/
LEAK TESTING in SMACC LEAK TESTING in SMACC

LEAK TESTING in SMACC - PowerPoint Presentation

olivia-moreira
olivia-moreira . @olivia-moreira
Follow
463 views
Uploaded On 2016-11-14

LEAK TESTING in SMACC - PPT Presentation

Cold vacuum system recall Phase 1 2 amp 3 VSC activities Resources Infrastructure Still to do Paul Cruikshank on behalf of TEVSC Paul Cruikshank TEVSC Leak Testing in SMACC 3 ID: 488824

leak amp lhc vsc amp leak vsc lhc vacuum testing splice paul cruikshank smacc review nov leaks arc test

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "LEAK TESTING in SMACC" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

LEAK TESTING in SMACC

Cold vacuum system recallPhase 1, 2 & 3 VSC activitiesResources, InfrastructureStill to do......... Paul Cruikshank on behalf of TE-VSC

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide2

2

Paul Cruikshank TE/VSC Leak Testing in SMACC 3rd LHC Splice Review, 12-14 Nov ‘12Slide3

LHC arc cold vacuum systems - recall

3Paul Cruikshank TE/VSC Leak Testing in SMACC 3rd LHC Splice Review, 12-14 Nov ‘12Slide4

LHC arc cold vacuum systems - recall

4Paul Cruikshank TE/VSC Leak Testing in SMACC 3rd LHC Splice Review, 12-14 Nov ‘12Slide5

LHC arc cold vacuum systems - recall

5

LHC

magnetcryostat

QRL

cryostat

Jumpers

Vacuum

barriers

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide6

LHC arc cold vacuum systems - recall

6Paul Cruikshank TE/VSC Leak Testing in SMACC 3rd LHC Splice Review, 12-14 Nov ‘12Slide7

LHC arc cold vacuum systems - recall

7LHC cryostats were designed with DN100 ISO-K ‘pumping’ ports at vacuum subsector extremities. 300l/s turbos can be installed (and removed) without breaking vacuum

Tunnel equipment: 63 m

3

/

hr

mobile primaries – 20 units

300 l/s mobile primaries – 40 units

MS Leak detectors – 20 units

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide8

LS1 leak test

support & consolidation - cold vacuum8IC statusArc splice train

- LT supportLHC

cons- LT support

DFBA

- LT support

VSC

IV consolidation

VSC cold BV cons

Closed

(phase

1)

Degrade

IV,

Vent IV

,

LT

(80 K < T <300

K),

Localise

known He leaks,

He & RGA analysis

Vent BV, RF ball,

Open

(phase 2)

M clamshell,

Cryomagnets

,

CC, Y, Diodes

Splices

&

l

yra

,

DFBAK,

Flexibles,

Localise

He leaks (5 bar),

Vent QRL & SAM,

Flap valves,

DN200 springs &

pumpouts

,

Reclamping

of DN100 & 63,

Additional by-passes &

turbos

,

Turbo maintenance,

Pump & LT QRL

&

SAM,

PIM

temp

protection,

PIM exchange,

Rupture

discs,

RF

ball,

Pump & LT BV,

Protection shells,

Closed

(phase 3)

Pump

IV,LT envelope,LT internals,LT after PT,LT envelope,LT internals,LT after PT,LT envelope,LT internals,LT after PT,

b

efore train

t

ime window

-

typical activities in an arc

Paul Cruikshank TE/VSC Leak Testing in SMACC 3rd LHC Splice Review, 12-14 Nov ‘12Slide9

LS1 leak test

support & consolidation - cold vacuum9IC statusArc splice train

- LT supportLHC

cons- LT support

DFBA

- LT support

VSC

IV consolidation

VSC cold BV cons

Closed

(phase

1)

Degrade

IV,

Vent IV

,

LT

(80 K < T <300

K),

Localise

known He leaks,

He & RGA analysis

Vent BV, RF ball,

Open

(phase 2)

M clamshell,

Cryomagnets

,

CC, Y, Diodes

Splices

&

l

yra

,

DFBAK,

Flexibles,

Localise

He leaks (5 bar),

Vent QRL & SAM,

Flap valves,

DN200 springs &

pumpouts

,

Reclamping

of DN100 & 63,

Additional by-passes &

turbos

,

Turbo maintenance,

Pump & LT QRL

&

SAM,

PIM

temp

protection,

PIM exchange,

Rupture

discs,

RF

ball,

Pump & LT BV,

Protection shells,

Closed

(phase 3)

