Download Presentation The PPT/PDF document "Procurement 101" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Procurement 101
Processes and Procedures for Contracting at UO
Presented by
:
Greg Shabram, Associate
Director
Laura Harris, Contracts Officer
Purchasing and Contracting ServicesSlide2
Agenda
Procurement Process OverviewProcurement Planning
Developing a Statement of Work
Solicitation
Special Topics in Procurement
2Slide3
Procurement Process FrameworkSlide4
Procurement Planning
Develop Minimum Specifications and Estimate Total Dollar Value
Determine Applicable Policies and Procedures
Create and Procurement Team and Plan
Draft a Statement of Work (SOW)
4Slide5
Estimating Total Dollar Value
Total cost for each year of the project
All reasonably foreseeable costs associated with that project payable to one vendor
Take into account recurring spend, if foreseeable
If close to a competitive threshold err towards the higher amountSlide6
Determine Applicable Policies and Procedures
Can you buy the goods/services from a QRF, an existing price agreement, or from the eProcurement system?
Check the approvals list to determine any additional stakeholders
Use the following flow chart to determine the correct procurement process Slide7
Buy Decision
Can you buy from a QRF?
Yes
No
Buy from QRF
Can you buy
from
an
established
Price Agreement?
Yes
Buy off Price Agreement
Is the purchase exempt or valued at under $25K?
No
Yes
Direct Procurement
No
Is this
only available from a
Sole Source?
Yes
Post and buy Direct
Is there a limited vendor pool?
Yes
Conduct AP
Is the total value less than $150K?
No
Yes
Conduct RFQ/ITB*
No
Conduct RFP/ITB*
Procurement Planning Flowchart
*An ITB is only appropriate when price is the only selection factor
No
NoSlide8
Create a Procurement Team and Plan your Procurement
This step scales to the scope of your procurement
Could be just you issuing a PO, may be a team of multiple UO departments and stakeholders
Host a kickoff meeting
Invite team members (Dept. Staff, Campus Stakeholders, PCS Staff)
Agree on a procurement schedule based on applicable procurement process
Identify who will draft SOW and when it will be completed
Clearly identify roles and responsibilitiesSlide9
Create a Procurement Team and Plan your Procurement – Cont.
Develop a BATNA
What happens if the procurement fails?
At what point are you willing to walk away from a vendor?
Divide needs from wants
Identify UO strategic interests addressed by the procurement.
Notify applicable departments on the approvals list (invite stakeholders to the kickoff meeting if appropriate)Slide10
Discussion 1
Think of the largest purchase that you plan to make this yearEstimate the value, identify the appropriate procurement process, and identify stakeholders
When do you plan to hold your kickoff meeting? Send us an outlook invite!
Be prepared to share with the groupSlide11
Drafting Specification/SOWs
11
An effective SOW should clearly define what work will be done,
what interim steps must be completed, who
will do it, and when they will complete
the work and each step.
The SOW does not need to be an exhaustive list of every action necessary to complete a project, but the SOW should be detailed enough so that anyone with the appropriate background should be able to understand, without any ambiguity, what will result from the project. Slide12
Drafting Specification/SOWs
12
Every SOW should, at minimum, include the following elements:
A description of the deliverables, including any specifications or standards that those deliverables must
meet.
The
tasks that support the deliverables, as well as which Party (the University for the Contractor)
responsible
for completing those tasks.
A
timeline that details when each task will be completed and when each deliverable will be delivered.
The
resources (people, equipment, facilities, etc.)
required
for the project and the party responsible for providing those resources.
Acceptance
criteria and an acceptance procedure.
A
clear price for the project, that is limited to a fixed amount. Slide13
Discussion 2
13
We need a volunteer!
Let’s work as a group to draft a SOWSlide14
Conducting the Procurement
Goals: Ensure Fairness
Foster Competition
Satisfy Stakeholder Interests
Get the Best Value!*Shameless Plug* Pay With a PCard!Slide15
Conduct a Procurement
Direct Procurement: Draft your SOW
Understand the Marketplace
Ask vendors for quotes
NegotiatePurchase (with a PCard!)Slide16
Formal/Informal Procurement
Draft/Post AP, ITB, RFQ, or RFPReview responses in accordance with terms of solicitation and UO policies
Select the best value sourceSlide17
Sole Source
Criteria: Due to specific needs or qualifications, the goods or services required are only reasonably available from a single vendor.
Must clearly demonstrate that the SOW is the only reasonable manner UO could meet its need, and that the vendor is the only vendor in the marketplace that can fulfill that SOW.
Process:
Posted for at least 7 calendar days.
If no protests are made, the transaction may proceed.Slide18
Alternative Procurement
Criteria: A limited vendor pool of at least two entities or a purchase of IT services (i.e. SaaS)
Responds to innovative business and market methods.
Contributes
to UO’s productivity improvement and process redesign.Results in comprehensive cost-effectiveness and productivity for UO
.
Process:
Posted for at least 5 business days.
Informal posting and selection criteria.
Greater opportunity to negotiate price and terms prior to award. Slide19
Request for Quote
Criteria: All goods and services between $25k and $150k
Selection based on best
value or lowest price.
Process:Posted for at least 5 business days. Informal posting and selection criteria.
Must solicit bids from three vendors, one being an MWESBSlide20
Request for Proposal
Criteria: All goods and services over $150k
Selection based on best value
Process:
Posted for at least 21 calendar days Formal
posting and
selection criteria
Must solicit bids from three vendors, one being an
MWESB
May include controlled meetings with vendors and down selection processes
Must develop a detailed scoring and source selection process Slide21
Invitation to Bid
Criteria: All goods and services over $150k
Selection based on
lowest price
Process:Posted for at least 21 calendar days Formal posting and selection criteria
Must solicit bids from three vendors, one being an MWESB
May include controlled meetings with vendors and down selection processes
Must develop a detailed scoring and source selection process Slide22
RFP Scenario
We’ve drafted a SOW. Lets draft an RFP and determine possible vendors. Slide23
Special Topics
Strategic Purchasing
Duck Depot
Payment
Delegated Contracting AuthorityNext Class
es:
Procurement 102: 3/15
Rules and Ethics: 4/17
Procurement 101: 5/22Slide24
Policy
Training
Templates
Written Procedures and Instructions
WebsiteDirect assistance from PCS Staff via phone, email and in-person meetings
Each department is assigned a Contracts Officer and Contracts Tech.
I
f you do not know yours let us know and we’ll put you in touch with them!
Tools & Support
24Slide25
Questions?
25