/
NERCA NERCA

NERCA - PowerPoint Presentation

karlyn-bohler
karlyn-bohler . @karlyn-bohler
Follow
383 views
Uploaded On 2017-08-29

NERCA - PPT Presentation

WEBINAR HOW LONG IS A ROOFING CONTRACTOR TO BE LIABLE FOR ROOF PERFORMANCE June 4 2015 Stephen M Phillips Hendrick Phillips Salzman amp Flatt PC 230 Peachtree Street Suite 2500 Atlanta GA 30303 ID: 583183

contract statute limitations warranty statute contract warranty limitations specifications performance contractor problematic nullum time tempus years state warranties roofing

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "NERCA" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

NERCA WEBINAR

HOW LONG IS A ROOFING CONTRACTOR TO BE LIABLE FOR ROOF PERFORMANCE?

June 4, 2015

Stephen M. Phillips

Hendrick, Phillips, Salzman & Flatt, P.C.

230 Peachtree Street, Suite 2500

Atlanta, GA 30303

(404) 522-1410

smp@hpsf-law.comSlide2

Hostile Playing Fields: Contractors Facing More and Longer Liability in Certain Arenas

Problematic Specifications, Warranties and Nullum TempusSlide3

Dealing With Problematic Specifications and Warranty Requirements

Normal Measure of Liability for Roof Contractor

Perform the work in a good and workmanlike mannerComply with the contract requirements, which includes all provisions in specifications

Ignore a provision in specifications at your peril

Subject to suit for applicable statutes of limitation and respose in your state

3Slide4

Theories of Roofing Contractor Liability

Roofing contractor could be liable for:

Breach of contractNegligence (tort)Breach of warranty

Negligent misrepresentation

East theory potentially has a different statute of limitations both with regard to length and start date.

4Slide5

Warranty – An Additional Remedy or an Exclusive Remedy?

Consider making your warranty the Owner’s sole

and exclusive remedy and your sole liability post-completion

Consider adding a dispute resolution provision in your contract and warranty setting a time period for a legal claim to be filed and establishing arbitration as the dispute resolution procedure

5Slide6

Shortening Statutes of Limitation and Arbitration

Parties can by contract shorten the statute of limitations in most states. A provision along these lines could be inserted in the construction contract:

Any legal claim against Roofing Contractor alleging breach of this contract or negligence by Roofing Contractor shall be resolved through arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association and must be initiated no later than ___ years after Roofing Contractor performed the roofing installation covered by this contract.

6Slide7

Statute of Limitations - Massachusetts

Contract – Mass. Gen. Laws Ann., ch

260 § 2Time: 6 years Begins to run: In commercial construction cases, after the breach of contract occurs, even if damages are unknown.

7Slide8

Statute of Limitations for Tort Claims and Repose - Massachusetts

Statute of Repose – Mass. Gen. Laws Ann., ch

260 § 2BThis statute applies only to claims based in tort or implied warranty. It does not apply to contract actions and does not apply to third party actions based upon an express indemnification agreement.

Private property – 3 years, running from date cause of action accrues. 6 year statute of repose from the earlier of (1) the opening of the improvement to use or (2) the substantial completion of the improvement and the taking of possession for occupancy by the owner.

8Slide9

Statute of Limitations - Massachusetts

Shortening – yes, as long as reasonable. One year contractual limitations period has been upheld.

9Slide10

Statute of Limitations - Connecticut

Contract - Conn. Gen. Stat. Ann. § 52-576

Time: 6 years (written or oral); 3 years (executory)A contract is executory when neither party has fully performed its contractual obligations, and is executed when one party has fully performed its contractual obligations.

Begins to run: From the date an injury is inflicted. For defective workmanship claims, this generally is the date of the completion of the work.

10Slide11

Statutes of Limitation and Repose

Connecticut

Shortening – yes, as long as reasonable. One year contractual limitations period has been upheld. It appears that, under Connecticut law, the parties may contractually provide for a reasonable limitation period for filing suit that is shorter than the applicable statute of limitations and that a one-year contractual limitations period is reasonable.

