LHCYETS 201718 Coordination meeting 22 27th February 2018 AGENDA YETS planning followup Marta Alcaide Leon Maria Barberan Marzia Bernardini Sebastien Bustamante 16Jan18 ID: 799426

february lhc 27th coordination lhc february coordination 27th meeting 2018 jan amp installation yets january march test point 2017

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "1 LHC coordination meeting 27th February..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

1

LHC coordination meeting 27th February 2018

LHC-YETS 2017/18 Coordination meeting #22

27th February, 2018 AGENDA YETS planning follow-up Marta Alcaide Leon, Maria Barberan, Marzia Bernardini, Sebastien Bustamante

16-Jan-18

Slide2

YETS 2017-2018:

general informations

LHC coordination meeting 27th February 20182From Monday 4th December @ 6am,

to Friday 9th March (activities completed) - 1.5 wksPowering tests ph.1 from Saturday 3rd March (outside normal working hours)From 4th March: machine patrolled and in restricted modeUnlock out W10 (5th March – 9th March)LHC back to BE-OP on Friday 9th March

morning

meetings

from

Monday 12th MarchPATROLS in progressDSO tests on Friday 2nd and Saturday 3rd March  NO ACCESS IN LHC AND EXPERIMENTS!!!!IMPACT: Until 9th March intervention period YETS-LHC-2017-18From the 10th March Intervention period Operation 2018YETS coordination available  phone 161669CCC available from 26th February  phone 77600OSS website (planning, constraints, …):https://espace.cern.ch/en-dep-mef-lpc/YETS2017-18/SitePages/Home.aspxINDICO:https://indico.cern.ch/category/9286/

16-Jan-18

Slide3

LHC-YETS 2017-2018 - Version 4

LHC coordination meeting 27th February 2018

3AUG TEST

PointDayPointDayLHC1 + ATLAS

5th January (W1)

BA1

22nd January (W4)

LHC18 + SM18

11th January (W2)BA231th January (W5)LHC2 + ALICE19th February (W8)20th February (W8)BA32nd February (W5)LHC3 + PM32

17th January (W3)

BA4 + CNGS

8th February (W6)

LHC4

16th January (W3)BA512th February (W7)LHC5 + CMS 24th January (W4)BA615th January 5h00-10h00LHC61st February (W5)BA714th February (W7)LHC75th February (W6)LHC818th January (W3)PS Complex13th and 14th January (W2)Prevessin17th February (W7)BA805th March (W10)Meyrin + Adm.6th January (W1)BA816th March (W10)Meyrin W. + ISR3rd February (W5)BA82 + 857th March (W10)

TEST SECOURS (10min)AUTO TRANSFERT TESTAll points on 9th January (6am – 6:10am) (W2)No access in LHC1, LHC18, BA6 & BA7, PS Complex on 27th and 28th January (Saturday & Sunday) (W4)

16-Jan-18

NEXT WEEK

Slide4

LHC-YETS 2017-2018 main activities

LHC coordination meeting 27th February 2018

4

    CV MaintenancePoint

Weeks

Start

Finish

LHC1

50-51–52-1-211th December12th January

LHC18

3

15th January

19th January

LHC26-7-8* (cut of cryogenics cooling)5th February23th FebruaryLHC3 (in progress)926th February2nd MarchLHC42-3-48th January26th JanuaryLHC549-50–51–52-1

11th December12th JanuaryLHC66-7-8

5th February

23rd February

LHC7

9

26

th

February

2nd MarchLHC83-4-5 (cut of cryogenics cooling)15th January2nd February

 * maintenance reduced to the minimum   Cryo Maintenance (+ Reconfiguration)PointWeeksStartFinishLHC182-38th January19th JanuaryLHC2 (under discussion)7-812th February23rd FebruaryLHC4 A & B2-3-(4) & 5-6-(7)8th January16th FebruaryLHC6 A & B2-3-(4) & 5-6-(7)8th January16th FebruaryLHC8 A & B2-3-(4) & 5-6-(7)8th January16th February

16-Jan-18

Slide5

YETS 2017-2018:

open points & updates

LHC coordination meeting 27th February 20185Sector 1-2: Coax cables pulling from 20L2 & 21L2 to RE22 for BE-BI support from EN-EL(in progress)

Sector 3-4: New BPM cabling at 8L4 and 9L4  support from EN-EL (in progress)LHC5:LSS5: Request from CMS to install a passive detector under the ITs UL55: civil engineering works for lifting platform – on goingLHC 6 N2 Pressure tests OK  Line ready for commissioning and connection to dumps (Today 27/03)LHC 8 MKI8D storage16-Jan-18Light ECR requested by Anne-Laure for traceability of these changes, even if temporary

