Download The PPT/PDF document "The Republic of the Union of Myanmar" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
The Republic of the Union of MyanmarMinistry of Electric PowerElectricity Supply EnterpriseChin State Office
Priorities and Detailed Description of Electrification PlanFor Chin State
Dated -21.Oct.2015
Slide2Electrification Plan after discussion with local goverment We have submitted to the local government for implementation the the NEP with World Bank Loan that we have planned for priority to the villages lists within 2 miles from existing 11 kV lines. Then we have got the message to cooperate with township management committee. Therefore, we have to coordinate with township management committee and village lighting committee for electrification the villages within 2 miles from existing 11 kV lines.2
Slide3To be Constructed 11 kV Distribution Line 8 miles 400 V Distribution Line 2.5 miles 11/0.4 kV Distribution Transformer 4 NosElectricfication Plan for Village of Chin State
(Within 2 miles from Exiting 11 kV Distribution Line)Falam DistrictNo. of Village - 1 NosHousehold - 72Estimated Cost - 70.58(Mil kyats)
Mindat DistrictNo. of Village - 3 NosHousehold - 109Estimated Cost - 207.09(Mil kyats) Chin State No. of Village - 4 Nos
Household - 181Estimated Cost - 277.67
(Mil kyats
)
(To
Kalay
)
(
Cikhar
)
(
Tonzang
)
(
Teedim
)
(
Falam
)
(
Hakha
)
(
Rih
Khawdar
)
(Thanthlang)
(Rezuar)
(Matupi)
(Mindat)
(Paletwa)
(Sami)
(Kanpetlet)
(To Saw )
(To Kyauhtoo)
(To Gangaw)
(To Natchaung)
3
Slide4Detailed Electrification Plan for Chin State(Within 2 miles from Existing 11 kV Distribution Line)
No
Districk
No of House
House
hold
Popu
-
lation
To be constructed
Estimated
cost
(Mil
Kyates
)
Task
by regional
Cost for 11 kV Line
11/0.4 kV Transformer
400V
Lines
(Miles)
Estimated Cost
(Mil
Kyats)
mile
Material Cost
Transport
Cost
Constr-uction
Cost
Total
kVANoMaterialCostTrans-portCostConstru-ctionCostTotal1. Falam6472311247.827.662.658.08100111.350.800.3512.5070.58144.892Mindat1091094906143.4622.987.8174.24150329.42.41.0532.85207.091.567.335Total1731818018191.2830.6410.4232.32250440.753.21.445.35277.672.5112.225
4
Slide5Detailed Electrification Plan for Falam District(Within 2 miles from Existing 11 kV Distribution Line)
No
Township
Name of Village
To be Electrified
No of House
House
hold
Popu
-
lation
To be constructed
Estimated
cost
(Mil
Kyates
)
Task
by regional
Cost for 11 kV Line
11/0.4 kV Transformer
400V
Lines
(Miles)
Estimated Cost
(Mil
Kyats)
mile
Material
Cost
Transp-Ort CostConstr-uctionCostTotalkVANoMate-rialsCostTrans-portCostConstr-uctionCostTotal1. FalamLa thi6472311247.827.662.658.08100111.350.800.3512.5070.58144.89Total6472311247.827.662.658.08100111.350.800.3512.5070.58144.895
Slide6LegendLocation Map of Electrification Plan for Falam District(Within 2 miles from Existing 11 kV Distribution Line)
La thi Village11/0.4 kV(100
kVA)Parte VillageNgasit vaa mini Hydropower (500kVA)2 miles
Legend
Ngasit
vaa
mini Hydropower (
500kVA)
11 kV Line
11 kV Line (2 Mile)
11/0.4 kV TR (100 kVA)
6
Slide7Detailed Electrification Plan for Mindat District(Within 2 miles from Existing 11 kV Distribution Line)
No
Town
ship
Name of Village
To be Electrified
No of House
House
hold
Popu
lation
To be constructed
Estimated
cost
(Mil
Kyates
)
Task
by regional
Cost for 11 kV Line
11/0.4 kV Transformer
400V
Lines
(Miles)
Estimated Cost
(Mil
Kyats)
mile
Mater-
ials
CostTrans-portCostConstruc-tion CostTotalkVANoMaterialsCostTransportCostConstru-ctionCostTotal1. MindatKyawl Taw2424122247.827.662.658.085019.800.800.3510.9569.030.522.445Baw(3)2020125247.827.662.658.085019.800.800.3510.9569.030.522.445Pye6565243247.827.662.658.085019.800.800.3510.9569.030.5
22.445
Total
109
109
490
6
143.46
22.98
7.8
174.24
150
3
29.4
2.4
1.05
32.85
207.09
1.5
67.335
7
Slide8Pye
Village11/0.4 kV( 50 kVA)Kyaw Taw Village11/0.4 kV( 50kVA)Baw (3) Village11/0.4 kV( 50
kVA)2 miles2 miles2 milesLocation Map of Electrification Plan for Mindat District
(Within 2 miles from Existing 11 kV Distribution Line)
Legend
11 kV Line
11 kV Line 6 Miles
11/0.4 kV TR ; 150
kVA
8
Slide9The Statement of Fiscal Yearly Budget and Electrified Connection for Chin StateNoFiscal YearState/RegionCapital Budget for ESE (mil Kyats)State/Region
Capital Budget for DRD (mil Kyats)Electrified ConnectionON Grid
Off GridTotal CostFor 11 kV Line & 11/0.4 TRTotal
Cost
for 400 V LineTotal
Off Grid
Village
(
Nos
)
Consumer
(
Nos
)
Village
(
Nos
)
Consumer
(
Nos
)
1
2014-2015 Estimate (RE+BE)
147.51
62.05
209.561149.96
4
344686225
2
2015-2016 Estimate (RE+BE)275.59
98.65374.25430.40
5152
79
2139
32016-2017 Budget
Estimate (RE+BE)1970.53
509.772480.3
2977.2017
1334516
14886
Grand Total1699.03665.192364.234557.56261830663232509
Slide10Sr NoDescriptionQuantities
Transported Site1
11/0.4 kV ,100 kVA Transformer1 NoFalam District , PMO Office
2
10 meter Iron Pole
95
Nos
Falam
District , PMO Office
3
ACSR
95/15 mm-
sq
3863
kgs
Falam
District , PMO Office
4
11 kV Pin Insulator with
Sindle
285
Nos
Falam
District , PMO Office
5
11 kV Disc Insulator with
fiting
Clamp
60
Sets
Falam
District , PMO Office
6
Surge
Arrestor , Disconnection Switch , Fuse
1 Sets
Falam
District , PMO Office
7
Other Material
1 Lot
Falam District , PMO Office Main Materials List Transported to Falam District Office10
Slide11Sr NoDescriptionQuantities
Transported Site1
11/0.4 kV ,50 kVA Transformer3 NosMindat District , PMO Office
2
10 meter Iron Pole
285
Nos
Mindat
District , PMO Office
3
ACSR
95/15 mm-
sq
11590
kgs
Mindat
District , PMO Office
4
11 kV Pin Insulator with
Sindle
855
Nos
Mindat
District , PMO Office
5
11 kV Disc Insulator with
fiting
Clamp
174 Sets
Mindat
District , PMO Office
6
Surge
Arrestor , Disconnection Switch , Fuse
3
Sets
Mindat
District , PMO Office
7
Other Material
1 Lot
Mindat District , PMO Office Main Materials List Transported to Mindat District Office11
Slide12THANK YOU12