets)

Slide23

Instrumentation

In collaboration with other working groups, arrive at final design and integration of beam instrumentation relevant for the IP

This includes the instrumentation for the IP feedback, but also luminosity monitoring in the post-collision lineFollow-up of discussions related to polarization

Slide24

Vacuum in IR region

R.Veness

et al

Slide25

Vacuum

Final design of all vacuum systems involved, including specification of all vacuum tubes/tanks, valves and pumps

Calculation of static and dynamic vacuum pressures in BDS, IR and post-collision linesValidate that the impact on beam dynamics and luminosity is a

cceptable

Slide26

Integration

H.Gerwig

and many others

Slide27

Integration

Work out in more detail the L*=6 m backup solution

andcompare with L*=3.5 m (luminosity, acceptance,

stabilisation

,

etc

)

Follow

-up evolution of detector designs

For both detectors or eventual new detector designs In particular impact of changes close to beam

Together with BDS teams, finalize choice of L* Can one agree on a single L*, which one? If needed, is it possible to have two different L* ?

Work out solution with QD0 in the tunnel, first conceptually (1 year?), at a later stage also technically.

Compare with L* = 3.5 m.Design and construction of push-pull platforms Optimize time for push-pull operationDetailed integration with civil engineering and services

Slide28

Safety

Agree with safety and civil engineering on all general safety aspects in the surface and underground areas

Fire safety, smoke extraction, ventilation, RP,

escape routes, etcetera

Finalize RP simulations with final BDS and detector layouts

Are detectors self-shielding enough? Shielding cavern-garage, ...

RP implications (if any) of muon backgrounds from BDS

Evaluation of all accident scenarios. Requirements for MPS

Design shielding accordingly

Evaluate whether big shielding doors are necessary. Thickness?Cryogenic safety issues

Slide29

Backgrounds

Collaborate with BDS, Post-collision line and LCD to evaluate and minimize backgrounds from machine, dumps and IPEvaluate, together with BDS, the impact of

muons and their cleaning on the IR in terms of RP safety and backgroundsConfirm that

Beamcal

ad

Lumical

are sufficient to serve as masks against neutrons from the various dumps

Finalize integration of post-collision line in IR

Slide30

And everything else …….

Slide31

Other issues

Continue to coordinate between different working groups

Magnets, stabilization, post-collision line + dumps, BDS, LCD, CESEstablish link between detectors and CES group for specification of all services and their integration

Work towards full and more precise cost estimate

P

rovide relevant chapters in Project Preparation Plan

Prepare first version of Safety File

Slide32

Spare slides

Slide33

Topic

Main contributors

QD0 magnet

M.Modena

,

A.Bartalesi

,

E.Solodko

,

A.Vorozhtsov

, QD0 stabilization

A.Jérémie, G.Balik, B.Bolzon,

L.Brunetti B.Caron,G.Deleglise, L.PacquetQD0

support, pre-isolationA.Gaddi

, H.Gerwig,

F.Ramos

Pre-alignmentH.Mainaud

-DurandIP FeedbackP.N.Burrows, J.Resta

Lopez, C.PerryAnti-solenoidB.Dalena

, A.Bartalesi, M.Modena, H,Gerwig,

A.GaddiInstrumentationTh.Lefèvre, E.Bravin

VacuumR.VenessSpent beam matters

E.Gschwendtner,

A.ApyanOverall integration

H.Gerwig, A.Hervé, A.Gaddi, K.Elsener

, N.SiegristShieldingF,Butin,

H.GerwigSafetyJ.Vollaire,

S.MallowsCE and Services interfaceM.Gastal, J.Osborne

BackgroundsA.Sailer, B.Dalena,

H.BurkhardtOther topicsK.Elsener,

L.Linssen, M.Battaglia, D.Schulte

, J.Snuverink,R.Tomas Garcia,

D.Tommasini, V.Ziemann, F.Zimmermann

Slide34

Stabilization (2)

In particular (Annecy groups):

Collaboration modelContinue characterization of vibration environment (correlations)

Continued sensor studies, in particular capacitive gauges and chemical sensors

Continued actuator studies and control loop optimization

Calculations on vibration modes of QD0 and support structures and combine those with pre-isolator and feedback loops in overall

simulations

Contribute to integration with other IR equipment, supports, controls,

etc

(CERN responsibility)

Tolerance studies with respect to external magnetic fields and radiationConstruction of full prototype with test in real life (ATF2 or lab?)Liaison with MDI and stabilization working groups. Documentation