ELENA Project January 14, 2016 ELENA Project January 14, 2016

ELENA Project January 14, 2016 - PowerPoint Presentation

reportssuper
reportssuper . @reportssuper
Follow
343 views
Uploaded On 2020-08-28

ELENA Project January 14, 2016 - PPT Presentation

Installation followup 1 Erwan Harrouch ENMEF Cable identification for the TL installation January 14 2016 Erwan Harrouch ENMEF 2 Situation Very tight schedule for the TL installation 9month with very small margin ID: 810008

2016 installation january harrouch installation 2016 harrouch january erwan mef week follow power marking support vacuum lni date postponed

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "ELENA Project January 14, 2016" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

ELENA Project

January 14, 2016

Installation follow-up

1

Erwan Harrouch EN-MEF

Slide2

Cable identification for the TL installation

January 14, 2016

Erwan Harrouch EN-MEF

2

Situation :

Very tight schedule for the TL installation. (~9month with very small margin)

Cabling activities :

3 months of

decabling

/ 2 month of cabling

Slide3

Cable identification for the TL installation

January 14, 2016

Erwan Harrouch EN-MEF

3

Proposition :

Identification and labeling of all the cables concerned by the de-cabling campaign

By who : Equipment owner

When : March

2016

Goal : Save time during the transfer line installation and allow EN-EL to prepare the campaign

CODEDESCRIPTION

B..ABEAM OBSERVATION (AD)

BCTC

TRANSFO DE COURANT (AD)

BL.A

BEAM OBS. MONITORS (AA)

BRPA

BEAM OBS PU PATCH-PANEL

BRSC

? ANCIEN CODE ANNULE

BTVA

BTV (AD)

BWCA

CHAMBRES A FILS (AD)

CV.A

TV MACHINE AD

ER.M

BT RESEAU CONVERTISSEUR

M..A

AIMANTS (AA)

MMDA

INTERLOCKS AIMANTS (AD)

MP.A

ALIM AIMANT (AD)

R..A

POWER SUPPLIES (AA)

RC.P

CONTROLE ALIMENTATION (AD)

TBSA

BEAM STOPPER (AD)

VG.A

JAUGES VIDES (AD)

VP.A

POMPES VIDES (AD)

VRSA

SUBLIMATEURS (AD)

VV.A

VANNES VACUUM (AD)

XASA

AD/LIGNE EXPERIENCE ASACUSA

YA.A

SECURITE ACCES (AD)

Slide4

Worksite follow-up

January 14, 2016

Erwan Harrouch EN-MEF

4

Mechanical support installation

Sealing done

(Drying on-going)

Alignment tables installed : 6/6 sectors done!

LNI tables remain to be installedBTV Support delivered,

status of the kicker support to be clarified?

Slide5

January 14, 2016

Erwan Harrouch EN-MEF

5

Source re-installation

The

gaz

panel is relocated.

Are the pipes cut high enough?

Metallic plate cut

Meeting at 3.30 with EN-CV to arrange the supporting of the pipeWorksite follow-up

Slide6

Worksite follow-up

January 14, 2016

Erwan Harrouch EN-MEF

6

Reception of the cables on-going 75% done without major issue

Next campaign in February for DC cables and Remaining control cables (~300)

Cable to AD pulled, reception done

Slide7

Worksite follow-up

January 14, 2016

Erwan Harrouch EN-MEF

7

Optic fiber installation on-going

Panel relocated

VIC done to pull the optic fiber from the power room (work planned for week 4)

LV

installation and IT Installation :

IT works : completed?

LV Works completed : Tests to be doneStart of installation of the power sockets in two weeksFirst step : Prototyping and marking of the position

Slide8

Worksite follow-up

January 14, 2016

Erwan Harrouch EN-MEF

8

SMB-SE works

Side platform being modified

Reinstallation by next week

Modification of the false floor by next week

Support of the

Btrain magnet : To be done before the 15th of February

Courtesy to O. Choisnet

Slide9

Closure of the shielding wall

January 14, 2016

Erwan Harrouch EN-MEF

9

Modification of the opening for the vacuum chamber (delivery date : 1/3/2016)

Marking of the vacuum chamber foreseen by the end of the week to give the greenlight for closure

Slide10

LNI Installation update

January 14, 2016

10

MGNLG and MQNAF installation postponed to February

Vacuum sector ready on the 14/03 - 1week of margin (No changes)

Slide11

Gbar

bunker installation

January 14, 2016

Erwan Harrouch EN-MEF

11

Delivery of the LEP Yoke will start on the

18/01/2016?

Order of the standard block is being completed

Marking of the bunker will start next week

Slide12

Summary of next week

January 14, 2016

12

LV Installation (R. Necca)

Prototyping and ground marking for the ring power sockets

Mechanical support installation (A. Kolehmainen)

Alignment

tables

installation for LNI

LNI installation (E. Harrouch)Closing of the shielding Gbar bunker installation

Cleaning of the area (E. Harrouch)Ground marking of the bunker (T. Dobers)Source Installation (A. Megia)Completion of the source installation

Erwan Harrouch EN-MEF

Slide13

Planning update

January 14, 2016

Erwan Harrouch EN-MEF

13

TE-EPC (Date are being checked)

HV

power converters installation is postponed to the 1/6/2015

Installation of the software for

1/6/2015

LNI planning is now in line with the magnet delivery scheduleTE-ABTFast deflectors installation postponed to the 08/02

Doublet+SEM installation strategy needs to be definedEN-CVCV installation in the power room is postponed to the 15 of FebruaryBE-BIInstallation date of ELENA BTV is not defined yet (delay expected)Tune installation, date of installation not completely clear yet. Set to the 1

st of April (at the latest estimation)Delay on the delivery of the BPM expected (Impact on the schedule to be studied)TE-MSCMagnet installation sequence is updated for JanuaryInstallation schedule of the Correctors magnets needs a close look

GeneralThe installation strategy of equipment under vacuum need to be studied The hardware tests need to be integrated to the planning