/
AUGUST  9 ,  2019, Holyoke Massachusetts AUGUST  9 ,  2019, Holyoke Massachusetts

AUGUST 9 , 2019, Holyoke Massachusetts - PowerPoint Presentation

motivatorprada
motivatorprada . @motivatorprada
Follow
344 views
Uploaded On 2020-06-22

AUGUST 9 , 2019, Holyoke Massachusetts - PPT Presentation

Manasa Kotha 4135404753mkothaisonecom 20202021 Third Annual Reconfiguration Auction 20202021 ARA 3 20212022 Second Annual Reconfiguration Auction 20212022 ARA 2 20222023 First Annual Reconfiguration Auction 20222023 ARA 1 ID: 783704

resources capacity 2022 2021 capacity resources 2021 2022 values ara demand icr intermittent generating resource 2020 england assumptions ccp

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "AUGUST 9 , 2019, Holyoke Massachusetts" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

AUGUST 9, 2019, Holyoke Massachusetts

Manasa Kotha(413)-540-4753|mkotha@iso-ne.com

• 2020-2021 Third Annual Reconfiguration Auction (2020-2021 ARA 3) • 2021-2022 Second Annual Reconfiguration Auction (2021-2022 ARA 2) • 2022-2023 First Annual Reconfiguration Auction (2022-2023 ARA 1)

Assumptions for the Installed Capacity Requirement (ICR) Values

Calculations

Slide2

Objective of this Presentation

Review the ICR-Related Values* development, NEPOOL committee review and FERC filing schedules

for Annual Reconfiguration Auctions (ARAs) to be conducted in 2020Review the assumptions for calculating:

Installed Capacity Requirement (ICR)Transmission Security Analysis (TSA)Local Resource Adequacy Requirement (LRA)Local Sourcing Requirement (LSR)

Maximum Capacity Limit (MCL)

Marginal Reliability Impact (MRI) System Wide and Zonal Demand Curves, as applicable

*The ICR, TSA, LRA, LSR, MCL, Demand Curve values and

the Hydro-Quebec Interconnection Capability Credits (HQICCs) are collectively referred to as the ICR-Related Values

2

Slide3

ARAs ICR-Related Values Development ScheduleICR-Related Values for the ARAs to be conducted in 2020 will be calculated, reviewed and filed concurrently2020-2021 ARA 3 ICR-Related Values

2021-2022 ARA 2 ICR-Related Values2022-2023 ARA 1 ICR-Related Values3

Date

TopicAugust 9

PSPC review of assumptions for ICR-Related Values for ARAs and assumptions for ARA 3 tie benefits study

August 29

PSPC review of ARA 3 tie benefits study

September 9

PSPC review of proposed ICR for ARAs

October 8

PSPC review of

proposed

ICR-Related Values

October 23

RC review/vote of proposed ICR-Related Values

November 1

PC review/vote of proposed ICR-Related Values

By November 30

File with FERC

Slide4

Calculation of ICR-Related Values

4

LSR,

MCL, and

MRI Demand Curves will

be calculated for the

same Capacity

Zones determined for the respective Forward Capacity Auction (FCA)

ICR

-Related Values

 

CCP

2020-2021

CCP

2021-2022

CCP

2022-2023

Import

Capacity

Zone

(TSA, LRA, LSR)

Southeast New England (SEMA, RI, NEMA-Boston)

Southeast

New England (SEMA, RI, NEMA-Boston)

Southeast

New England (SEMA, RI, NEMA-Boston)

Export

Capacity

Zone

(MCL)

Northern New England

(ME,

NH, VT)

Northern New England

(ME,

NH, VT)

Northern New England (ME, NH

, VT

)

Demand

Curves

MRI Demand

Curves

System

&

Zonal

MRI Demand

Curves

System

&

Zonal

MRI Demand

Curves

System

&

Zonal

Slide5

Assumptions for the CCP 2020-2021 ARA 3, CCP 2021-2022 ARA 2 and CCP 2022-2023 ARA 1

ICR-Related Values Calculations

5

Slide6

Modeling the New England Control Area for ARAs to be Conducted in 2020The General Electric Multi-Area Reliability Simulation model (GE MARS) is used to calculate several of the ICR-Related ValuesInternal transmission constraints are not modeled in the ICR calculation. All loads and resources are assumed to be connected to a single electric bus