Slide6

YETS 2017-2018:

open points & updates

LHC coordination meeting 27th February 2018616-Jan-18SOLENOID installation in S. 1-2Beam Screen re-

cooldown test in 31L2  proposal 15th and 16th FebruaryGo-no-go by 19th Februaryinstallation of solenoid in 31L2 (as 16L2) from 7th to 9th MarchCabling needed for TE-EPC  EL cables pullingNew proposal from ABP to combine the solenoid with extra BLM bundlesCable installation for BLMs  proposal from 21st to 27th February (No need of EL support)BLM installation  proposal 28th February and 1st MarchELQAPOWERING TEST

Slide7

LHC coordination meeting 27th February 2018

7

The Warm Magnet Tests will be performed in 2 steps:Magnet Patrol to verify if there is any water leak  ongoingConditions needed: only demineralized water

Warm magnets heat run Conditions needed: No presence in the area, the EIS magnets will be removed from chain for this test , Demineralized water, power converters and WIC are required operational  P2 + Ti2 & P8 +Ti8  Scheduled on 26th February night  P1, P3, P5, P6 & P7  Scheduled on 5th March night YETS 2017-2018: open points & updates16-Jan-18

Slide8

LHC coordination meeting 27th February 2018

8

DocumentTitle

AuthorDocument typeStatusLHC-MW-EC-0002Radiation Shielding Installation and Possible Optics Change for the MBW and MQW Magnets in IR 3 and 7 of the LHC. Second phase LS2 LS3 and HL-LHCP. Fessia / E. Skordis P. A. Thonet ECR

Released

LHC-HHAAS-SYP-0003

Mitigation Measures during the

PM85

Lift Replacement Damien LafargeSafety Plans ProcedureReleasedLHC-LJ-EC-0045Installation of a Heavy Load Lifting Platform in USC55Michal CzechECRReleasedLHC-HHAAS-EC-0007LHC Lifts ReplacementDamien LAFARGEECRReleasedLHC-TC-EC-0009Installation of Two Wire Collimators in IP1 for Long Range Beam-Beam CompensationAdriana RossiECRReleasedLHC-TC-EC-0010Replacement of one Primary Crystal Collimator (TCPC) in IR7 - UPDATEDInigo

Lamas,

Stefano Redaelli

ECR

Released

LHC-V-EC-0006 v.0.1Modification of the Nitrogen Injection Line for LHC TDE in UD62 and UD68Eric PageECRCancelledLHC-LJ-EC-0046Relocation of Cables, Optical Fibres and Services for Connection of HL-LHC UPRs to LHCStefano BertolasiECRReleasedLHC-MKI-EC-0003Exchange of LHC Kicker Magnet MKI8DMichael BarnesECRReleasedLHC-V-EC-0007 v.0.1Removal of solenoids and installation of aC coated RF insert at the extremities of Q5R2Eric PageECRCancelledLHC-XAFP-EC-0004Maintenance of AFP DetectorM.RijssenbeekECRReleasedLHC-G-EC-0003Longitudinal Monitoring System Cryostats on Low Beta Triplet 5L and 5RAndreas HertyECRReleasedLHC-G-EC-0004Modification of Wire protection Support on DFBXAndreas HertyECRReleasedLHC-G-EC-0006Longitudinal Cryostat Monitoring System on Low Beta Triplets 1L, 1R, 2L, 2R, 8L and 8RAndreas HertyECRReleasedLHC-G-EC-0007Additional GGPSO Points for the HL-LHC Project – Technical Note approvedMathieu DuquenneECRReleasedLHC-G-EC-0008Installation of Additional GIMSA on Q2 and Q3 CryostatAndreas HertyECRReleasedLHC-V-EC-0008 Modification of Beam Vacuum Instrumentation in the Arc 1-2 - UPDATEDGiuseppe BregliozziECRReleasedLHC-TDE-EC-0003Nitrogen Pipeline to the Beam-Dump GallerieMats WilhelmssonECRReleasedLHC-BGC-EC-0001Fluorescence Measurement Test Chamber Installation – UPDATE in progressGerhard Schneider

ECRReleasedLHC-V-EC-0009New RF bridge design for the VMSIN.156.6R8.RGiuseppe BregliozziECRReleasedLHC-RF-EC-0003Upgrade of the control system for THYRISTOR controlled reactors LHC PA6K Kahle

ECR

Under Approval

LHC-BLM-EC-0009

Installation of Beam Loss Diamond Detectors in IP7 Collimator Region LHC

Belen Salvachua

ECR

Under Approval

Solenoid installation 31L2Laurent TavianECRIn workCMS installation passive box/detectorDragoslav-Laza LazicECRIn workEDMS 1906402Current derivative sensor prototypes temporary installation on the RQ5 and RQTF magnet circuit in UA27Ernesto De MatteisTest procedureUnder ApprovalLHC-XRP-EC-0013Electronic Components for Timing Detectors in Roman Pots of TOTEM & CT-PPSJoachim BaechlerECRReleased (EYETS)LHC-XRP-EC-0014CT-PPS Timing Detector installation in cylindrical Roman Pot

