Paul Yockey Flight Administrator Retail Market Subcommittee 120915 Retail Market Subcommittee 120915 Flight 1015 Flight 1015 Summary InFlight Testing Flight 1015 is 100 complete ID: 485762

crs 2015 change flight 2015 crs flight change tasks testing total completed connectivity 2014 including tested existing subcommittee12 retail

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Flight Testing Update" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Flight Testing Update

Paul Yockey

Flight Administrator Retail Market Subcommittee12/09/15Slide2

Retail Market Subcommittee

12/09/15

Flight 1015

Flight

1015

Summary

In-Flight Testing:

Flight 1015 is 100% complete

6 New CRs tested (Including 1 additional DUNS and 1 PUCT Option 2)

Existing CRs: 5 CRs added a new territory

1,436 tasks have been completed including connectivity

Adhoc Period Testing:

4 CR tested for Change of Service Provider

1 CR tested for Bank Change

7 CRs tested connectivity with all partners due to system changes

Adhoc Period: 655 total tasks have been completed including connectivity

TDSP Testing:

1 TDSP tested connectivity due to minor changes to Gateway (Not included in Adhoc Period total tasks.)Slide3

Retail Market Subcommittee

12/09/15

2015 Flight Summary

2015 Summary

12 New CRs (Including 4 additional DUNS) completed testing with a total of 70 TDSP territories.

33 Existing CRs

(

13

Change of Service Provider,

4

Bank Change

, 8 Added a total of 14 Territories and 8 Connectivity for System Change)

completed

testing

22 of the Existing CRs used the newly instated Adhoc Period for their testing.

1 TDSP tested minor changes to Gateway (Connectivity only)

4472 Total Tasks CompletedSlide4

Retail Market Subcommittee

12/09/15

2015 Flight Comparison

2015/2014 Comparison with 2015 New Script Pack

2015 - 12 New CRs (Including 4 additional

DUNS using Round Robin)

2014 - 21 New CRs (Including 14 additional

DUNS using Round Robin)

2015

- 33 Existing CRs

(

13

Change of Service Provider,

4

Bank Change

, 8 Added a total of 14 Territories and 8 Connectivity for System Change)

2014

-

36 Existing CRs (14 Change of Service Providers, 7 Bank Change, 15 Added a total of 16 Territories)

2015 - 4472 Total Tasks Completed

2014

-

8954 Total Tasks Completed

2015 - Average

Tasks per CR = 99.38

2014

-

Average Tasks per CR = 157.08

2015

-

11 Days of In Flight Testing

2014

-

33 Days of In Flight Testing

2015

-

36.74% reduction of average tasks per CR

2015 - 66.67

% reduction of In Flight Test DaysSlide5

Retail Market Subcommittee

12/09/15

Questions?