Internal transmission constraints are addressed through the LSR and MCLsA LSR will be calculated for the import-constrained Southeast New England (SENE) Capacity Zone, consisting of the NEMA/Boston, SEMA and RI Load ZonesAn MCL will be calculated for the export-constrained Northern New England (NNE) Capacity Zone, consisting of the combined Load Zones of Maine, New Hampshire and Vermont The MRI based method for calculating demand curves will be used to develop System and Capacity Zone Demand Curves

6

Slide7

7

Assumptions for the ICR-Related Values Calculations

Load Forecast

Net of behind-the-meter (BTM)

p

hotovoltaic

(PV) resource

forecastLoad forecast distributionQualified Capacity (QC) of resources*Generating Capacity Resources Intermittent

Power

Resources (IPR)

Import Capacity Resources

Demand Resources (DR

)

Resource availability

Generating Resources’ availability

Intermittent Power Resources’ availability

Demand Resources’ availability

*

Known resource retirements are removed; new cleared capacity resources are added as applicable; capacity imports are de-rated according to assumed external transmission transfer capability

.

Slide8

OP-4 Actions used to Develop Assumptions for the ICR-Related Values Calculations

8

Load or capacity relief assumed obtainable from implementing the following actions of the Operating Procedure No. 4, Action during a Capacity Deficiency (OP-4)

Request emergency assistance from neighboring Control Areas (Tie reliability benefits)

Quebec (includes Hydro-Quebec Interconnection Capability Credits (HQICCs))

Maritimes

New York

Initiate 5% voltage reduction

Slide9

9

Load Forecast (MW)For Applicable Capacity Zones and Total New England

50/50 & 90/10 reference (net of BTM PV) load forecasts values are from the 2019 CELT load forecast (

labeled “2A Summer (MW): ISONE Control Area, New England States, RSP Sub-areas, and SMD Load Zones

) for the corresponding RSP sub-areas used in the ARA ICR Values calculations (see:

https://www.iso-ne.com/static-assets/documents/2019/04/forecast_data_2019.xlsx

)The reference 50/50 load forecast shown is for informational purposes; in the ICR Values calculations, the GE MARS model sees an hourly distribution of loads with the BTM PV modeled with an

hourly

profile and a 7-day window uncertainty methodology

The 90/10 load forecast values are used directly in the calculation of TSA for import-constrained Capacity Zones; all other values shown are for informational purposes

 

SENE

NNE

Total New England

CCP

50/50

90/10

50/50

90/10

50/50

90/10

2020-2021

12,244

 

13,213

 

 

5,300

 

5,533

28,353

30,273

2021-2022

12,337

13,325

 

5,339

5,595

 

28,499

30,449

2022-2023

12,439

13,449

5,386

5,645

28,670

30,652

Slide10

Load Forecast, cont.Modeling of BTM PV

ICR calculations will use an hourly profile of BTM PV corresponding to the load shape for the year 2002, used by the Northeast Power Coordinating Council (NPCC) for reliability studies. For more information on the development of the hourly profile see: https://www.iso-ne.com/static-assets/documents/2017/06/pspc_6_22_2017_2002_PV_profile.pdfUsed for all probabilistic ICR-Related Values calculations

Modeled in GE MARS by Regional System Plan (RSP) 13-subarea representationIncludes an 8% transmission and distribution gross-upPeak load reduction uncertainty is modeled (randomly selected by MARS from

a seven day window distribution)The values of BTM PV published in the 2019 CELT Report are the values of BTM PV subtracted from the gross load forecast to determine the net load forecastThe published 90/10 net load forecast for the SENE sub-areas is used in the TSA

Notes:

For more info on the PV forecast, see

https

://www.iso-ne.com/static-assets/documents/2019/04/final-2019-pv-forecast.pdf 10

Slide11

Resources’ Qualified Capacity (QC) Resource Data : Used the latest available data for each CCP

11Note:

*Qualified New Capacity Resources on critical path schedule monitoring with deliverability prior to June

1, 2022

2020-2021 ARA 3

2021-2022

ARA 2

2022-2023 ARA 1

2020-2021 ARA 2 bilateral

period QC

data

2021-2022 ARA

1 QC

data

2022-2023 FCA Existing QC

data + 2022-2023 FCA New Capacity Resources

amount

*

Import

Capacity Resources

The

QC

values are

de-rated

if the sum of the import

QC

is higher than the remaining

transmission

t

ransfer

c

apability

(TTC) of the external interface after accounting for tie benefits

This is the same procedure used for the ARA ICR calculations in previous years

Slide12

12

Resources’ QC (MW)

