/
Chapter 7 Rate of Return Analysis Chapter 7 Rate of Return Analysis

Chapter 7 Rate of Return Analysis - PowerPoint Presentation

stefany-barnette
stefany-barnette . @stefany-barnette
Follow
397 views
Uploaded On 2018-03-12

Chapter 7 Rate of Return Analysis - PPT Presentation

1 Chapter Contents Internal Rate of Return Rate of Return Calculations Plot of NPW versus interest rate i Fees or Discounts Examples Incremental Analysis Using Spreadsheet 2 Engineering Economics ID: 648274

engineering economics 000 rate economics engineering rate 000 irr return cash year 200 interest alternative analysis question 175 800

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Chapter 7 Rate of Return Analysis" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Chapter 7Rate of Return Analysis

1Slide2

Chapter ContentsInternal Rate of Return Rate of Return Calculations

Plot of NPW versus interest rate

i

Fees or DiscountsExamplesIncremental AnalysisUsing Spreadsheet

2

Engineering EconomicsSlide3

Rate of return analysis is the most frequently used exact analysis technique in industry.Major advantagesRate of return is a single figure of merit that is readily understood.Calculation of rate of return is independent from the

minimum attractive rate of return

(

MARR).Rate of Return Analysis

3

Engineering EconomicsSlide4

Internal Rate of ReturnWhat is the internal rate of return (IRR)?IRR is the interest rate at which present worth or equivalent uniform annual worth is equal to

0.

In other words, the internal rate of return is the interest rate at which

the benefits are equivalent to the costs.

4

Engineering EconomicsSlide5

Internal Rate of ReturnInternal rate of return is commonly used to evaluate the desirability of investments or projects.

IRR can be used to rank multiple prospective projects.

Because the internal rate of return is a rate quantity, it is an indicator of the efficiency, quality, or yield of an investment.

To decide how to proceed, IRR will be compared to preselected minimum attractive rate of return (Chapter 8)

5

Engineering EconomicsSlide6

6 Given a cash flow stream, IRR is the interest rate i which yields a

zero NPW

(i.e.,

the benefits are equivalent to the costs), or a zero worth at any point in time. This can be expressed in 5 different ways as follows.

NPW = 0

PW of benefits

– PW

of

costs = 0

PW of benefits = PW of costs

PW of

benefits/PW

of

costs = 1

EUAB – EUAC = 0

Internal Rate of Return (IRR)

Engineering EconomicsSlide7

ExampleA person invests $1000 at the end of each year. If the person would like to have $80,000 in savings at EOY 26 what interest rate should he select?

When the compound interest tables are visited the value of

i

where (F/A,

i

%, 26)=80 is found as 8%, so

i

=8%

Checking the Tables

26 yrs @ 6%, F/A = 59.156

26 yrs @ 10%, F/A = 109.182

26 yrs @ 8%, F/A = 79.954

7

Engineering EconomicsSlide8

ExampleA person invests $1000 at the end of each year. If the person would like to have $80,000 in savings at EOY 26 what interest rate should he select?

When the compound interest tables are visited the value of

i

where (F/A,

i

%, 26)=80 is found as 8%, so

i

=8%

Checking the Tables

26 yrs @ 6%, F/A = 59.156

26 yrs @ 10%, F/A = 109.182

26 yrs @ 8%, F/A = 79.954

8

Engineering EconomicsSlide9

Example – EXCEL solutionRATE(n, A, P,

F, type, guess

)

rate(26, 1000, 0, -80000) = 8%

rate (26, -1000, 0, 80000)

= 8%

A, P, F must have different signs (+ or –)!

IRR

(

value range

,

guess

)

value range = the cash flow stream

9

Engineering EconomicsSlide10

ExampleCash flows for an investment are shown in the following figure. What is the IRR to obtain these cash flows?

YEAR

CASH FLOW

0

($500)

1

$100

2

$150

3

$200

4

$250

10

Engineering EconomicsSlide11

EXAMPLE CONTINUES

-8.85

YEAR

CASH FLOW

0

($500)

1

$100

2

$150

3

$200

4

$250

11

Nov. 2, 2011

Engineering EconomicsSlide12

QUESTION CONTINUES

-8.85

12

Nov. 2, 2011

Engineering EconomicsSlide13

INTERPOLATION

5%

15%

X%

30.95

-8.85

5-X

30.95

10

39.80

0

13

Engineering EconomicsSlide14

INTERPOLATION

5%

15%

X%

30.95

-8.85

5-X

30.95

-10

39.80

0

14

Engineering EconomicsSlide15

INTERPOLATION

12%

15%

X%

3.350

-8.850

12-X

3.350

-3

12.200

0

15

Engineering EconomicsSlide16

INTERPOLATION

12%

15%

X%

3.350

-8.850

12-X

3.350

-3

12.200

0

16

Engineering EconomicsSlide17

EXCEL solution IRR(C1:C5) = 12.83%

C1 ~ C5 stores the stream of the 5 cash flows:

-500, 100, 150, 200, 250

17

Engineering EconomicsSlide18

Example A student, who will graduate after 4 years, borrows $10,000 per year at 5% interest rate at the beginning of each year. No interest is charged till graduation. If the student makes five equal annual payments after the graduation (end-of-period payments

).

a)

What is each payment after the graduation?

b) Calculate IRR of loan?