Gianetti

v. Greater Bridgeport Individual Practice

Ass'n

, 2005 WL 2078546, 3 (

Conn.Super.,2005

)

11Slide12

Statutes of Limitation and Repose

Connecticut

Conn

. Gen. Stat. Ann. §

38a

-290

No insurance company doing business in this state shall limit the time within which any suit shall be brought against it or any claim shall be submitted to arbitration on (1) a fidelity or surety bond to a period less than three years from the time when the loss insured against occurs; (2) a construction performance bond to a period less than three years from the date on which the principal last performed work under

the

contract;

(3) a construction payment bond to a period less than three years from the date on

which

the claimant last performed work or supplied material for which the claim is made; and (4) all other policies to a period less than one year from the time when the loss insured against occurs.

12Slide13

Statute of Limitations – New York

Contract - N.Y. Civ. Prac. L. & R. 213(2)

Time: 6 yearsBegins to run: Cause of action accrues, and statute of limitations begins to run, from time of breach.

Sunbeam Products, Inc. v. Wing

Shing

Products (BVI) Ltd.

, 311 B.R. 378 (2004). In construction cases, claims against contractors for defects in construction generally accrue upon substantial completion of physical work. On public works projects, a contractor may specify the completion date by giving appropriate notice to the state agency under Section 138-a of the New York State Finance Law.

13Slide14

Statute of Limitations – New York

Statute of Repose - None generally applicable. Statute of repose

for claims against architects/engineers, and for personal injuries arising out of exposure to toxic substances.14Slide15

Statute of Limitations – New York

Shortening – Yes. N.Y. Civ. Prac. L&R § 201 provides “An action, including one brought in the name or for the benefit of the state, must be commenced within the time specified in this article unless a different time is prescribed by law

or a shorter time is prescribed by written agreement.”

15Slide16

Statute of Limitations – New Jersey

Contract - N.J. Stat. Ann. 2A:14-1

Time: 6 yearsBegins to run: When a person knew or should have known he had a cause of action against the party to be sued.

16Slide17

Statute of Limitations – New Jersey

Statute of Repose - N.J. Stat. Ann. 

2A-14-1.1Time: 10 years

Begins to run: After the date of substantial completion of the structure.

Shortening – Yes. “Generally, contract provisions limiting the time parties may bring suit have been held to be enforceable, if reasonable.”

Mirra

v. Holland America Line

, 331

N.J.Super

. 86, 751

A.2d

138 (2000).

17Slide18

Statute of Limitations – Pennsylvania

Contract - 42 Pa. C.S.A. §

5525Time: 4 yearsBegins to run: From the date of the alleged breach of contract. For breach of construction contracts involving latent defects, from the date a person became aware, or through the exercise of reasonable diligence should have become aware, of the defect. In a case involving a leaky roof, one court held that the statute began to run after the leaks proved to be persistent, occurred in a variety of locations and repeated repair efforts proved futile. If a patent defect involved, the statute runs from the date of the breach of the contract.

18Slide19

Statute of Limitations – Pennsylvania

Statute of Repose - 42 Pa. C.S.A.

 5536Time: 12 years. 14 years if injury occurs between 10th to 12th year.

Begins to run; After the date of substantial completion of a project.

19Slide20

Statute of Limitations – Pennsylvania

Shortening – Yes. Permitted if reasonable. 42 Pa. C.S.A. § 5501(a) provides “An action, proceeding or appeal must be commenced within the time specified in or pursuant to this chapter unless, in the case of a civil action or proceeding, a different time is provided by this title or another statute

or a shorter time which is not manifestly unreasonable is prescribed by written agreement.”

20Slide21

Statute of Limitations – Pennsylvania

Repair Doctrine" -- In a 1991 case, the Superior Court of Pennsylvania adopted "the repair doctrine," which in effect suspends the running of the statute of limitations. In cases where (1) the defendant undertook continuous repair; (2) the defendant represented that the repairs would cure the defect; and (3) the plaintiff relied upon the representation that the repairs would cure the problem, the repair doctrine will preclude the defendant from asserting that the statute of limitations ran during the period the defendant was attempting the repairs.