By Capacity Zone & Total New England

2020-2021 ARA 3

2021-2022 ARA 2

2022-2023 ARA 1

Note:

Generating resources exclude a

30 MW derating to reflect the value of the

firm Vermont Joint Owners (VJO)

contract

for CCP 2020-2021 and CCP 2021-2022

Known retirement requests are removed from the applicable CCP

Resource Type

SENE

NNE

New England

Non-intermittent Generating Capacity Resources

9,651

7,368

30,482

Intermittent

Power Resources

223

557

1,061

Import

Capacity Resources

-

255

1,750

On-Peak Demand Resources

1,588

473

2,739

Seasonal Peak Demand Resources

-

-

596

Active Demand Capacity Resources

254

274

962

Grand Total

11,716

8,927

37,590

Resource Type

SENE

NNE

New England

Non-intermittent Generating Capacity Resources

9,652

7,360

30,227

Intermittent

Power Resources

222

7191,236Import Capacity Resources- 2511,680On-Peak Demand Resources1,6215302,874Seasonal Peak Demand Resources--656Active Demand Capacity Resources249253945Grand Total11,7449,11337,618

Resource Type

SENE

NNE

New England

Non-intermittent Generating Capacity Resources

9,640

7,314

31,008

Intermittent

Power Resources

478

650

1,395

Import

Capacity

Resources

-

 

235

1,698

On-Peak Demand Resources

1,742

537

3,013

Seasonal Peak Demand Resources

-

-

651

Active Demand Capacity Resources

326

259

1,086

Grand Total

12,186

8,996

38,851

Slide13

Internal TTC Assumptions (MW)

- For LSR and MCL Modeling13

Based on transmission transfer capability limits presented at the March 20, 2019 Reliability Committee meeting. The presentation is available at

: https://www.iso-ne.com/static-assets/documents/2019/03/a7_fca_14_transmission_transfer_capabilities_and_capacity_zone_development.pdf

 

Southeast

New

England Import (MW)

(for SENE LSR)

North-South Interface (MW)

(for NNE MCL)

CCP

N-1

N-1-1

N-1

2020-2021

5,400

4,500

2,725

2021-2022

5,700

4,600

 

2,725

2022-2023

5,700

4,600

2,725

Slide14

Resource Availability Assumptions

Generating

Capacity ResourcesForced outages assumption

Each generating unit’s Equivalent Forced Outage Rate on demand (non-weighted EFORd) modeledBased on a 5-year average (Jan 2014 – Dec 2018) of generating unit data submitted to Generation Availability Data System (GADS)

NERC GADS Class average data is used for immature & non-commercial units

Scheduled outage

a

ssumptionEach generating unit’s weeks of maintenance modeledBased on a 5-year average (Jan 2014 – Dec 2018) of each generating unit’s actual historical average of planned and maintenance outages scheduled at least 14 days in advance

NERC GADS

c

lass average data is used for immature & non-commercial units

Each CCP will have the appropriate

generating units

modeled along with their individual availability

statistics

Intermittent Power Resources are modeled as 100% available since their outages have been incorporated in their 5-year historical output used in their ratings

determination

14

Slide15

Resource Availability Assumptions, cont

.

Demand Resources (DR)Use historical DR performance from summer & winter

2014 – 2018 (same values developed for FCA 14)For more information see the May 2019 PSPC presentation:

https://www.iso-ne.com/static-assets/documents/2019/05/a3_dr_season_perfrmnce_0530219.pdf

Modeled by Load Zones and type of DR with outage factor calculated as 1- performance/100

The

same performance values will be applied for CCP 2020-2021 through CCP 2022-202315

Slide16

Resource Availability Assumptions, cont.16

Import Capacity

Resources

Modeled

in the ICR calculations

as:

Pool

backed are 100% availableResource backed are modeled with availability assumptions shown below

NERC Class Avg

EFORd

Maintenance (Weeks)

HYDRO 30 Plus

3.76

7.00

Slide17

Resource Availability Assumptions, cont.

