PLAN - LS2 Activities 	 BE-ICS 2016 Status & Action Plan PLAN - LS2 Activities 	 BE-ICS 2016 Status & Action Plan

PLAN - LS2 Activities BE-ICS 2016 Status & Action Plan - PowerPoint Presentation

likets
likets . @likets
Follow
343 views
Uploaded On 2020-08-06

PLAN - LS2 Activities BE-ICS 2016 Status & Action Plan - PPT Presentation

1 15 January 2016 E SanchezCorral Edms 1572767 Outline LS2 Plan Lifecycle and deadlines BEICS Status Activities Contributions Action Plan for Resources Allocation PLAN Tool amp Support ID: 800023

ls2 plan resources contributions plan ls2 contributions resources activities ics groups amp activity contribution requests required pps requested request

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "PLAN - LS2 Activities BE-ICS 2016 Stat..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

PLAN - LS2 Activities BE-ICS 2016 Status & Action Plan

1

15 January 2016E. Sanchez-Corral

Edms:

1572767

Slide2

Outline

LS2 Plan Life-cycle and deadlines

BE-ICS Status ActivitiesContributionsAction Plan for Resources AllocationPLAN Tool & SupportReporting toolsImprovements, support requestsTraining sessions 2

Slide3

LS2 Plan Life-cycle – Version 1After deadline 21/11

Not possible to enter new activities before the next exercise (V2 : 2S2016)

But found out that we can still create new Activities and then ask LS2 Coordinators (K. Foraz) to SUBMMIT Activities to PRIORITIZATION321/11

- Not

able to assess the resources availability before the

prioritization

stage is

completed

-

Can register Resources details

for:

Activities

G

roup Contributions requests

Can request

for Contributions from other groups -> Other groups can still request us for a Contribution (-> number of resquests received has increased !)

All

contributions should be estimated and validated

Slide4

BE-ICS LS2 Activities - Status

4

LS2BE-ICS08-01-2016GS-ASE16-12-2015EN-ICE2015Activites14585

60

Contribution

resquests

137

58

? (~80)

Contributions requests made by BE-ICS to

other

groups= 191

To validate by BE-ICS before 30/04

To be validated by other groups or sections within BE-ICS before 30/04

Slide5

GS-ASE LS2 Activities 5

Section

Domain of activityNumber of Activities

Contributions

made to other groups

CSE – P.

Ninin

- New Personnel Protection

sys:

MEDICIS (2016)

SPS (LS2)

PPS Evolutions

2016:

PS:

ADT, ISOLDE

LS2

PS: LN4 connection

LHC: replace

obsolete access control,

new access point PZ66, temp PA

LHCb

7

EN-EL: control cabling, power supply, optical

fibre

EN-MED: mechanical doors, grids

EN-STI,

IT-CS

EIS

equipment groups EN, TE, BE: power converters, beam stoppers, magnets, RF, AUG

ASE-AS: BIW

HSE: inspections

AC- R. Nunes

ZORA Personnel Protection Systems (PPS) Maintenance (YETS)

11

Similar to CSE

AS – S. Grau

Safety Alarms Systems

67

Slide6

BE-ICS LS2 Resources Allocation Action Plan

6

30/01 to 30/04We have to detail the resources required for BE-ICS activities and contributions requested from other groupshttps://plan.cern.ch/app/plan/1/dashboardFor most of the GS-ASE activities the resources required already declared during Initialization Phase. Validation of requests for BE-ICS Contributions:Identify contributions which are already covered by our declared activities (projects, maintenance) Proposed solution: define link between contribution request and activity covering that contributionContribution request per Activity phase (preparation, installation, commissioning). Declare resources requiredValidateFollow-up contributions made to other groupsTill 30/01 (start ‘Resources Allocation’ ) we can still request for contributions to other groups. And we may receive requests from other groups ( 10 new requests received in 2016) !

Slide7

BE-ICS LS2 Contribution Requests7

https

://plan.cern.ch/app/plan/1/dashboardClick to edit Group Contribution required resources

Slide8

BE-ICS LS2 Contributions - Resources Allocation Example

8

Contribution requested covered by Project 'Personnel Protection System modification for LN4 connection': Activity 10048

Slide9

Evaluation of Contributions Requests for PPS (CSE & AC)

9

Related with Access Systems & EIS: 9 + 10 requestsRequested byContributionValidation /ActionHSE-RPTREC dev & support (Act. 10961)-> Transfer to EN-ACE-AMM)BE DSOTests DSO ZORA PPS after each YETSOKBE/ENMaintenance

during YETS

OK – AC

YETS Maintenance

EIS

equipment groups (TE-ABT, BE-RF)

Upgrade

EIS SPS

OK –

SPS PPS project (2016-LS2) –

check requirements in our technical spec!

EN-STI

ADT Renewal OK - ECR PS-ADT 2016EN-HETemporary access sys above PX84 shaft during replacement of PZ85 lift? – LHC ECR (2S2016 or LS2?)TEInterface with ELENA EISOK – ELENA projectBE

Connection of Linac4 to the PSBOK – ECR PS-LN2-Booster-SWY-LN4 (LS2)

Slide10

PLAN Tool10

Reporting tools

Mail notification: Contributions requested to the groupContributions made by the groupPentaho platform link. Pentaho Reporting help page of Plan HelpRequests for improvements / supportReport of Contributions (made by, requested to) of previous groups (GS-ASE, EN-ICE)Management of group’s CONTRIBUTIONSFor contributions already included in a group LS2 Activity (projects, O&M)Not really required to detail resources but just link to activity & validatePerson responsible for the contribution should be declared and available in Tool and Reports Indicate in interface mandatory fields required to allow to change Activity status to next phaseClarification concerning ‘editable’ data and required data for each phase ! In 2015, requested for ‘Activity’ creation Clon Activity -> clon of all the data including planning and resources … but not implemented !Use of PLAN within BE-ICSEach section leader should have ‘edit’ privileges and receive ‘Contribution’ requests’ reports mail notifications Investigate available functionality, try to use it if useful for managing our projects & activities -> ask the PLAN team for support &

improvements

Ex. Planning, resource management

Training

Resource

Allocation: 4/02 10am

,

874-1-011

Slide11

PLAN report mail notification - Example

11

Slide12

PLAN report mail notification - Example

12