(hint: use cash flow from when the student started borrowing the money to when it is all paid back)

c)

Is the loan attractive to the student?

18

Engineering EconomicsSlide19

EXAMPLE CONTINUESYear

Cash Flow

0

10,000

1

10,000

2

10,000

3

10,000

4

0

5

(9240)

6

(9240)

7

(9240)

8

(9240)

9

(9240)

a)

b)

19

Engineering EconomicsSlide20

INTERPOLATION:

c)

Since the rate is low, the loan

looks

like a good

choice.

20

Engineering EconomicsSlide21

INTERPOLATION:

c)

Since the rate is low, the loan

looks

like a good choice

21

Engineering EconomicsSlide22

a) pmt(5%, 5, -40000) = $9,238.99 per month.

b)

irr

(g1:g10) = 2.66%.

c)

Since the rate is low, the loan

looks

like a good

choice.

22

Engineering Economics

EXCEL SolutionSlide23

Plot of NPW versus Interest Rate Borrowing Cases

Year

Cash Flow

0

200

1

-50

2

-50

3

-50

4

-50

5

-50

:

:

:

:

23

p. 218

Engineering EconomicsSlide24

Plot of NPW versus Interest RateInvestment Cases

Year

Cash Flow

0

-200

1

50

2

50

3

50

4

50

5

50

:

:

:

:

24

Engineering EconomicsSlide25

Fees or DiscountsQuestion: Option 1

: If a property is financed through a loan provided by a seller, its price is $200,000 with 10% down payment and five annual payments at 10%.

Option

2: If a property is financed through the same seller in cash, the seller will accept 10% less. However, the buyer does not have $180,000 in cash.

What is the IRR for the loan offered by seller?

25

Engineering EconomicsSlide26

QUESTION CONTINUESYear

Pay Cash

Borrow from Seller

0

($180,000)

($20,000)

1

($47,484)

2

($47,484)

3

($47,484)

4

($47,484)

5

($47,484)

26

Engineering EconomicsSlide27

QUESTION CONTINUES

INTERPOLATION:

27

Engineering EconomicsSlide28

QUESTION CONTINUES

INTERPOLATION:

This is a relatively high rate of interest, so that borrowing from a bank and paying cash to the property owner is better.

28

Engineering EconomicsSlide29

EXCEL SolutionCombined cash flows (difference between options 1 & 2):At time 0: -$160,000EOY 1-5: $47,484IRR =

rate(5, 47484, -160000)

=

14.78% per yearIRR = irr(a1:a6) = 14.78%

per year

29

Engineering EconomicsSlide30

Loan and Investments are EverywhereQuestion: A student will decide whether to buy weekly parking permit or summer semester parking permit from USF. The former costs $16 weekly; the latter costs $100 due May 17th

2010; in both cases the duration is 12 weeks. Assuming that the student pay the weekly fee on every Monday:

a) What is the rate of return for buying the weekly permit?

b) Is weekly parking attractive to student?

*Total 12 weeks

30

Engineering EconomicsSlide31

QUESTION CONTINUESWeek

Weekly

Semester

May

17

0

($16)

($100)

May

24

1

($16)

May

31

2

($16)

June 7

3

($16)

June 14

4

($16)

June 21

5

($16)

June 28

6

($16)

July 5

7

($16)

July 12

8

($16)

July 19

9

($16)

July 26

10

($16)

August 2

11

($16)

a) To find IRR%, set cash flows equal in PW terms

– 100 = – 16 – 16 (P/A,i%,11)

(P/A,i%,11) = (100 - 16) / 16

(P/A,i%,11) = 5.25

Looking in the table for the above value:

IRR = 15%

b) Nominal interest rate for 52 weeks

IRR ≈ 15%/week or 15*52

= 780%/yr

Since the rate is high, paying the semester fee looks like a good choice.

31

Effective annual interest

= (1+.15)^52 – 1 = 1432% !

Engineering EconomicsSlide32

EXCEL SolutionCombined cash flows (difference between the 2 options):At time 0: -$84EOM 1~11: $16

IRR =

rate(11, 16, -84)

= 14.92% per monthIRR = irr

(C1: C12) = 14.92% per month

32

Engineering EconomicsSlide33

Rate Of Return Calculations Question: There are two options for an equipment: Buy or Lease for 24 months. The equipment might be either leased for $2000 per month or bought for $30,000. If the plan is to buy the equipment, the salvage value of the equipment at EOM 24 is $3,000. What is the IRR or cost of the lease?