Pump

IV,LT envelope,LT internals,LT after PT,LT envelope,LT internals,LT after PT,LT envelope,LT internals,LT after PT,

b

efore train

t

ime window

50 %

10

%

10 %

20

%

10

%

IS Workload

-

t

ypical activities in an arc

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide10

Phase 1 leak testing

Cryostat still closed & under vacuumTightness status of arc IV and BV Under vacuum, > 80 K, He pressure constant, 3 days/arcLongitudinally localise known helium leaks (see later)

Insulation Vacuum degradation to assist warm-up

Insulation vacuum venting to tunnel air

RF ball test (see

C.Garion

presentation)

10

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide11

Phase 1 - activities

22 internal He leaks to solve 2 leaks > 10-4 mbarl/s , 12 leaks > 10-6 mbarl/s @ RTHighest priorities are: 3-4, A27L4, coldmass circuit – very large leak should be localised quickly 4-5 QRL SubS B, line C – will need dedicated intervention scenario with CRGNote: - the LHC operates with these leaks; - the 2 biggest leaks weren’t present at RT after welding and PTest; - for many of known leaks, search in 2006 & 2007 was not successful

, but they have not evolved.

- previously eliminated leaks a) at welds - incomplete, inclusions, porosity, LME, etc

b) others - shocks, inclusions, false arcs, ultrasonic vibrations,

etc

11

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide12

Longitudinal leak localisation

- which IC to open?12An under vacuum leak test in molecular flow conditions, using turbomolecular pump, mass spectrometer leak detector and helium as tracer gas.Assume linear conductance of cryostat, so C 

1/L (with & without MLI)For S >> C1 or C2:

q1/q2

C1/C2

L2/L1

For

LHC cryostats, S ~ C so apply correction for effective pumping

speed

Experience shows method is not perfect to one interconnect! Additional adjacent interconnects were often opened to

localise

the leak.

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide13

Phase 1 - Leak testing

Known internal leaks:Re-measure the known internal helium leaks before venting:Cryostat under vac, temp > 80 K, He pressure constant, Two 8 hour days per known leak with above conditions.Need CRG support to pump and pressurise circuits.Leaks in the same arc can be treated in parallelAfter venting @ RT, MSC to open 5 priority interconnects/leak (1 day).VSC will need pressure ~ 6 bar in cold mass

& c’k circuit for

2 days.Co-activity with ‘special intervention team’ needs to be co-ordinated.

13

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide14

Clamshells

– recall~20 diameters and diameter combinations for LSS standalonesNBR, polyurethane, silicone rubber, metal+mastic

14

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide15

Clamshells

Support rings for asymmetrical modelsSealing on non-perfect tube surfaces:alcohol for small defects to allow a E-8 mbar.l/s residual signal to reduce to E-10 rangemastic for bridging gaps

vacuum grease for intermediate

defects (e.g. surface scratches)Same

space

as orbital

welding

machine

15

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide16

Phase 2 - Leak testing in train

Leak test all new welds before W closure:Validate beam vacuum – new PIMsValidate 100% M welds with clamshell – 60 IC/weekValidate 100% other new welds with clamshell (new magnets, etc. )Treat non-conformities with MSC special intervention team (& MME) 16

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide17

Phase 2 - Clamshells on M

Technical challenges: ~ 10’000 M welds to clamshell Want to develop & validate a ‘long clamshell’ to test both M welds How to supply He into 214 m cold mass volume (also pump out of air)?Baseline - via one unwelded M sleeveSpecial interface tool to develop – modified clamshell,Local pumping system and backfill (~ 6 m3) from He bottle, Option 1 - v

ia M2N hose – must be cut & rewelded – 13 positions/arc

Option 2 - via QRL – when available (R2E, cryo maintenance)

Any ‘holes’ in 214 m cold mass envelope will block clamshell test (& train)

eg

M lines, N connection box at SSS, jumper, diode, DFBA

Second pass required after final M sleeve is welded

Expect between 10 to 50 leaks on M welds (installation statistics).

17

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide18

Phase 2 - LT Support - SIT & DFBA

Special intervention teamCryomagnet exchange (MB & SSS) = V, X, E, N, C’, K linesY repairs = X, CCryostat, diodes, Q6 He level gauge, Q1 braids, Clamshells and special tools existDedicated VSC team DFBAMain splices, lyras, flexible hoses - 1.9 K volume of DS

Pigtails – 4.5 K bath – independent closed He volume DFBAK HCM removal – above plus jumper & LCM interconnect,

Clamshell geometries to develop, beam vacuum equipment to remove.

