Download The PPT/PDF document "ELENA Project January 14, 2016" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
ELENA Project
January 14, 2016
Installation follow-up
1
Erwan Harrouch EN-MEF
Slide2Cable identification for the TL installation
January 14, 2016
Erwan Harrouch EN-MEF
2
Situation :
Very tight schedule for the TL installation. (~9month with very small margin)
Cabling activities :
3 months of
decabling
/ 2 month of cabling
Slide3Cable identification for the TL installation
January 14, 2016
Erwan Harrouch EN-MEF
3
Proposition :
Identification and labeling of all the cables concerned by the de-cabling campaign
By who : Equipment owner
When : March
2016
Goal : Save time during the transfer line installation and allow EN-EL to prepare the campaign
CODEDESCRIPTION
B..ABEAM OBSERVATION (AD)
BCTC
TRANSFO DE COURANT (AD)
BL.A
BEAM OBS. MONITORS (AA)
BRPA
BEAM OBS PU PATCH-PANEL
BRSC
? ANCIEN CODE ANNULE
BTVA
BTV (AD)
BWCA
CHAMBRES A FILS (AD)
CV.A
TV MACHINE AD
ER.M
BT RESEAU CONVERTISSEUR
M..A
AIMANTS (AA)
MMDA
INTERLOCKS AIMANTS (AD)
MP.A
ALIM AIMANT (AD)
R..A
POWER SUPPLIES (AA)
RC.P
CONTROLE ALIMENTATION (AD)
TBSA
BEAM STOPPER (AD)
VG.A
JAUGES VIDES (AD)
VP.A
POMPES VIDES (AD)
VRSA
SUBLIMATEURS (AD)
VV.A
VANNES VACUUM (AD)
XASA
AD/LIGNE EXPERIENCE ASACUSA
YA.A
SECURITE ACCES (AD)
Slide4Worksite follow-up
January 14, 2016
Erwan Harrouch EN-MEF
4
Mechanical support installation
Sealing done
(Drying on-going)
Alignment tables installed : 6/6 sectors done!
LNI tables remain to be installedBTV Support delivered,
status of the kicker support to be clarified?
Slide5January 14, 2016
Erwan Harrouch EN-MEF
5
Source re-installation
The
gaz
panel is relocated.
Are the pipes cut high enough?
Metallic plate cut
Meeting at 3.30 with EN-CV to arrange the supporting of the pipeWorksite follow-up
Slide6Worksite follow-up
January 14, 2016
Erwan Harrouch EN-MEF
6
Reception of the cables on-going 75% done without major issue
Next campaign in February for DC cables and Remaining control cables (~300)
Cable to AD pulled, reception done
Slide7Worksite follow-up
January 14, 2016
Erwan Harrouch EN-MEF
7
Optic fiber installation on-going
Panel relocated
VIC done to pull the optic fiber from the power room (work planned for week 4)
LV
installation and IT Installation :
IT works : completed?
LV Works completed : Tests to be doneStart of installation of the power sockets in two weeksFirst step : Prototyping and marking of the position
Slide8Worksite follow-up
January 14, 2016
Erwan Harrouch EN-MEF
8
SMB-SE works
Side platform being modified
Reinstallation by next week
Modification of the false floor by next week
Support of the
Btrain magnet : To be done before the 15th of February
Courtesy to O. Choisnet
Slide9Closure of the shielding wall
January 14, 2016
Erwan Harrouch EN-MEF
9
Modification of the opening for the vacuum chamber (delivery date : 1/3/2016)
Marking of the vacuum chamber foreseen by the end of the week to give the greenlight for closure
Slide10LNI Installation update
January 14, 2016
10
MGNLG and MQNAF installation postponed to February
Vacuum sector ready on the 14/03 - 1week of margin (No changes)
Slide11Gbar
bunker installation
January 14, 2016
Erwan Harrouch EN-MEF
11
Delivery of the LEP Yoke will start on the
18/01/2016?
Order of the standard block is being completed
Marking of the bunker will start next week
Slide12Summary of next week
January 14, 2016
12
LV Installation (R. Necca)
Prototyping and ground marking for the ring power sockets
Mechanical support installation (A. Kolehmainen)
Alignment
tables
installation for LNI
LNI installation (E. Harrouch)Closing of the shielding Gbar bunker installation
Cleaning of the area (E. Harrouch)Ground marking of the bunker (T. Dobers)Source Installation (A. Megia)Completion of the source installation
Erwan Harrouch EN-MEF
Slide13Planning update
January 14, 2016
Erwan Harrouch EN-MEF
13
TE-EPC (Date are being checked)
HV
power converters installation is postponed to the 1/6/2015
Installation of the software for
1/6/2015
LNI planning is now in line with the magnet delivery scheduleTE-ABTFast deflectors installation postponed to the 08/02
Doublet+SEM installation strategy needs to be definedEN-CVCV installation in the power room is postponed to the 15 of FebruaryBE-BIInstallation date of ELENA BTV is not defined yet (delay expected)Tune installation, date of installation not completely clear yet. Set to the 1
st of April (at the latest estimation)Delay on the delivery of the BPM expected (Impact on the schedule to be studied)TE-MSCMagnet installation sequence is updated for JanuaryInstallation schedule of the Correctors magnets needs a close look
GeneralThe installation strategy of equipment under vacuum need to be studied The hardware tests need to be integrated to the planning