Joachim BaechlerECRReleased (EYETS)LHC-BRAN-EC-0001 BRAN_C Prototype for IP1 of the LHCSune JakobsenECRReleased (EYETS)*HL-LHC Major changes during YETS 2017-18 status @21st February 201816-Jan-18

Slide9

LHC

Cryogenics status

LHC coordination meeting 27th February 2018916-Jan-18Inner triplet

DateIT1R16 February IT1L

12 February

IT2R

21 February

IT2L

12 FebruaryIT5R20 FebruaryIT5L19 February

IT8L

12 February

IT8R

12 February

No Access in the ITs areasInner Triplets FILLEDSectorCryoStart1-22 March2-32 March3-45 March4-55 March5-612 March6-712 March7-85 March8-15 March

Slide10

Safety aspects for activities

LHC coordination meeting 27th February 2018

10ActivityGroup & Work site supervisorLocation

StatusDrilling for new platform in UL55SMB Christophe BiotUL55VIC on 8th FebruarySolenoid installation & related activities in 31L2TE-MSC ?

31L2

VIC 19th

February

Nettoyage

dans la zone des ItsSMBPoint 4VIC 15th FebruaryFibre for BLM pixel detector in C6L7EN-EL Antonio GonzalesLSS7VIC 20th February16-Jan-18

Slide11

LHC-YETS:

constraints (s.1-2 and s.2-3)

LHC coordination meeting 27th February 20181116-Jan-18

Slide12

LHC-YETS: recommissioning (s.1-2 and s.2-3)

LHC coordination meeting 27th February 2018

1216-Jan-18

Slide13

LHC-YETS:

constraints (s.3-4 and s.4-5)

LHC coordination meeting 27th February 20181316-Jan-18

Slide14

LHC-YETS: recommissioning (s.3-4 and s.4-5)

LHC coordination meeting 27th February 2018

1416-Jan-18Access to LSS4 required on Monday 5th for 1h max

Slide15

LHC-YETS:

constraints

(s.5-6 and s.6-7)LHC coordination meeting 27th February 20181516-Jan-18

Slide16

LHC-YETS:

Recommissioning (s.5-6 and s.6-7)

LHC coordination meeting 27th February 20181616-Jan-18

Slide17

LHC coordination meeting 27th February 2018

17

16-Jan-18LHC-YETS: constraints (s.7-8 and s.8-1)

Slide18

LHC-YETS: Recommissioning (s.7-8 and s.8-1)

LHC coordination meeting 27th February 2018

1816-Jan-18

Slide19

LHC coordination meeting 27th February 2018

19

LSS1L16-Jan-18

Slide20

All points & Point 1

LHC coordination meeting 27th February 2018

2016-Jan-18

Slide21

LHC coordination meeting 27th February 2018

21

LSS1R16-Jan-18

Slide22

Arc 1-2

LHC coordination meeting 27th February 2018

2216-Jan-18

Slide23

LSS2L

LHC coordination meeting 27th February 2018

2316-Jan-18

Slide24

Point 2

LHC coordination meeting 27th February 2018

2416-Jan-18

Slide25

LSS2R & Arc2-3

LHC coordination meeting 27th February 2018

2516-Jan-18

Slide26

LSS3 & Point 3

LHC coordination meeting 27th February 2018

2616-Jan-18

Slide27

Arc 3-4 & LSS4L

LHC coordination meeting 27th February 2018

2716-Jan-18

Slide28

Point 4, LSS4R & Arc4-5

LHC coordination meeting 27th February 2018

2816-Jan-18

Slide29

LSS5L & Point 5

LHC coordination meeting 27th February 2018

2916-Jan-18

Slide30

LSS5R

LHC coordination meeting 27th February 2018

3016-Jan-18

Slide31

Arc5-6 & LSS6L

LHC coordination meeting 27th February 2018

3116-Jan-18

Slide32

Point 6

LHC coordination meeting 27th February 2018

3216-Jan-18

Slide33

LSS6R & Arc 6-7

LHC coordination meeting 27th February 2018

3316-Jan-18

Slide34

LSS7L & Point 7

LHC coordination meeting 27th February 2018

3416-Jan-18

Slide35

LSS7R & Arc 78

LHC coordination meeting 27th February 2018

3516-Jan-18

Slide36

LSS8L & Point 8

LHC coordination meeting 27th February 2018

3616-Jan-18

COMPLETED

Slide37

LSS8R & Arc8-1

LHC coordination meeting 27th February 2018

3716-Jan-18

Slide38

Agenda next meetings

LHC coordination meeting 27th February 2018

3816-Jan-18

Week 10 – 6th MarchYETS planning & access constraints – OSS teamHandover with BE-OP Friday 9th March  CCC morning meetings from Monday