Dedicated VSC team(s) IV & BV

Other challenges:

Closed volumes can be pumped and backfilled (&

pressurised

)

with He

Open volumes must be injected with He just prior to welding then

clamshelled

on-line.

18

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide19

Phase 3 - Leak testing after W closure

Evacuate & global leak test all insulation vacuum subsectors after W closure:Evacuate with mobile groupsValidate cryostat envelope – W, DN200, new magnets, reclamping, etc Validate internal helium circuits at 1 bar – M, N, new magnets, Y, etc.Need helium via QRL, all headers of sectors closed A closure rate of 60 IC/week gives ~ 12 vacuum subsectors in parallelValidate internal circuits after P.Test at 50% of design pressureTreat any non-conformities with MSC special intervention team & CRG

Duration of 2-3 weeks/vacuum subsector – expect 0 - 3 internal leaks/arc.

19

Leak imported from phase 2:

Clamshell not possible,

Clamshell poor sensitivity,

Interconnection damage

Leak opened by

outgassing

or

Leak opened by

P.Test

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide20

Documentation

Procedures:Existing procedures for arc & LSS leak testingExisting maintenance procedures for pumping groupsExisting procedures for vacuum degradationExisting procedure for relief spring installationNeed to produce generic procedure for clamshell testsData storage: Use of WISH tool to define status of leak test tasks Create NCR in edms

in case of leak and attach to WISH step Maintain test/activity details in VSC Excel files – who, what, when,

Team leaders in the tunnel send daily reports

Maintain overview table of subsector status,

List of known He leaks – NCR in

edms

20

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide21

Resources summary

VSC Staff2 Engineers, 1 Fellow, 5 techniciansVacuum support contract S13314 industrial support staff required for ins vacuum system (& B.Vac) arc activities in 2013, then reduction will depend on agreed planning.FSU support (FSU-TE-09,S145)0.5 additional workshop mechanic for PIM activity (+0.5 for expts)Polish collaboration

6 eng/technical staff for cold beam vacuum interconnect QA

inspection at opening/closing, beam vac temporary protection,

endoscopy at PIM cutting positions

install protection shells

All will require safety training, access training, safety equipment..........

21

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide22

Infrastructure needs

Bungalows/office space:Office space at even points only (shared with VSC-LBV)CERN wireless intranet & telephoneQA, doc, tech meeting, storage of sensitive equipment Polish Collaboration – all equipment provided by VSCcars, bikes, trailers, safety equip, PC, camerasPEFRA;3 dedicated VSC

Pefra at each even point from tunnel access date.for mobile pumping groups, detectors, tooling – shared with LBV.

Dedicated VSC/EIV logistics zone on surface:

At each even point, 5m2 storage & 14 bicycles & 5 trailers.

22

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide23

Still to do in 2012

Optimise phase 1, 2 & 3 activities with SMACC & LS1 coordination Complete inventory of SIT & DFBA tasks Continue procurement of additional clamshells Develop tooling for helium injection at unwelded M sleeve. Expand, integrate, equip & train IS, FSU, & PL teams

Create ECRs

Complete QA procedures

Complete PPSPS, Safety Folder, DIMR,

Other?

23

Paul Cruikshank TE/VSC Leak Testing in SMACC 3

rd

LHC Splice Review, 12-14 Nov ‘12Slide24

Thanks for your attention.

24Paul Cruikshank TE/VSC Leak Testing in SMACC 3rd LHC Splice Review, 12-14 Nov ‘12Slide25

VSC Consolidation – Insulation Vacuum

25Paul Cruikshank LS1 Preparation - Insulation Vacuum 20th June 2012ActivityAreaMotivation(1/impact if not done)Other Groups Affected

Potential conflict with splice consolidation

Install Flap

Valves

arcs, LSS, QRL

Self closing over pressure valves

 

no

Install by-pass valves

arcs 2-3, 7-8, 8-1

Pumping

redundancy

 

no

Install additional

turbos

(& cables

)

