Monday November 20 2017 300 PM Wakulla County BOCC Chambers WORKSHOP PURPOSE To provide an update to the Board on the following Community Needs Assessment Proposed citizen projects Input received from public meetings and comment period September 19 October 6 2017 ID: 680387

received project support wakulla project received wakulla support projects sewer jack springs alliance rudloe myip creek bay oyster panacea

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "RESTORE Act Multi Year Implem..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

RESTORE Act

Multi Year Implementation Plan: Status and Development Workshop

Monday

, November 20, 2017 @ 3:00 PM

Wakulla County BOCC ChambersSlide2

WORKSHOP PURPOSE

To provide an update to the Board on the following:

Community Needs Assessment

Proposed citizen projects

Input received from public meetings and comment period September 19 – October 6, 2017

Proposed MYIP Project

Draft MYIP without Projects

Decision Points

Slide3

Community Needs Assessment (CNA)

Phase One

: Staff completed an initial analysis of existing local documents and approved state plans. The list of documents and plan is included in the CNA appendices.

Phase Two

: Staff solicited input during public meetings and during the public comment period for gap analysis.

No public input was received.

Phase Three

: The final CNA is attachment number 3 of the Agenda.Slide4

Proposed Citizen Projects

…a snapshot of each project submittedSlide5

Project Title:

Septic Tank to Sewer and Retrofit Assistance/Connection to Sewer Assistance

Submitted by: Stan Derzypolski

Project Objective: Inspect failing septic systems, both residential and commercial, in the BMAP area for operational failure. Assist with implementation of retrofit to reduce nitrate load into aquifer, extend sewer system and assist with existing residential connection.

Estimated total cost: $500,000

Staff met with Mr. Derzypolski regarding his proposed project. He agreed that the project is very similar to another county project, however, believes that his project should add an educational component to it.Slide6

Submitted by: Maureen Mitchell, Panacea Waterfront

Project Objective: To purchase a head boat to be located at Rock Landing Dock that will create employment; to promote and operate the boat and bring visitors to the area.

Estimated Total Cost: $300,000

Project Title:

Panacea Head Boat Educational & Eco ToursSlide7

Project Title:

St. Marks Sewer Upgrade/WWTP

Submitted by: Bob Phillips

Project Objective: Make all of St Marks sewer system gravity drain to central pumping station – taking out all grinder pumps thereby stopping raw sewage from being washed into the watershed during storms and high water events.

Estimated Total Cost: $3 millionSlide8

Project Title:

A Partnership for Reviving Apalachee Bay Oyster Reefs

Submitted by: John Taylor * Wakulla Fishermen’s Association, Inc.

Project Objective: Provides shoreline restoration on hard-bottom Apalachee Bay oyster reefs to enhance commercial and recreational fisheries, including Wakulla’s commercial fishing heritage; strengthen tidal, storm surge and coastal erosion protection; improve water quality’ strengthen economic, social and environmental capital with a team approach including seafood-dependent workers.

Estimated Total Cost: $2.6 million

Staff met with Mr. Taylor and Ms. Dana Peck regarding the project. Staff will contact FWC to arrange a meeting with all parties involved to discuss the potential of FWC’s involvement and services available to facilitate the project. Slide9

Project Title:

St. Marks Fishing Pier

Submitted by: Zoe Mansfield

Project Objective: Provide recreational opportunities in the areas that are not available by allowing the public access to pier fishing and increase birding opportunities for views and photographers.

Estimated Total Cost: $290,000Slide10

Project Title:

St. Marks Boardwalk

Submitted by: Zoe Mansfield

Project Objective: Complete an existing phase of boardwalk and expand the existing trail to develop a trailhead. The project is shovel ready with plans and permits.

Estimated Total Cost: $900,000Slide11

Project Title:

ADA Compliant Kayak & Canoe Launch

Submitted by: Zoe Mansfield

Project Objective: To enhance recreational opportunities on the St Marks river by allowing for a low-impact access to coastal and river areas. It will be located next to San Marco de Apalachee Fort and will help boost tourism for canoeist, kayakers, stand up paddlers, fishermen, birding and environmental viewing.

Estimated Total Cost: $65,000Slide12

Project Title:

Convert Grinders to a Gravity Sewer System

Project submitted by: Zoe Mansfield

Project Objective: Replace grinders with gravity drain to reduce operational cost and malfunction of units. This would benefit ecological resources with restoration and protection of the natural resources ,ecosystems, fisheries, marine and wildlife habitats and help with public safety and welfare.

Estimated Total Cost: $5.5 million

Slide13

Input from Public Meetings and Comments

Public meeting and comment period was from

September 19 thru October 6, 2017Slide14

Comments Received:

Eighteen (18) Citizens provided an array of comments on array of projects and ideas, but did not submit project forms or supporting documentation. Comments were received on the following topics:

Dredging and Channel Markers – support, received from Robbie Lowther

Observation Tower near Panacea – support, received from Robbie Lowther and Jack Rudloe

Community Center Pool – support, Denise Spivey

Sewer Connection in older neighborhoods, specifically Ameliawood Subdivision – support, received from Denise Spivey

Extension of deadline for comments on proposed projects – support, received from Wakulla Springs Alliance

Installation of barriers to deter vehicle traffic on private land (Pine Island) – support, received from Bradley Hartman

Water quality study of Oyster Bay and Skipper Bay – support, received from Bradley Hartman

Sponsorship of a one time oyster relay from closed waters to open waters, support received by Bradley Hartman

Minimize/eliminate development along the shores of Skipper Bay – support, received by Bradley HartmanSlide15

Comments Received Regarding SEP Projects

Artificial Reefs

– support, received by Jack Rudloe, Wakulla Springs Alliance and Panacea Waterfront. Opposes, received by Bob Phillips.