Amodeo v. Ryan Homes, Inc.

, 595

A.2d

1232 (Pa. Super. 1991)

21Slide22

Statute of Limitations – Rhode Island

Contract – R.I. Gen. Laws §9-1-13

Time: 10 years.Begins to run when the plaintiff discovers, or with reasonable diligence should have discovered, the wrongful conduct of the defendant

22Slide23

Statute of Repose – Rhode Island

Statute of Repose – R.I. Gen. Laws §9-1-29

Time: 10 yearsBegins to run: After substantial completion of the improvement

23Slide24

Shortening Statute of Limitations – Rhode Island

Shortening – Not settled. In

Gilbane Building Co v. Ocean State Building & Wrecking, Inc., 748 A.2d 826 (R.I. 2000), the Supreme Court of Rhode Island suggested it would have enforced a one year statute of limitations contained in a

warranty;

however the question was moot because the action sounded in breach of the underlying contract, not breach of warranty.

24Slide25

Contractual Shortening of Statute of Limitations

Allowed –

Connecticut – performance and payment bond limitation cannot be less than 3 years Massachusetts

New Hampshire

New Jersey

New York

Pennsylvania

25Slide26

Contractual Shortening of Statute of Limitations

Not Allowed - Vermont

26Slide27

The Problem – Public Projects

Nullum Tempus Occurrit

Regi - “No Time Runs Against the King”State v. Lombardo Brothers Mason Contractors

2012 Decision of Connecticut Supreme Court

1992 – State of Connecticut hired design and construction management firms to build

a

law library at

U

Conn

1994 – Construction commences. Gilbane is Construction Manager

1996 – Construction completed

1996 – Water intrusion problems begin; contractors attempted repairs

2000 – State hires forensic engineers

State undertakes $15 million corrective work

27Slide28

Nullum Tempus– Public Projects

2008 - - States sues 28 contractors, designers, construction professionals seeking recover of $15 million

All 28 defendants seek dismissal of suit based on expiration of Connecticut’s 6 year contract statute of limitations and 7 year statute of repose

Trial court grants defendants’ motion for dismissal

State of Connecticut appeals. Argues that the State is immune for statutes of limitation and repose and all claims could be prosecuted regardless of passage of time based on

nullum

tempus.

Gilbane argued that, even

if

nullum

tempus

doctrine still existed, language in its contract with the State indicating that the statutory period of repose applicable to design work applied,

should

that the State had waived

nullum

tempus.

2012 – Connecticut Supreme Court rules says doctrine of

nullum

tempus

is

alive

and well and cannot be waived by contract; only the state legislature can eliminate

nullum

tempus

.

28Slide29

Nullum Tempus – Public Projects

States

differ in their approaches toward the nullum tempus doctrine.Only four states have completely abolished nullum

tempus

: New Jersey, South Carolina, West Virginia and Colorado

Some states apply

nullum

tempus

only to claims brought by the State itself and state agencies.

Other states apply the doctrine to political

subdivisions

and units of local government.

Some states distinguish whether the government unit bringing the suit is performing a

governmental

or proprietary function.

29Slide30

Nullum Tempus– Public Projects

New York – Nullum tempus

applies if the public entity is exercising uniquely sovereign rights and would not apply when the state agency is asserting ordinary property rightsPennsylvania - Claims by school districts against contractors, architects and others are not subject to a statute of limitations defense, but parties can waive

nullum

tempus

by contract

language. Case decision ruling that language

in the AIA A201 General

Conditions,

which defined when the statute of limitation would run for claims that arose before and after substantial

completion, was sufficient to show waiver of

Nullum tempus

30Slide31

Nullum Tempus– Public Projects

New Hampshire – nullum

tempus applies to the State, making it exempt for statute of limitationsNew Jersey – has abolished nullum

tempus

by

court decision

Massachusetts –

appears to have abolished

nullum

tempus

in most situations

31Slide32

The Problem – Public Projects

What Can Contractors Do About Nullum Tempus?

