/
EuCard-WP7-HFM 10 th  Collaboration Meeting EuCard-WP7-HFM 10 th  Collaboration Meeting

EuCard-WP7-HFM 10 th Collaboration Meeting - PowerPoint Presentation

joyousbudweiser
joyousbudweiser . @joyousbudweiser
Follow
342 views
Uploaded On 2020-06-30

EuCard-WP7-HFM 10 th Collaboration Meeting - PPT Presentation

Fresca2 Dipole construction status assembly and tooling JC Perez on behalf of Fresca2 collaboration team Outline Fresca 2 components delivery status Assembly procedure and tooling Traces fabrication ID: 790824

msc 2012 perez mdt 2012 msc mdt perez 18th coil september assembly shell coils structure pack yoke cern cool

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "EuCard-WP7-HFM 10 th Collaboration Meet..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

EuCard-WP7-HFM10th Collaboration Meeting

Fresca2 Dipole construction status, assembly and tooling

J.C Perez

on behalf of Fresca2 collaboration team

Slide2

OutlineFresca 2 components delivery statusAssembly procedure and tooling

Traces fabrication

Heat treatment furnace

Vacuum Impregnation systemNext stepsConclusion

September 18th 2012

J.C. Perez TE/MSC-MDT

2

Slide3

Components delivery statusPrice inquiry for the structure launched in September 2011

The order placed in November 2011 has been split between 3 European companies

Cold-mass to

Aratz (Spain)Coil-pack (& dummy coil) to

Boessenkool (Netherland)Axial compression system to Mectalent

(Finland)All components have been delivered and accepted

September 18th 2012

J.C. Perez TE/MSC-MDT

3

Slide4

Assembly procedureSeptember 18th 2012

Coil layer 1-2

Coil layer 3-4

Fiber glass cloth filler

J.C. Perez TE/MSC-MDT

4

Slide5

Gap impregnationSeptember 18th 2012

2 facing surfaces of the coils will be mold released

Gap between coils will be filled with 0.9 mm fiber glass cloth

Impregnation of the fiber glass using the coils as cavity

This will guarantee a perfect contact between the 2 coils

This technique will allow to separate the coils in case of failure of one coilTests performed at CERN polymer laboratory confirm the feasibility

J.C. Perez TE/MSC-MDT

5

Slide6

Coils assembly sequence September 18th 2012

Coil lifting tool

Coil rotation tooling

J.C. Perez TE/MSC-MDT

6

Slide7

Coil pack assemblySeptember 18th 2012

Horizontal pads

Coil-pack assembly lifting tool

Coil-pack assembly

Coil-pack rotating tooling

C

onceptual design of all lifting tools is ready and price offers received. The official order will be placed end of September. Delivery scheduled for November 2012.

J.C. Perez TE/MSC-MDT

7

Slide8

Shell and Yoke assemblySeptember 18th 2012

Sliding the aluminum shell

The 2 half yokes will be aligned with no gap in between

A CERN standard rotating device will be used to turn the magnet

J.C. Perez TE/MSC-MDT

8

Slide9

Real shell and yoke assembly (1/2)September 18th 2012

J.C. Perez TE/MSC-MDT

9

Slide10

Real shell and yoke assembly (2/2)September 18th 2012

½ yokes assembly

Instrumented Shell

Sliding the shell

Guiding system

Assembly completed

J.C. Perez TE/MSC-MDT

10

Slide11

Shell pre-loadingSeptember 18th 2012

Two bladders will be used to push the ½ yokes towards the shell inner radius to allow gap keys insertion

Standard hydraulic jacks can be used instead of bladders to perform this operation

Bladders have been produced @ CERN

J.C. Perez TE/MSC-MDT

11

Slide12

Sliding the coil pack in the structureSeptember 18th 2012

The assembled parts will be rotated to horizontal position

T

he coil-pack will be pushed into the yoke aperture

Pumping bladders & insertion of keys

J.C. Perez TE/MSC-MDT

12

Slide13

Pictures of the coil-packSeptember 18th 2012

J.C. Perez TE/MSC-MDT

13

Slide14

Axial compression systemSeptember 18th 2012

J.C. Perez TE/MSC-MDT

14

Slide15

Magnet in the cryostatSeptember 18th 2012

J.C. Perez TE/MSC-MDT

15

Slide16

Aluminium dummy coil assemblyThe first mechanical assembly will be performed using aluminum blocks replacing the real coils

This will qualify the support structure, the assembly and loading procedure and validate the FEM

6 stations will be placed on the shell mid-plane

and 4 at 45° (20 gauges). See detailed presentation from J.E. Muñoz Garcia

The aluminum dummy coils will be instrumented with

14 strain gauges stations measuring along azimuthal and longitudinal direction

Axial roads will be

instrumented (

longitudinal direction

) The

way to cool-down the structure to 77 K in LN2 is under investigation

September 18th 2012

J.C. Perez TE/MSC-MDT

16

Slide17

Mechanical tests @ 77 K

An existing cryostat will be used to cool-down the structure to

77 K

A dedicated structure has been designed to support the instrumented mechanical structure (delivery expected October 2012)

Shell, yokes, aluminium dummy coils and longitudinal rods will be equipped with temperature sensors

During cool-down the temperature gradient on different pieces will not exceed 20 K

A dedicated cooling control will be developed

September 18th 2012

J.C. Perez TE/MSC-MDT

17

Slide18

Coils instrumentation and protection

Each double pancake will be equipped with 2 traces

New traces have been designed and will be produced at CERN

Each coil layer will be protected by 2 independent quench-heater circuits

Voltages across the coil will be monitored thanks to 9

V

taps

per side

September 18th 2012

J.C. Perez TE/MSC-MDT

18

Slide19

Heat treatment furnace

The heat treatment furnace ordered to GERO will be commissioned at the contractor premises by end of September 2012

Delivery to CERN is scheduled in October 2012

September 18th 2012

J.C. Perez TE/MSC-MDT

19

Slide20

Vacuum impregnation systemThe acceptance tests for the new vacuum impregnation tank will be held in Spain in October 2012

The system will be installed in 927 laboratory and commissioned in November 2012

September 18th 2012

J.C. Perez TE/MSC-MDT

20

Slide21

Next stepsPre-load shell-yoke sub-assembly and check gauges

Coil pack assembly with pressure sensitive paper

Rotation of shell-yoke

Coil pack re-assembly and insertion in the shell-yokeBladder operationAxial loading operation

Cool-down to 77 K

September 18th 2012

J.C. Perez TE/MSC-MDT

21

Slide22

ConclusionsAll structure components have been delivered to CERNShell, rods and aluminium dummy coil are being instrumented

The shell has been slid around the yoke

First mechanical assembly using aluminium dummy coils planed in October 2012

The structure to support the magnet in the cryostat for cool-down using Ln will be delivered in November 2012

First cool-down of the structure to 77 K scheduled for end 2012The heat treatment furnace will be operational in October 2012

The vacuum impregnation tank will be operational November 2012First set of traces scheduled for December 2012

September 18th 2012

J.C. Perez TE/MSC-MDT

22

Slide23

Fresca2 Collaboration Team

CEA/

Saclay

:M. Durante, P. Manil, J.F. Millot

, J.M. Rifflet, F. Rondeaux

, CERN:P.

Ferracin

,

G. de

Rijk, E

. Fornassiere, J. Humbert, A. Milanese,

L.

Oberli

, M. Timmins, G.

Villiger

,

TE/MSC-MDT Section

September 18th 2012

Thanks for your attention

J.C. Perez TE/MSC-MDT

23