/
PRESENTATION TITLE PRESENTATION TITLE

PRESENTATION TITLE - PowerPoint Presentation

myesha-ticknor
myesha-ticknor . @myesha-ticknor
Follow
399 views
Uploaded On 2018-01-05

PRESENTATION TITLE - PPT Presentation

Presented by Name Surname Directorate Date 1 RAND WATERS PRESENCE IN Mpumalanga Regional Bulk Infrastructure Reticulation Related Projects Challenges and Way Forward 2 2 The Asset planning division together with the assistance of operations have assessed the immediate infrastruct ID: 620005

completed water rand projects water completed projects rand june thembisile capacity bushbuckridge plant treatment april dam local august municipality

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "PRESENTATION TITLE" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

PRESENTATION TITLEPresented by:Name SurnameDirectorateDate

1

RAND WATER’S PRESENCE

IN

MpumalangaSlide2

Regional Bulk InfrastructureReticulation Related ProjectsChallenges and Way Forward

2

2Slide3

The Asset planning division together with the assistance of operations have assessed the immediate infrastructure needs for the area of operation. Demand is currently only partially being met from a number of abstraction and treatment plants as most plants suffer from a lack of maintenance. In order to bring current plants up to design capacity and reliability, renewal projects are recommended at several of the plants to provide standby capacity, improving operational control for both water quantity and quality purposes. This is the immediate focus of the capital expenditure program. The following projects have been identified: Acornhoek Water treatment plant – Refurbishment of the water treatment system.

Thulamhashe water treatment plant – Automation and addition of redundancy on the

Hoxane water treatment plant – Automation and addition of redundancy on the coagulant dosing system. This will include various other aspects

realting to the improvement of water treatment

Meeting further demand, current and future, will require augmentation of both treatment and bulk pipeline capacity. This is considered as the second phase of the program although some augmentation of infrastructure is expected to be invested in the initial stages. This is expected to increase as condition assessments of the infrastructure are completed in the upcoming year. The following projects have been identified:

Additional Hoxane raw water pump station and connecting pipeline

Additional Hoxane purification and pumping station. Hoxane to Ndonga pipeline (800/700diameter)

20Ml reservoir at Ndonga Pipeline Ndonga to Cunningmore (800/700diameter)

An interim cash flow projection over the five year period is estimated at R600m.

Regional Bulk Infrastructure – Bushbuckridge

3Slide4

Bushbuckridge Local Municipality supply area

Plant (WTW)

Design Cap (Ml/day)

Operational

capacity (

Ml/day)

Operational capacity due to drought

Production reduction due to drought (%)

Municipal Area

Raw water source

Raw water source status

Inyaka

100

100

100

0%

BushbuckridgeInyaka Dam Fair Hoxane 2725250%BushbuckridgeSabie river (release from Inyaka dam)Fair Thulamahashe9.06350%BushbuckridgeMutlumuvi riverPoor Acornhoek 6.0440%BushbuckridgeAgricultural dam and klein sand riverFair Edinburgh 3.02,7163%BushbuckridgeAgricultural damPoor Sand River1.00.80.440%BushbuckridgeSand riverPoor Marite 42.42.40%BushbuckridgeNwaritjie river (release from Inyaka Dam)Fair

4Slide5

Mbombela

Local Municipality supply area

Plant (WTW)

Design Cap (Ml/day)

Operational capacity (

Ml/day)

Current Operational capacity due to drought

Production reduction due to drought (%)

Municipal Area

Raw water source

Raw water source status

Kanyamazane New

47

53

53

0%

MbombelaCrocodile river (release from Kwena dam)Fair Kanyamazane Old62.42.40%MbombelaCrocodile river (release from Kwena dam)FairNyongane1422220%MbombelaSabie river (release from Inyaka dam)FairMshadza Package plant20.80.450%MbombelaSmall streamPoor Dwaleni Package Plant20.60.350%MbombelaSmall stream poor Mganduzweni Package Plant20.80100%MbombelaAgricultural damPoor 5Rand Water undertakes operations and maintenance for the Kanyamazane plant onlyTherefore, Rand Water has limited ability to increase capacityContract with Mbombela has expired and on a month-to-month basis. The current contract does not even cover the cost of running the plant.There is current and increasing debt. In the last session in January 2017, Mbombela agreed to take to council the settlement agreement on the accumulated debt. However, given the past, there is little chance of success.Therefore Rand Water’s success in this area is limited.Slide6

