Magnetic Field Mitigation Magnetic Field Mitigation

Magnetic Field Mitigation - PowerPoint Presentation

lois-ondreau
lois-ondreau . @lois-ondreau
Follow
407 views
Uploaded On 2016-12-04

Magnetic Field Mitigation - PPT Presentation

Schedule Options Alan Grant Option 1 Step IV base line schedule NO PRY Partial Return Yoke Option 2 Step IV schedule Spectrometer Solenoids Installed BEFORE PRY Overview 24th September ID: 497255

risk pry installed september pry risk september installed delay magnetic field option path schedule mitigation 2013 review 24th step

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Magnetic Field Mitigation" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Magnetic Field MitigationSchedule Options

Alan GrantSlide2

Option 1Step IV base line schedule - NO PRY

(Partial Return Yoke)

Option 2Step IV schedule – Spectrometer Solenoids Installed BEFORE PRY

Overview

24th September 2013

Magnetic Field Mitigation Review

2Slide3

Option 1 - Step IV base line schedule - NO PRY

Critical Path

24th September 2013Magnetic Field Mitigation Review

3

(Risk)-(R2) 40day delay

(Risk)-(R3) 20day delay

(Risk)-(R4) 10day delaySlide4

24th September 2013

Magnetic Field Mitigation Review

4

Option 1 - Step IV base line schedule -

NO

PRY

Critical Path

Assumes we can engineer solutions to known localised shielding issues

More risky – may have overlooked some components

Critical path driven by West Mezzanine Wall and compressor installation

Magnets cooled in September 14

If channel does not work may have to install PRY – risk of delay for

stepIV

completion

2/1/15

29/9/15Slide5

Option 2 - Step IV schedule – Spectrometer Solenoids Installed

BEFORE

PRY

5

(Risk)-(R1) 80day delay

Fig 2. Devices moved offline. South PRY lower installed

Fig 3. South PRY upper installed

Fig 1. Devices installed online initially.

Images courtesy of Jason TarrantSlide6

Option 2 - Step IV schedule – Spectrometer Solenoids Installed BEFORE PRY

Critical Path

24th September 2013Magnetic Field Mitigation Review

6

(Risk)-(R2) 40day delay

(Risk)-(R3) 20day delay

(Risk)-(R4) 10day delaySlide7

12th September 2013

Magnetic Field Mitigation Review

7

Option 2 - Step IV schedule – Spectrometer Solenoids Installed

BEFORE

PRY

Critical Path

27/10/15

30

/1/15

Assumes

S

outh side PRY available mid

A

pril

Assumes North side PRY available mid July – but not installed until mid September

Critical path driven by West Mezzanine Wall and compressor installation

Magnets cooled in September 14

Magnet training

can only take

place after full PRY is

installed Slide8

Critical path driven by West Mezzanine Wall and compressor installation Further work required to identify & quantify risks.

Estimated cost:- £500k & 5man

yrs effort UKAssumes delivery of South PRY mid April 14 and North PRY mid July 14North PRY not installed until September 14 Risk Delay – assumes we incur all identified delaysSchedule & risks need to be monitored as these will change

Summary

24th September 2013

Magnetic Field Mitigation Review

8

Finish Date

Delayed finish due to Risk

StepIV

base line

2/1/15

29/9/15

SS before PRY

30/1/15

27/10/15