The national picture Homes needed The national picture Homes needed

The national picture Homes needed - PowerPoint Presentation

importedferrari
importedferrari . @importedferrari
Follow
345 views
Uploaded On 2020-06-23

The national picture Homes needed - PPT Presentation

Our ambitions o ver 5 years Modern methods of construction Innovation Village Innovation village Three things to test The modular methods Electric heating methods Smart homes and technologies ID: 784083

frame volumetric steel light volumetric frame light steel good homes heat flexibility heating suppliers planning start design methods modular

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "The national picture Homes needed" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Slide2

The national picture

Homes needed

Slide3

Our ambitions

o

ver 5 years

Slide4

Modern methods of construction

Slide5

Innovation Village

Slide6

Innovation village

Slide7

Slide8

Slide9

Three things to test

The modular methods

Electric heating methods

Smart homes and technologies

Slide10

Our selection process

Design flexibility

Affordability

Mortgageability

Build warranties

Insurability

Market analysis identified 12 potential suitable suppliers

8 of the 12 were shortlisted to interview and assessed

5 suppliers were selected for the project

Slide11

Our suppliers

Ilke

– volumetric light steel frame (good affordability

for

volumetric

)

Icarus –

panelised light steel frame (good

d

esign flexibility

, fewer constraints and logistical challenges than

volumetric

)

Xella

aerated

c

oncrete panels (good

d

esign

f

lexibility

, fewer constraints and logistical challenges than

volumetric

, new to residential UK market

)

Premier – volumetric light steel frame (good design flexibility for volumetric, experience of delivering)

Simply Modular – volumetric timber frame (good design flexibility, smaller modules for easier transportation)

Slide12

Ilke

– volumetric light steel frame

Slide13

Icarus – panelised light steel frame

Slide14

Xella

– aerated concrete panels

Slide15

Premier – volumetric light steel frame

Slide16

Simply Modular – volumetric timber frame

Slide17

Three heating systems

Communal borehole ground array with individual ground source heat pumps provided to each property

Enhanced fabric energy efficiency, highly insulated electric storage heaters and phase change store providing domestic hot water

PV, air source heat pump and phase change heat store providing domestic hot waterThe options will inform our heating system decisions for our future development programme, moving towards a low carbon heat future

Slide18

Slide19

CIBSEJournal

April 2018

Slide20

Smart homes

Slide21

Timeline so far

Project start

Planning submission

23

rd

October

Planning detail

20

th

November

Planning Committee

a

pproval 24

th

January

Groundworks and

i

nfrastructure

s

tart on site

Homes England grant approved

2017

2018

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

Slide22

What’s next…

Groundworks and infrastructure start on site

Superstructure start on site

Exhibition of the North

First homes occupied

Slide23

Slide24

Any questions?