/
MQXFA1M Status Update Dan Cheng, et al MQXFA1M Status Update Dan Cheng, et al

MQXFA1M Status Update Dan Cheng, et al - PowerPoint Presentation

shoulderheinz
shoulderheinz . @shoulderheinz
Follow
342 views
Uploaded On 2020-06-30

MQXFA1M Status Update Dan Cheng, et al - PPT Presentation

3 20 2017 MQXFA1M Schedule Highlights Approximately 4 weeks to work on MQXFA1M 417 The halflength ShellYoke assemblies are complete and have been tensioned w ith full length tomorrow ID: 790822

mqxfa1m coil complete pack coil mqxfa1m pack complete yoke progress hardware assembly dummy shell fuji completed schedule saves week

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "MQXFA1M Status Update Dan Cheng, et al" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

MQXFA1M Status Update

Dan Cheng, et al

3

/20/

2017

Slide2

MQXFA1M Schedule Highlights

Approximately

4

weeks to work on MQXFA1M (~4/17)

The half-length Shell-Yoke assemblies are

complete

and have been tensioned w

ith full

length tomorrow

yoke rods

Coil GPI

on

dummy coils

was completed last

week

CERN SG instrumentation was completed last week; offsets taken

Opportunities to accelerate schedule:

Removed

a Fuji build

to save

~2 weeks

Dummy build with 2

nd

Fuji paper will stay with the bladder ops of MQXFA1M (see CERN presentation 2/15 for precedent)

Will remove

the axial loading operation from the dummy assembly

Expect to disassemble MQXFA1M just before, or during

the week of Collaboration Meeting

Slide3

MQXFA1M Yoke-Shell Assembly

The Shell-Yoke should

has been completed

Slide4

MQXFA1M Coil Prep

Dummy Coil Pack Assembly:

Collars and load pads prep work: Complete

Dummy Coil SG (LARP & CERN) 100

% complete

Coil

GPI shims

complete

Slide5

MQXFA1M Dummy Coil Pack

Collar shims

are complete

Eliminated one Fuji Assembly

Final Dummy coil pack assembly complete: Mar

31

Slide6

MQXFA1M Integration

Axial rod instrumentation to be

completed this week

Azimuthal

preload

complete:

4/

11

Eliminating Survey and Axial loading

saves ~5-7 days

Risk is that we won’t have a procedure or baseline to compare to

Magnet

Disassembly can start

~before collaboration meeting

Slide7

MQXFA1 Schedule Highlights

Approximately 6 weeks to work on MQXFA1 after Readiness Review 4/

28 (though we will not wait to proceed if in position to)

Schedule is

not

very

compressible, but

we have options:

Currently planning two Fuji Paper coil packs before final coil pack assembly, but will try to eliminate one build; saves approx. 5 daysLikely we will not survey this magnet (saves approx 4 days)NOTE: Real coil preparations may fall into critical pathMust be completed by mid April for MQXFA1 Fuji assembliesCoil CMM and elecrical

QC

complete

Coil

Instrumentation, GPI, and

final QC

must be completed afterTech for instrumentation is not yet settled (will be soon!)

Slide8

MQXFA1 Projected schedule update

Overtime

will

be used to expedite certain

processes

Connector skirts and wiring harness/pigtail will be

outsourced

Currently planning two Fuji Paper coil packs before final coil pack assembly, but will try to eliminate one build;

saves approx. 5 days

Likely we will not survey this magnet (

saves approx 4 days

)

This, and MQXFA1M optimizations can move ship

date ~3+ weeks to ~6/16

Slide9

Yoke and Shell Parts and hardware progress

Slide10

Yoke and Shell Parts and hardware progress

Slide11

Yoke and Shell Parts and hardware progress

Slide12

Yoke and Shell Parts and hardware progress

Slide13

Coil Pack and hardware progress

Slide14

Coil Pack and hardware progress

Slide15

Coil Pack and hardware progress

Slide16

Coil Pack and hardware progress

Slide17

Magnet Assembly Process Flow