Be aware of possible applicationCheck if doctrine would apply to your project

Seek to include language in your contract that would indicate parties have waived the doctrine, possibly as indirect as language in AIA 201 relied upon by Pennsylvania court

Lobby for legislative reform

32Slide33

Potential Performance Bond Liability Extending to Warranty

When does the Performance Bond Obligation End?

Performance bonds pose a risk of personal liability exposure depending upon who signed the General Agreement of Indemnity with the bonding company/surety

33Slide34

Long-term Contractor Warranties and Performance Bonds

Milwaukee Board of School Directors v. Bitec

, Inc.2002 contract between Milwaukee Board of School Directors and Specialty Associates (roofing contractor) for new roof for $361,495

Performance bond contained no time limitation for suit to be initiated on bond

Contract called for contractor to correct defects for one year and contractor was required and issued a separate 5-year roof warranty

34Slide35

Long-term Contractor Warranties and Performance Bonds

Milwaukee Board of School Directors v. Bitec

, Inc.School District filed suit in 2007 against contractor, manufacturer and contractor’s surety

Surety contended its obligation was over when job was completed and 5 year warranty was separate obligation which the contractor satisfied by issuing the warranty

Wisconsin Court of Appeals ruled surety was liable for performance of warranty obligations

35Slide36

Long-term Contractor Warranties and Performance Bonds

Always be sure that the performance bond itself contains a time limitation stating when the suit on the bond must be initiated

36Slide37

Long-term Contractor Warranties and Performance Bonds

AIA A 311 Performance Bond states: “Any suit under this bond must be instituted before the expiration of two (2) years from the date on which final payment under the Contract falls due.”

AIA A 312 Performance Bond states: “Any proceeding, legal or equitable under this Bond…shall be instituted within two years after Contractor Default or within two years after the Contractor ceased working or within two years after the Surety refuses or fails to perform under this Bond, whichever comes first.

37Slide38

38

Problematic Specifications, Performance Specifications and Expansive WarrantiesSlide39

Hopedale Memorial Elementary School 07 54

00-2

1.05 Performance Requirements

39Slide40

Hopedale Memorial Elementary School 07 54 00-6

40Slide41

Montview Middle School

07 54 19-7

1.5 Warranty A. Deliver to the Owner upon completion of the work of this Section, a conditional warranty for the roofing system, agreeing to promptly repair the roofing as necessary to prevent penetration of water through it.

1. Warranty shall cover product quality, performance and workmanship for a period of 20 years.

a. Warranty shall include total roofing system, and membrane flashings.

b. Warranty shall provide coverage for maximum peak gust wind speed of 105 miles per hour.

2. Insulation warranty shall cover product quality, performance and workmanship including reuse for a period of 40 years.

3. Applicator shall supply Owner with a separate 5 year workmanship warranty. In the event any work related to roofing, flashing, or metal is found to be within the Applicator warranty term, defective or otherwise not in accordance with Contractor Documents, the Applicator shall repair that defect at no cost to Owner. Applicator’s warranty obligation shall run directly to Owner.

41Slide42

2.2 – System Description

B. Performance Requirements

1. Design roofing system for peak wind speed (3 second gust) of 110 miles per hour.42

Problematic Specifications and WarrantiesSlide43

Problematic Specifications and Warranties

General Recommendations

No silver bulletAct EARLY – give yourself as much time as you can to deal with the problem

Need to ACT – take steps to avoid being liable to comply with an unreasonable specification or problematic specification

43Slide44

Problematic Specifications and Warranties

General Recommendations

ACT EARLYLook at specifications as soon as they are available, not close to bid date

If you know an architect or consultant has an unreasonable specification, seek to cause that architect or consultant to modify his or her “standard” specification prior to issuance of next project

44Slide45

Problematic Specifications and Warranties

General Recommendations

ACT EARLYPromptly after problematic specification comes out, communicate the problem