12th March

Slide39

Spare slides

LHC coordination meeting 27th February 2018

3916-Jan-18

Slide40

LHC coordination meeting 27th February 2018

40

ECR ‘Additional GGPSO Points for the HL-LHC Project’ (ECR LHC-G-EC-0007)  updated SMB team:

Write a technical note explaining the method used to visualise the pipes in point1 and point 5Report the result of the scans (with pictures where the pipes are highlighted) . In view of the scans, define the new GGPSO  locations. The technical note will be reviewed and then send for approval to SMB, CV, ACE-SU, coordination team, Integration team, DSOs, Paul Collier on behalf of LMC, Roberto Losito, Katy  Done (LHC-K-EN-0070) and approvedLSS1: GGPSO re-located, following the results of the scans  on-going

LSS5L: location confirmed 

on-going

 

Example of GGPSO

installed in the LHCSlide updated from LMC 17th January Points 1 & 5: GGPSO activities16-Jan-18

Slide41

LHC coordination meeting 27th February 2018

41

LSS1: Installation of Two Wire Collimators in IP1 for Long Range Beam-Beam Compensation EDMS LHC-TC-EC-0009 LSS1L – TCLVW.A5L1.B2 (new collimator)

Collimator installed, mechanical works, power converters installation, bake-out and water connection  completedCommissioning on-goingLSS1R – TCTW.R1.B2 (replacement of TCTPV.4R1.B2) Mechanical works, power converters installation, wire cable pulling completedDismantling TCTPV.4R1.B2 and Installation of the TCTW.4R1.B2 completedBake-out and commissioning completed LSS7: Replacement of the crystal in one Primary Crystal Collimator TCPCV.A6R7.B2

EDMS

LHC-TC-EC-0010

Definition of the replacement of the crystal collimator TCPCH.A5R7.B2 instead of TCPCV.A6R7.B2

Installation of the

TCPCH.A5R7.B2 and alignment completedBake-out on-goingCommissioning scheduled next weekBake-out TCTPV.4R1.B2 Bake-out TCLVW.A5L1.B1TCPCH.A5R7.B2 installationCollimators in LSS1 & LSS716-Jan-18

Slide42

LHC coordination meeting 27th February 2018

42

Installation scheduled next weekTest procedure EDMS 1906402

See E. De Matteis presentationInstallation plan for current derivative sensors in UA27 UA27Sensor installation16-Jan-18

Slide43

LHC coordination meeting 27th February 2018

43

Courtesy of

C.Biot – EDMS 1890832VIC performed on the 6th of February ✓ SMB-SE methodology and procedure to dig the trenches approved  SMB-SE ensures that the water pipe will not be broken during the works ✓Worksite preparation done and CE works started yesterday (Tue 20/02/2018) ✓Next Steps

End of the works planned for the

1

st

of

March 2018 (W9)A visit with EN-HE lift platform contractor is planned on W10 for trench measurements required for lift platform design finalization.EN-HE will install a cover plate to cover the trench up to LS2 and re-install firemen platformPoint 5: New lift platform in UL55 – CE works for YETS16-Jan-18

Slide44

44

LHC coordination meeting 27th February 2018

18/01: HE leak test performed with a robot and manually Leak detected at the connection flange between the Nitrogen sector and the dump core02/02 : CTD line venting for gasket replacement at the connection flange between the Nitrogen sector and the dump core

05/02 HE leak test performed with a robot and manually after replacement of the gasket  No leak detected and dump pressurized with N2 Decision to cancel TI window replacement activitiesFrom 05/02: CTD line pumping up to end of W8Courtesy

of

T.

Polzin

, D. Grenier, J. Finelle

– EDMS 1893835LHC 6: Dump activities in UD6216-Jan-18

Slide45

45

LHC coordination meeting 27th February 2018

Line + control panel installed and ready for pressure tests on 15

th February ✓Pressure test on 16/02 revealed a leak near TD62 Leak identified and welding recovered on Tue 20th Februry ✓Final(?) pressure test planned for Thursday 22nd February

Line connection with dump in UD62 and UD68 planned for the 27

th

February - still on plan

LHC 6: N2 pipes installation

16-Jan-18

Slide46

LHC coordination meeting 27th February 2018

46

All

big works completed ✓Lift test  5000 races already done

HSE

commissioning

scheduled today 21st FebruaryLift available for users on Friday 23rd February morning  

PM85 lift replacement

16-Jan-18