QRL extremities

Pumping

redundancy

EL

no

Install long cable for

turbos

IR3R - LSS3

Eliminate

remote-restart

problem

EL

no

Localise and repair known leaks

all arcs

Eliminate helium leaks

MSC, CRG

yes

Leak test envelopes

cryostat & He

(before

& after

splice repairs)

arcs, LSS, QRL

Check tightness integrity

CRG

yes

Maintain turbo pumping groups

arcs, LSS

Maintenance - preventive and corrective

 

no

Inspect

beam screen capillary

arc 8-1

Understand

origin of

helium leak

 

no

Repair

gauge cabling in mid

arcs

all arcs

Eliminate faulty gauge reading

 

no

Add pump-out

ports

all

arcs

Increase pumping speed

in case of helium leaks

MSC

no

Finalise

‘auto-restart’

All arcs

Restart

turbos

after

p.cut

no

Minor taskSlide26

VSC Support – Insulation Vacuum

26Paul Cruikshank LS1 Preparation - Insulation Vacuum 20th June 2012ActivityAreaMotivationOther Groups Affected

Comments

Splice consolidation

All arcs

Busbar

non-conformities

Train activity

Cryomagnet replacement

All arcs

Except 5-6,6-7

Various non-conformities

MSC

s

pecial

intervention team

IR3 DS - bypass cryostat for collimators

Postponed

SMI2 proto

Connnection cryostat consolidation

TBC

Busbar

protection

MSC

s

pecial

intervention team

Y-Lines repair

All arcs?

Cryo

performance

MSC

s

pecial

intervention team

New

DN200,

Re-clamping

of

inst

flanges

2-3, 7-8, 8-1,

All

arcs

Safety

conformity

MSC

s

pecial

intervention team

SAM helium gauge consolidation

6R2,

6L8

Cryo

control

MSC

s

pecial

intervention team

Triplet braid

LSS1

& 5

Cryo

performance

MSC

s

pecial

intervention team

DFBA

consolidation

All arc ?

Busbars

& braids

?

These projects will require extensive VSC leak testing/technical support

Are they already in ‘PLAN’ ?Slide27

VSC Consolidation – Cold Beam Vacuum

27Paul Cruikshank LS1 Preparation - Insulation Vacuum 20th June 2012ActivityAreaMotivationOther Groups Affected

Potential conflict with splice consolidation

Exchange/repair PIMS

Arcs, LSS

Eliminate critical PIMs

MSC

yes

Install

beam vac.

protection

shells

Arcs, LSS

Protection against electrical arcs

MSC

yes

Exchange S3-4 beam screens with reversed saw teeth

Arc 3-4

Dynamic

vacuum effects

MSC,EL,SU

Yes

Install additional rupture

disc

Arcs

SSS, LSS

Protect

beam vac.

against overpressure

 

no

Leak test envelope- arc, LSS

Arcs, LSS

Check tightness integrity

 

yes

Install/remove mobile pumping groups

Arcs, LSS

Remove desorbed gas/recondition

 

no

Install additional gauges in arcs

Arcs

Consolidate instrumentation

EL

no

RF ball test

Arcs

Aperture check

no

Faster closing of some

sector valves

Pneumatics modification

Arcs

Reduce

debris propagation

no

Low priority

Due to synergies, some VSC resources are shared between insulation & beam vacuum arc activities Slide28

VSC Consolidation – Insulation Vacuum (not in tunnel)

28Paul Cruikshank LS1 Preparation - Insulation Vacuum 20th June 2012ActivityAreaMotivationOther sections Affected

Potential conflict with splice consolidation

Profibus interface on mobile

turbos

(41) & primaries (20)

Remote visibility/operation

of mobile groups

 

ICM

Rebuild 10

mobile pumping groups with offset electronics

Radiation

hard groups in case of helium leaks

ICM

 

Equip 14 MB + 5 SSS +

undulator

with beam screens

Replacement

cryomagnets

In advance of LS1

Activities outside tunnel are also added to ‘PLAN’ to have overview of all resource needs..........Slide29

Clamshells on M lines (1)

Why weren’t M line clamshells adopted during LHC installation ?Many ‘holes’ in 214 m cold mass chain (late magnets, NCR, ELQA, etc) – late clamshell tests would stop series W closure.Masked time was available to treat leak non-conformities after W closure.Was less leak testing parallelism per arc and per sector.Why adopt M line clamshells for splice consolidation?Early feedback on weld quality in advance of W closureLittle masked time available to treat leak non-conformities in global testWhole arc is closed in 4 weeks – twice rate of LHC installation peak

(Most) leak identification & repair is removed from critical path

In proposed LS1 planning, clamshells can be performed in masked time.If no M clamshell test – foresee several additional NC weeks in global test

29

Paul Cruikshank LS1 Preparation - Insulation Vacuum 20

th

June 2012