Flow-based capacity calculation, pre-coupling Flow-based capacity calculation, pre-coupling

Flow-based capacity calculation, pre-coupling - PowerPoint Presentation

payton
payton . @payton
Follow
68 views
Uploaded On 2023-11-08

Flow-based capacity calculation, pre-coupling - PPT Presentation

Nordic CCM Stakeholder Meeting July 1 2021 Jakob Glarbo Møller jlmnordicrscnet Outline Background on NorCap project What is parallel run How are we doing so far NorCap Intro ID: 1030726

flow based parallel run based flow run parallel capacity norcap domains methodology security allocation market calculation validation ntc process

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Flow-based capacity calculation, pre-cou..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

1. Flow-based capacity calculation, pre-couplingNordic CCM Stakeholder Meeting July 1, 2021Jakob Glarbo Møllerjlm@nordic-rsc.net

2. OutlineBackground on NorCap projectWhat is parallel run?How are we doing so far?

3. NorCap IntroBackgroundBlack-out in Central Europe in 2006 -> EU makes forming RSCs across TSOs mandatoryFlow-based (FB) capacity allocation calculation is expected to better represent limits to operational security PurposeTo implement the capacity calculation methodology based on the Flow-based methodology instead of the currently used NTC methodology.

4. NorCap High Level ProcessIntraday and Day ahead processesIGMCGMFlow-based calculationCapacity/ domain validation MITEuphemiaIGMIGMATCextractionIGMDA (FB)XBIDFlow-based parametersNTC and AACNTC and AAC

5. What is parallel run?Market capacities are still based on NTC method (as today)The process for flow-based capacity allocation runs at the same timeGoal:Demonstrate stable processDemonstrate adequate data qualityAssess impact on socio-economic welfareBuild experience with the new process and methodologyInternal parallel run:Flow-based security domains are sent to SA WG to simulate market clearing and assess socio-economic welfareExternal parallel run:Flow-based security domains are sent to SA WG, NEMOs and external stakeholders (published through the Joint Allocation Office)

6. Internal parallel Run Started on May 25thCGM and CCC processes are running for 5 full days per week (4 weekdays + 1 weekend day)TSO domain validation is done as part of NUAT (software acceptance test)Calculated flow-based domains are sent to SA WG for market analysis.

7. IPR preliminary results