For public projects, must act before you submit a bid

For private projects, must act before you sign a contract

45Slide46

Problematic Specifications and Warranties

General Recommendations

Approach in same way you should act upon an unreasonable contract provisions – try to get it changed or clarifiedMay need to walk away from some jobs

46Slide47

Problematic Specifications and Warranties

Take Affirmative Action – Early Actions

Alert designer, general contractor and/or owner regarding the problematic provisionBe well prepared to explain why the provision is unreasonable

Listen to what the architect or owner is trying to accomplish

47Slide48

Problematic Specifications and Warranties

Take Affirmative Action – Early Actions

Explain how the problematic provision may not meet the architect’s or owner’s objectiveWork with the architect and other parties to develop alternative language that is consistent with Owner’s legitimate needs and is reasonable

48Slide49

Unreasonable Warranty Language

Take Affirmative Language

Seek clarification that long-term warranty is to be manufacturer’s warrantyIf long-term specified warranty is inconsistent with manufacturer’s warranties, alert architect to the discrepancy

You will need either to get the specification or the warranty revised or you will have a breach of contract liability

49Slide50

Problematic Specifications

Be Especially Wary of Performance Specifications

Sometimes the prescribed materials do not satisfy the performance requirementNeed to go on record and obtain clarification or revision prior to executing a contract

50Slide51

Problematic Specifications

What to Do With Expansive Performance RequirementsPress the Architect or other design professional to do the design rather than delegating design to the contractor

Go on record to point out design omissions and discrepancies

51Slide52

Unreasonable Specifications and Warranty Requirements

Actions To Take – Private Jobs

Qualify your proposal to address the unreasonable specification provisionPossibly submit two prices to account for the additional risk and/or expense of an unreasonable specification

Disparity may get the Owner’s attention

52Slide53

Unreasonable Specifications and Warranty Requirements

Actions To Take – Public Jobs

Notify Architect of problem as soon as you see it is impossible to satisfy or unreasonable specificationInvolve manufacturer

Raise issue at pre-bid meeting

Request a pre-bid meeting

53Slide54

Problematic Specifications

Actions to TakeArrange to have manufacturer’s representative attend the pre-bid meeting

Insist that an addendum be issued

54Slide55

Problematic Specifications

Public ProjectsUse the pre-bid meeting to alert the architect and owner’s representatives to unreasonable or problematic specifications including inconsistencies between specifications and performance requirements or omissions in specifications (e.g. lack of provision for air barriers)

Follow-up pre-bid meeting with pre-bid inquiry to architect

55Slide56

Unreasonable Specifications and Warranty Requirements

Performance Bonds

Bonding companies do not want to knowingly have performance bond liability beyond two yearsUse bonding company’s position to aid in your negotiations

Be sure performance bond includes a time limitation

56Slide57

Problematic Specifications

Major Problems for Roofing Contractor: Wind Warranties and Liabilities

Huge disparity between manufacturers standard warranty coverage for wind (perhaps 55 mph) vs. code requirementsSeek to obtain an enhanced wind warranty from the manufacturer that is the same as your obligation in your contract

57Slide58

Problematic Specifications

Major Problems for Roofing Contractor: Wind Warranties and Liabilities

Press the designer to calculate required uplift pressure and to specify products and system that are represented to designer as meeting that uplift requirementBe certain that you are installing a complete system that meets the required uplift pressure

58Slide59

Problematic Specifications

Major Problems for Roofing Contractor: Wind Warranties and Liabilities

Pay particular attention to workmanship that affects wind uplift resistance (i.e. spacing of ribbons of adhesive, thickness of adhesive ribbons, number of spacing of fasteners, walking in boards, undulations in deck, securement of wood nailers, securement and quality of edge detail)

59Slide60

Potential Anti-Trust Ramifications

Just as two or more contractors cannot agree on pricing, contractors should not agree to act jointly regarding contract terms, including warranties

Each contractor should and needs to act individually when dealing with a general contractor, architect or owner in the market place

NERCA’s

role is to educate

60

Related Contents


Next Show more