Current Rigging Items Large Trunion Upper Yoke Eyebrow Ring When Horizontal KeysYokeOutriggerRoller Assembly Small Trunion Upper Keys Lower Keys Lifting Attachment RingPolePlug Assembly ID: 787262
Download The PPT/PDF document "Removal and Repurpose of Central Magnet" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Removal and Repurpose of Central Magnet
Slide2Current Rigging Items
Large
Trunion
Upper Yoke
Eyebrow Ring (When Horizontal)
Keys/Yoke/Outrigger/Roller Assembly
Small
Trunion
Upper Keys
Lower Keys
Lifting Attachment
Ring/Pole/Plug Assembly
Russian Drawing
Need to Fabricate
Russian Drawing
Need to Fabricate
No
T
echnical Drawing
Part is in Boneyard
Slide3Upper Yoke
Approx. locations of lifting
trunions
(on opposite side as well)
Rigging
4X Large
Trunions
(Ø 280mm)
4X Appropriate
slings
Approx. 62 Tons
Slide4Upper Yoke
Approx. locations of lifting
trunions
(on opposite side as well)
Slide5Upper Yoke
Rigging
4X Large
Trunions
(Ø 280mm)
4X Appropriate slings
Slide6Upper Yoke & Upper Keys
Approx. locations of lifting
trunions
(on opposite side as well)
Rigging
4X Large
Trunions
(Ø 280mm)
4X Appropriate slings
Slide7Upper Yoke & Upper Keys
Slide8Upper Keys
Rigging
4X Small
Trunions
(Ø 120mm)
4X Appropriate
slings
Approx. 15 Tons each
Approx. locations of lifting
trunions
Exterior
Interior
Slide9Eyebrow Ring/Pole/Plug
Rigging
Lifting Attachment
2X Appropriate
slings
Approx. 102 Tons each
Placement of Lifting Attachment
Slide10Eyebrow Ring/Pole/Plug
Slide11Eyebrow Ring/Pole/Plug cont’d
Slide12Eyebrow Ring/Pole/Plug Disassembly
Thru Holes for Pole Piece Attachment
Rigging Process
Remove bolts that attach plug to pole piece
Lift plug out of pole piece (7.8 US TON)
Remove bolts that attach eyebrow ring to pole piece
Lift eyebrow ring off of pole piece (46 US TON)
Lift pole piece (48.1 US TON)
Slide13Eyebrow Ring/Pole/Plug Disassembly
Slide14Coil Weights
Inner Coil 1055
lb
x 3=
3165
lbs
Outer Coil=
8826
lbs
Retainer Rings
Inner Ring 412 x 4=
1648
lbs
Outer Ring 1284 x 2=
2568
lbs
Slide16Yoke/Keys/Outriggers/Rollers
Rigging
4X Large
Trunions
(Ø 280mm)
4X Appropriate
slings
Approx. 113 Tons
Approx. locations of lifting
trunions
(on opposite side as well)
Slide17Yoke/Keys/Outriggers/Rollers
Slide18Backup Slides
Eyebrow Ring (~ 46 US Ton)
Thru Holes for Pole Piece Attachment
Ø 52mm
Slide19Backup Slides
Pole Piece Center (~ 48.1 US Ton)
M48x5
M48x5
Eyebrow Ring Attachment Point
Pole Piece Plug Attachment Point
Slide20Backup Slides
Pole Piece Plug ( ~7.8 US Ton)
Ø52mm thru holes
Thru Hole for Pole Piece Center Attachment
Slide21Backup Slides
Slide22Backup Slides
Slide23Backup Slides