17

Note:

Non-intermittent Generating Capacity Resources uses the same per unit EFORd and maintenance weeks values developed for FCA 14. In the LOLE simulations, individual unit values are modeled

Assumed

summer MW weighted

EFORd/Forced Outage Rate (FOR)

and maintenance weeks are shown by resource types for informational purposesNon-intermittent Generating Capacity Resources category excludes a 30 MW

derating

to reflect the value of the firm VJO contract

CCP 2020-2021 ARA 3

Resource Type

Summer MW

Assumed Average EFORd (%) Weighted by Summer Ratings

Assumed Average Maintenance Weeks Weighted by Summer Ratings

Non-intermittent Generating Capacity Resources

30,482

6.3

4.9

Intermittent Generating Resources

1,061

0.0

0.0

Import Capacity Resources

1,750

2.7

8.2

On Peak Demand Resources

2,739

0.0

0.0

Seasonal Peak Demand Resources

596

0.0

0.0

Active Demand Capacity Resource

962

5.8

0.0

Total New England

37,590

5.4

4.3

Slide18

Resource Availability

Assumptions, cont.18

CCP 2021-2022 ARA 2

Notes:Non-intermittent Generating Capacity Resources

uses the same per unit EFORd and

maintenance

weeks values developed for

FCA 14. In the LOLE simulations, individual unit values are modeledAssumed summer MW weighted EFORd/FOR and maintenance weeks are shown by resource type

for informational purposes

Non-intermittent Generating Capacity Resources

excludes

a 30 MW derating to reflect the value of the firm VJO contract

Resource Type

Summer MW

Assumed Average EFORd (%) Weighted by Summer Ratings

Assumed Average Maintenance Weeks Weighted by Summer Ratings

Non-intermittent Generating Capacity Resources

30,227

6.2

4.8

Intermittent Generating Resources

1,236

0.0

0.0

Import Capacity Resources

1,680

2.5

7.9

On Peak Demand Resources

2,874

0.0

0.0

Seasonal Peak Demand Resources

656

0.0

0.0

Active Demand Capacity Resource

945

5.6

0.0

Total New England

37,618

5.2

4.2

Slide19

Resource Availability

Assumptions, cont.19

CCP 2022-2023 ARA 1

Note:Non-Intermittent Generating Resources uses the same per unit EFORd and Maintenance weeks values developed for

FCA 14.

In the LOLE simulations, individual unit values are modeled

Assumed summer MW weighted EFORd/FOR and maintenance weeks are shown by resource

types for informational purposes

Resource Type

Summer MW

Assumed Average EFORd (%) Weighted by Summer Ratings

Assumed Average Maintenance Weeks Weighted by Summer Ratings

Non-intermittent Generating Capacity Resources

31,008

6.1

4.8

Intermittent

Power

Resources

1,395

0.0

0.0

Import Capacity Resources

1,698

2.6

8.1

On Peak Demand Resources

3,013

0.0

0.0

Seasonal Peak Demand Resources

651

0.0

0.0

Active Demand Capacity Resource

1,086

5.9

0.0

Total New England

38,851

5.2

4.2

Slide20

20

TSA Assumptions for Import Capacity Zones2020-2021 ARA 3, 2021-2022 ARA 2 and 2022-2023 ARA 1

2020-2021 ARA 3

2021-2022 ARA 2

2022-2023 ARA 1

DR Qualified Capacity are

same values used

as shown in Slide 12DR derating factors used in TSA are the same factors that are being used in FCA 14 ICR calculations

RI: 15%; SEMA:3%; NEMA:11%

Peaking Generating

Capacity Resources

uses the individual unit’s availability (EFORd)

Resource Type

SENE

QC(MW)

EFORD

Non-intermittent Generating Capacity Resources

9,651

6%

Intermittent

Power

Resources

223

0%

Resource Type

SENE

QC(MW)

EFORD

Non-intermittent Generating Capacity Resources

9,652

6%

Intermittent

Power

Resources

222

0%

Resource Type

SENE

QC(MW)

EFORD

Non-intermittent Generating Capacity Resources

9,640

6%

Intermittent Power

Resources

478

0%

Slide21

Operating Procedure No. 4 (OP-4) Assumptions

- Actions 6 & 8⁠—5% Voltage Reduction (MW)

