May 13, 2015 May 13, 2015

May 13, 2015 - PowerPoint Presentation

kittie-lecroy
kittie-lecroy . @kittie-lecroy
Follow
356 views
Uploaded On 2016-03-09

May 13, 2015 - PPT Presentation

Update to COPS RMSCOPS Workshop V Update IDR Meter Protocol Requirement Threshold 1 050515 Workshop V IDR Meter Required Threshold Workshop V was held on Tuesday 050515 following RMS ID: 249094

threshold idr meter workshop idr threshold workshop meter ercot required scott nprr draft load tdsp

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "May 13, 2015" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

May 13, 2015Update to COPS

RMS/COPS Workshop V Update: IDR Meter Protocol Requirement Threshold

1Slide2

05.05.15

Workshop VIDR Meter Required Threshold Workshop V was held on Tuesday 05/05/15 following RMS: 36 MPs were in attendance included CRs, TDSPs, PUCT and ERCOT Staff members

Workshop V Reviewed and Discussed

:

TDSP’s responses include in the attached TDSP’s IDR Meter Required Threshold Matrix to the following: What is company position on increasing IDR Required Threshold to 1.0 MW or 1.5 MW?How new threshold would be applied to qualifying ESI IDs?Will ESI IDs currently BUSIDRRQ profiles be grandfathered in?How would Customer(s) requesting IDR removal that no longer qualify under new threshold limits be processed by each TDSP?At what point would or does 4CP apply?

2Slide3

05.05.15

Workshop VSummary of significant discussion points:

Concerns

expressed on the elimination of the mandatory IDR Meter threshold

:Unknown impacts to TDSP’s 4CP Tariffs, Invoicing and Load ResponseImpact on ERCOT’s Load Forecasting processes, unless these loads are identified by a new profile assignmentNote that the Task Force participants indicated a desire that new profile codes not be introduced due to the cost impacts to their organizations resulting from IT development, testing and implementation of multiple new Load Profiles when that may not be the best use of budget dollars.  Establishing a separate threshold for the evaluation of NON-IDR metered premise and AMS metered premise.

Concern that language would be confusing to manage.Recognition that the majority of premises have AMS meters and the subset of non-IDR metered premises are very limitedUnderstanding and willingness

during IDR Required Threshold Workshop V to have any non-IDR with a demand up to 1.5 MW/MVA settled on a load profile Draft NPRR redlined during Workshop V:

3Slide4

05.05.15

Workshop VWorkshop V Action Items: K. Scott

: Work with ERCOT to ensure that draft NPRR redlined changes are ready for “Submittal to PRS” recommendation to RMS for RMS’ June 2

nd

meeting. Draft NPRR review web-conference scheduled with ERCOT and K. Scott on Monday, May 18, 2015 at 10:00 AM. K. Scott: Send Workshop V’s Final Draft NPRR and Final TDSP’s IDR Meter Threshold Matrix response documents to RMS, COPS, and Metering listservs for market review no later than Friday, May 22, 2015. K. Scott: Work with ERCOT to identify location on ERCOT.com in which IDR Meter Required Threshold Workshops I-V final documents can be posted for market participant’s future reference.

4Slide5

Questions?