Project 1 Equipment Type Manufacturer Power o utput Last outage N ext outage Gas turbine MS 6001FA GE 70MW May 2011 66535 operational hours HGPI 74535 operational hours ID: 275752
Download Presentation The PPT/PDF document "Technical information of" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Technical information of Project 1
EquipmentTypeManufacturerPower outputLast outageNext outageGas turbineMS6001FAGE70MWMay 201166.535 operational hours (HGPI)74.535 operational hours (CI)Steam turbineDK 080/280MAN26MWNov 2012 70.933 operational hours (Major Overhaul)120.000 operational hours (Major Overhaul)GeneratorT24370GEC Alstom113MVA (10,5kV)Sept 200643.439 operational hours (Major Overhaul)Planned in 2013(Major Overhaul postponed due to suspention of operation)HRSG DBMA (Spain)HP steam: 540°C / 106 bar / 110t/hLP steam: 300°C / 7 bar / 20 t/h
1
Output:
95MW
el
, 90MW
th
Total operational hours:
72.182
Number of Shutdown:
230
Commissioning: 31
th
of Jan in 2001
Equipment layout: single
shaft
layout
(GT-Generator-ST)Slide2
Technical information of Project 2
EquipmentTypeManufacturerPower outputLast outageNext outageGas turbineH25 AXHitachi30,1MWMay 2012 32.990 operational hours(HGPI)50.490 operational hours (CI)Steam turbineSST 600/VE40Siemens22,6MWNov 201125.681 operational hours (Forced Major Overhaul)74.000 operational hours (Major Overhaul)GeneratorSGen5-110A-4pSiemens37 MVA (10,5kV)29 MVA (10,5kV)May 201230.215 operational hours (Minor overhaul)96.000 operational hours (Major Overhaul)HRSG Steam Gen 6AalborgHP steam: 540°C / 94 bar / 99t/hLP steam: 310°C / 10 bar / 3 t/h
2
Output:
47MW
el
, 64MW
th
Total operational hours:
36.114
Number of Shutdown:
51
Commissioning: 17
th
of July in 2007
Equipment layout:
2
shaft
layout
(each turbine has own generator)