Uses the 90-10 Peak load forecast net of BTM PV minus all DR multiplied by the 1% value assumed in estimating relief obtained from OP-4 voltage reduction

21

 

90-10 Peak Load

Passive DR

ACDR

Actions

6 & 8

5% Voltage Reduction

June

2020-Sept 2020

30,273

3,335

962

260

October

2020-May 2021

23,983

3,143

950

199

 

June

2021-Sept 2021

30,449

3,530

945

260

October

2021-May 2022

24,138

3,407

902

198

 

June

2022-Sept 2022

30,652

3,664

1,086

259

October

2022-May 2023

24,283

3,558

1,041

197

Slide22

OP4 Assumptions,

cont. - Tie Benefits

Values for 2020-2021 ARA 3 tie benefits will be the results of the 2020 ARA 3 tie benefits studyValues for 2021-2022 ARA 2 and 2022-2023 ARA 1 are those calculated for the corresponding

FCAs (FCA 12 and FCA 13, respectively)22

Control Area

2020-2021

ARA 3

2021-2022

ARA 2 (MW)

2022-2023

ARA 1 (MW)

Quebec via Phase II

TBD

958

969

Quebec via Highgate

TBD

143

149

Maritimes

TBD

506

516

New

York AC ties

TBD

413

366

Total

2,020

2,000

The tie benefits availability assumptions will be based on the availability assumptions associated with the external transmission line

updated

using the newly proposed

methodology*

These are the same values used to model the performance of the Import Capacity Resources that are

p

ool-

b

acked

*

Based on recently updated values using the newly proposed methodology presented at the March 30, 2019 Power Supply Planning Committee meeting.

The

presentation is available at:

https://www.iso-ne.com/static-assets/documents/2019/05/a5_tie_line_availability_05302019.pdf

Slide23

OP4 Assumptions, cont. - Minimum System Reserve Assumption (MW)

23

Minimum

system r

eserve

is the

minimum reserves held for transmission system security

Modeled at 700 MW

Slide24

Summary of all MW Modeled in the ICR Values Calculations

Notes:

Generating Capacity Resources excludes a 30 MW de-rate to reflect the value of the firm VJO contract for CCP 2020-2021 and CCP 2021-2022 Intermittent Power Resources have both the summer and winter capacity values modeled

Import Capacity Resources reflect a derating to account for TTC and each CCP’s tie benefitsOP-4 voltage reduction includes both Action 6 and Action 8 MW assumptionsMinimum system reserve is the minimum reserves held for transmission system securityTie benefits for 2020-2021 are the results of the 2020 ARA 3 tie benefits study; Tie benefits for 2021-2022 and 2022-2023 are those calculated for the corresponding FCA

24

Total

Capacity/OP4

Breakdown

2020-2021

ARA3

2021-2022

ARA2

2022-2023

ARA1

Non-intermittent Generating Capacity Resources

30,482

30,227

31,008

Intermittent

Power Resources

1,061

1,236

1,395

Import

Capacity Resources

1,750

1,680

1,698

Demand Resources

4,297

4,475

4,750

Voltage

Reduction

260

260

259

Minimum

system reserve

-700

-700

-700

Tie

benefits

TBD

 

2,020

2,000

Total Capacity

TBD

39,198

40,410

Slide25

Appendix IAcronyms

25

Slide26

AcronymsARA – Annual Reconfiguration AuctionBTM PV – Behind-the-meter Photovoltaic

FCA – Forward Capacity AuctionCCP – Capacity Commitment PeriodCSO – Capacity Supply ObligationCELT – Capacity, Energy, Loads and TransmissionCT – ConnecticutDR – Demand ResourceEE – Energy EfficiencyFCA – Forward Capacity Auction

FERC – Federal Energy Regulatory Commission26

Slide27

Acronyms, cont.HQICCs – Hydro-Quebec Interconnection Capability CreditsICR – Installed Capacity RequirementISO – ISO New England

LRA – Local Resource AdequacyLSR – Local Sourcing RequirementMCL – Maximum Capacity LimitMRI – Marginal Reliability ImpactNet ICR – ICR minus HQICCs OP-4 – Operating Procedure No. 4, Action During a Capacity DeficiencyPC – Participants Committee

PSPC – Power Supply Planning CommitteeRC – Reliability CommitteeTSA – Transmission Security Analysis

27

Slide28

28