6

Additional Challenges

Concession Agreement With

Sembcorp

Silulumanzi

This is a 30 year concession with

Mbombela

However, this is limited to the more affluent areas of

Mbombela

Rand Water operates the rural and poorer areasSlide7

Summary on Projects in MpumalangaRand Water is the implementing agent for the list of projects listed below .

These

projects are funded through MIG, MWIG NWRI , RBIG and MPG.

Project Name / Description

Current % Completion to date (work done

thusfar

compared to expected work)

1.

Thembisile

Hani

Completed – April 2016

 

2.

Thembisile

Hani

Completed

– March 20163. Thembisile HaniCompleted – April 20164. Thembisile HaniCompleted – April 20165. Thembisile HaniCompleted – Sep 20156. Thembisile HaniCompleted – March 20167. Thembisile Hani Completed – April 2016 8. Thembisile Hani Completed – March 20169. Thembisile Hani Completed – April 20161. EmakhazeniCompleted – August 20162. Emakhazeni Completed - 30 June 20163. Emakhazeni Completed – August 20164. EmakhazeniCompleted – August 20165. EmakhazeniCompleted - 30 June 20166. EmakhazeniCompleted – August 20167. EmakhazeniCompleted – August 20167Rand Water was appointed to undertake projects on behalf on different local municipalities in MpumalangaRand Water undertook these projects and the list of completion dates is shown on the following slidesThe list of projects was presented in the 2014 – 15 financial yearReticulation Related Projects in MpumalangaSlide8

Project Name / Description

Current % Completion to date (work done

thusfar compared to expected work)

1. Victor

Khanye

Completed – August 2016

2. Victor

Khanye

Completed – April 2016

3. Victor

Khanye

Completed – June 2016

1. Bushbuckridge

97.5%2. Bushbuckridge 90.0%3. Bushbuckridge 92.0%4. BushbuckridgeCompleted – December 20155. BushbuckridgeCompleted - November 20156. Bushbuckridge7. BushbuckridgeCompleted – Sep 20151. Dr Pixley Ka Seme Completed - June 20162. Dr Pixley Ka SemeCompleted - June 20163. Dr Pixley Ka Seme Completed - June 20164. Dr Pixley Ka SemeCompleted - June 20165. Dr Pixley Ka SemeCompleted - June 20161. DipalesengCompleted – March 20162. Dipaleseng Completed - June 20163. DipalesengCompleted – April 20161. Govan MbekiCompleted - June 20161. Steve TshweteCompletion (71%) – October 20168Slide9

Mpumalanga

– Strategic Challenges

No.

Description

Scheme

DWS Response

1

Identification

of assets for takeover

Bushbuckridge Scheme

There was transfer of regional bulk assets to

the

Botshabelo District Municipality in 2009. This was disestablished and the assets transferred to Bushbuckridge.

The IRR Masterplan identifies the Bushbuckridge scheme for transfer to the regional water utility (Rand Water).

The critical matter remains outstanding.

The new councilors of BBR are of the opinion that the municipality should continue with ownership.

Therefore Rand Water’s operations will not be viable.2Identification of assets for takeoverWestern Highveld SchemeThe IRR Masterplan identifies the Western Highveld scheme for transfer to the regional water utility (Rand Water). However this matter remains outstanding.3Funding PlanBushbuckridge and Western Highveld SchemesThe recommendation of work done by consultants on behalf of DWS is silent on the required funding. 4Resistance by local municipalitiesBushbuckridge Local Municipality There is increasing uncertainty in the relationship with Bushbuckridge Local Municipality. Rand Water received communication in January 2017, that council resolved to take over all projects that Rand Water has been undertaking9Slide10

THANK YOU10