Bayside Marina –

support, received by Matt Michalski. Oppose, received by Robbie Lowther, James Hennessy, Jack Rudloe, Wakulla Springs Alliance and Bob Phillips

Coastal Sewer (Shell Point, Spring Creek, Oyster Bay)

– oppose, received by Jack Rudloe and Wakulla Springs Alliance

Coastal Storm water Panacea

– oppose, received by Jack Rudloe and Wakulla Springs Alliance

Mashes Sands Park

– support beach renourishment and park improvement, received by Jack Rudloe, Wakulla Springs Alliance and Panacea Waterfront. Oppose dredging of sand flats, Jack Rudloe, Wakulla Springs Alliance and Panacea Waterfront.Slide16

Comments Received Regarding SEP Projects Continued…..

Otter Creek WWTP

– support, received from Jack Rudloe and Wakulla Springs Alliance.

Oyster Bed Restoration

– support, received from Jack Rudloe and Wakulla Springs Alliance.

Skipper Bay

– support, received from Bradley Hartman. Oppose, received from Jack Rudloe, Wakulla Springs Alliance and Bob Phillips.

Spring Creek

– support, received from Bradley Hartman. Oppose, received from James Hennessy, Jack Rudloe, Wakulla Springs Alliance and Bob Phillips.

Trail Head Oaks Property

– support, received from Panacea Waterfront. Oppose, received from Jack Rudloe, Wakulla Springs Alliance and Bob Phillips.

Wakulla Gardens septic to sewer

– support, received from Jack Rudloe and Wakulla Springs Alliance

WINCO St Marks

– support, received from Jack Rudloe and Wakulla Springs AllianceSlide17

SEP PROJECTS – RANKINGS COUNTY AND CITIZENS

Ranking

County Based on Scoring

Public Input Average

1

Wakulla Gardens Septic to Sewer

Coastal Storm water Panacea

2

Grieners Addition

Bayside Marina Purchase

3

Trail Head Oaks Property

Mashes Sands Park

4

Bayside Marina Purchase

Trail Head Oaks Property

5

Otter Creek WWTP

Artificial Reefs

6

Coastal Storm water (Panacea)

Coastal sewer (Shell Pt/Spring Creek/Oyster Bay

7

Coastal Sewer (Shell Pt/Spring Creek/Oyster Bay)

Wakulla Gardens

8

Oyster Bed Restoration

Skipper Bay

9

Artificial Reefs

Otter Creek WWTP

10

Skipper Bay

Grieners Addition

11

Spring Creek

Spring Creek

12

Mashes Sands Park

Oyster Bed Restoration

13

WINCO-St Marks

WINCO-St MarksSlide18

Proposed MYIP Project Selection Criteria

RESTORE Act Criteria: infrastructure projects benefitting the economy or ecological resources, including port infrastructure

Included in the Community Needs Assessment

Contributes to activities that are focused on water quality and marine life habitat within County Waters (e.g., reduces non-point pollution or provides/restores habitat), which was a recurring theme of needs at Public Meetings

Projects that cover an initial 3-5 year period (2018-2022) for sequencing and phasing purposes.

Projects partially funded from other State or Federal grants

Can be leveraged or matched with other State or Federal grants.

Necessary to continue a current septic-to-sewer project and sewer expansion.

Essential to water quality and marine life habitat within county waters.

County resources can support and maintain projects. Slide19

Proposed MYIP Projects 2018-2022

PROJECT: Wakulla Gardens/

Grieners

Addition Septic-to-Sewer

(SEP priority project #1, #2 and Citizen Ranking #7 and #10)

Activities:

Connection Fees for septic-to-sewer projects –

property agreements and connections

Otter Creek Retro fit –

Planning, design, procurement and construction

Lift Station, located on US98/Spring Creek (referred to as Jerry Moore Lift Station) –

Planning, design, procurement and construction

.

PROJECT: Artificial Reefs

(SEP priority project #9 and Citizen Ranking #5)

Activities:

Identification and analysis of viable reef areas

Permitting

ConstructionSlide20

RESTORE POT 1 FUNDING MATRIX

Spreadsheet will be presented at meeting. Slide21

Draft MYIP without Projects

Included with Agenda Package is draft MYIP w/o projects.

US Treasury has reviewed and advised we are on right track

Draft MYIP w/Projects and all attachments will be presented in January

Questions or changes to the draft?Slide22

DECISION POINTS and BOARD DIRECTION

Approve the Community Needs Assessment

Approve the proposed recommended MYIP Projects and Ranking

Approve the draft MYIP without projects

Other?Slide23

WAKULLA MYIP PLAN OF ACTION

January 8, 2018 BoCC MEETING

; Present draft MYIP with projects for board input (Task 3-4)

January 22, 2018 or February 5, 2018 BoCC MEETING

: Present FINAL MYIP for Board approval and to start the 45-day (Task 5) comment period.

April 2, 2018 BoCC MEETING

: Present summary of comments received and proposed responses for board approval/discussion and approval to submit FINAL MYIP to US Treasury (Task 5)Slide24

ANY QUESTIONS?