Download The PPT/PDF document "PLAN - LS2 Activities BE-ICS 2016 Stat..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
PLAN - LS2 Activities BE-ICS 2016 Status & Action Plan
1
15 January 2016E. Sanchez-Corral
Edms:
1572767
Slide2Outline
LS2 Plan Life-cycle and deadlines
BE-ICS Status ActivitiesContributionsAction Plan for Resources AllocationPLAN Tool & SupportReporting toolsImprovements, support requestsTraining sessions 2
Slide3LS2 Plan Life-cycle – Version 1After deadline 21/11
Not possible to enter new activities before the next exercise (V2 : 2S2016)
But found out that we can still create new Activities and then ask LS2 Coordinators (K. Foraz) to SUBMMIT Activities to PRIORITIZATION321/11
- Not
able to assess the resources availability before the
prioritization
stage is
completed
-
Can register Resources details
for:
Activities
G
roup Contributions requests
Can request
for Contributions from other groups -> Other groups can still request us for a Contribution (-> number of resquests received has increased !)
All
contributions should be estimated and validated
Slide4BE-ICS LS2 Activities - Status
4
LS2BE-ICS08-01-2016GS-ASE16-12-2015EN-ICE2015Activites14585
60
Contribution
resquests
137
58
? (~80)
Contributions requests made by BE-ICS to
other
groups= 191
To validate by BE-ICS before 30/04
To be validated by other groups or sections within BE-ICS before 30/04
Slide5GS-ASE LS2 Activities 5
Section
Domain of activityNumber of Activities
Contributions
made to other groups
CSE – P.
Ninin
- New Personnel Protection
sys:
MEDICIS (2016)
SPS (LS2)
PPS Evolutions
2016:
PS:
ADT, ISOLDE
LS2
PS: LN4 connection
LHC: replace
obsolete access control,
new access point PZ66, temp PA
LHCb
7
EN-EL: control cabling, power supply, optical
fibre
EN-MED: mechanical doors, grids
EN-STI,
IT-CS
EIS
equipment groups EN, TE, BE: power converters, beam stoppers, magnets, RF, AUG
ASE-AS: BIW
HSE: inspections
AC- R. Nunes
ZORA Personnel Protection Systems (PPS) Maintenance (YETS)
11
Similar to CSE
AS – S. Grau
Safety Alarms Systems
67
Slide6BE-ICS LS2 Resources Allocation Action Plan
6
30/01 to 30/04We have to detail the resources required for BE-ICS activities and contributions requested from other groupshttps://plan.cern.ch/app/plan/1/dashboardFor most of the GS-ASE activities the resources required already declared during Initialization Phase. Validation of requests for BE-ICS Contributions:Identify contributions which are already covered by our declared activities (projects, maintenance) Proposed solution: define link between contribution request and activity covering that contributionContribution request per Activity phase (preparation, installation, commissioning). Declare resources requiredValidateFollow-up contributions made to other groupsTill 30/01 (start ‘Resources Allocation’ ) we can still request for contributions to other groups. And we may receive requests from other groups ( 10 new requests received in 2016) !
Slide7BE-ICS LS2 Contribution Requests7
https
://plan.cern.ch/app/plan/1/dashboardClick to edit Group Contribution required resources
Slide8BE-ICS LS2 Contributions - Resources Allocation Example
8
Contribution requested covered by Project 'Personnel Protection System modification for LN4 connection': Activity 10048
Slide9Evaluation of Contributions Requests for PPS (CSE & AC)
9
Related with Access Systems & EIS: 9 + 10 requestsRequested byContributionValidation /ActionHSE-RPTREC dev & support (Act. 10961)-> Transfer to EN-ACE-AMM)BE DSOTests DSO ZORA PPS after each YETSOKBE/ENMaintenance
during YETS
OK – AC
YETS Maintenance
EIS
equipment groups (TE-ABT, BE-RF)
Upgrade
EIS SPS
OK –
SPS PPS project (2016-LS2) –
check requirements in our technical spec!
EN-STI
ADT Renewal OK - ECR PS-ADT 2016EN-HETemporary access sys above PX84 shaft during replacement of PZ85 lift? – LHC ECR (2S2016 or LS2?)TEInterface with ELENA EISOK – ELENA projectBE
Connection of Linac4 to the PSBOK – ECR PS-LN2-Booster-SWY-LN4 (LS2)
Slide10PLAN Tool10
Reporting tools
Mail notification: Contributions requested to the groupContributions made by the groupPentaho platform link. Pentaho Reporting help page of Plan HelpRequests for improvements / supportReport of Contributions (made by, requested to) of previous groups (GS-ASE, EN-ICE)Management of group’s CONTRIBUTIONSFor contributions already included in a group LS2 Activity (projects, O&M)Not really required to detail resources but just link to activity & validatePerson responsible for the contribution should be declared and available in Tool and Reports Indicate in interface mandatory fields required to allow to change Activity status to next phaseClarification concerning ‘editable’ data and required data for each phase ! In 2015, requested for ‘Activity’ creation Clon Activity -> clon of all the data including planning and resources … but not implemented !Use of PLAN within BE-ICSEach section leader should have ‘edit’ privileges and receive ‘Contribution’ requests’ reports mail notifications Investigate available functionality, try to use it if useful for managing our projects & activities -> ask the PLAN team for support &
improvements
Ex. Planning, resource management
Training
Resource
Allocation: 4/02 10am
,
874-1-011
Slide11PLAN report mail notification - Example
11
Slide12PLAN report mail notification - Example
12
Slide13