33

Engineering EconomicsSlide34

QUESTION CONTINUESMonthBuy Option

Lease Option

0

($30,000)

($2,000)

1-23

($2,000)

24

$3,000

0

To find IRR%,

set

cash flows of Buy and Lease options equal in PW terms

34

Engineering EconomicsSlide35

35

Engineering Economics

Try

i

= 5%

28000 – 3000(0.3101) – 20000(13.489) = 91.7

Try

i

= 4%

28000 – 3000(0.3477) – 2000(14.148) = -1339.1

i

5%

per monthSlide36

Combined cash flows (difference of buy & lease):At time 0: -$28000EOM 1~23: $2000EOM 24: $3000

IRR =

irr

(e1:e25) = 4.97% per month

EXCEL Solution

36

Engineering EconomicsSlide37

When there are two alternatives, rate of return analysis is often performed by computing the incremental rate of return, Δ

IRR,

on the difference between

the two alternatives.

Incremental Analysis

37

Engineering EconomicsSlide38

Incremental AnalysisThe cash flow for the difference between alternatives is calculated by taking the higher initial-cost alternative minus the lower initial-cost alternative.

The following

decision path

is made for incremental rate of return (ΔIRR) on difference between alternatives:

Two -Alternative

Situations

Decision

Δ

IRR≥MARR

Choose

the higher-cost alternative

Δ

IRR<MARR

Choose

the lower-cost alternative

38

Engineering EconomicsSlide39

Incremental AnalysisQuestion: If any money not invested here may be invested elsewhere at the MARR of 6% which alternative (1 or 2) given below should you select using the internal rate of return (IRR) analysis?

Year

Alternative 1

Alternative 2

0

($20)

($30)

1

$33

$45

39

Engineering EconomicsSlide40

Question ContinuesYear

Alternative 1

Alternative 2

Alt2-Alt1

0

($20)

($30)

($30)-($20)=($10)

1

$33

$45

$45-$33=$12

40

Effective annual interest

(P/F,i,1) = 1/(1+i) = 0.833

1+i =1/0.833 = 1.2000

i

= 20%

Engineering EconomicsSlide41

Incremental AnalysisQuestion: When an equipment is installed it will save $800 per year in costs. The equipment has an estimated useful life of 5 years and no salvage value. Two suppliers are willing to install the equipment

Supplier

1

will provide the equipment in return for three beginning-of-year annual payments of $500 each.

Supplier

2

will provide the equipment for $1345.

If the MARR is 15%, which supplier should be selected?

41

Engineering EconomicsSlide42

QUESTION CONTINUESYear

0

1

2

3

4

5

Supplier 1

($500)

($500)

($500)

$800

$800

$800

$800

$800

Supplier 2

($1345)

$800

$800

$800

$800

$800

Supp2-Supp1

($845)

$500

$500

0

0

0

42

Engineering EconomicsSlide43

QUESTION CONTINUES

43

Engineering Economics

EXCEL Solution:

IRR =

rate(2, 500, -845)

=

12.00%

per yearSlide44

Think-Pair-ShareThe company uses a MARR of 14%. Based on the rate of return, which is the most desirable alternative for a 10-yr analysis period? (Use incremental ROR analysis to choose a better alternative)

Try

i= 25%

44

Engineering EconomicsSlide45

SolutionRequire an incremental ROR analysis to choose a better alternative between the two given alternatives.Year Alt B- Alt A0 -$165,000

1-10 $78,000

10 $20,000

PW of incremental costs – PW of incremental benefits

= 165,000 – (78,000(P/A, i, 10) + 20,000(P/F,i

, 10)) = 0

You want it to be higher than 14% which is MARR

Try 15%

165,000 – (78,000(5.019) + 20,000(0.2472)) = – 231,426

Try 50%

165,000 – [78,000(1.965) + 20,000(0.0173)] = 11,384

MARR < 15% <

Δ

IRR < 50%.

Choose Alternative B

.

45

Engineering EconomicsSlide46

IRR = rate(10,78000,-165000,20000, ,0.4) = 46.35%/yrIRR =

irr

(a1:a11)

= 46.35% per year

EXCEL Solution

46

Engineering EconomicsSlide47

Fancy Gadgets, Inc. has developed a new Thing-A-May-Jig at a cost of $2,000,000. Projected profits from the sale of Thing-A-May-Jigs for the next five years are: $300,000, $400,000, $500,000, $600,000, and $250,000. At the end of the fifth year, the production equipment associated with the Thing-A-May-Jig project will be disposed of for $750,000. Determine the rate of return for the Thing-A-May-Jig project. Try i

= 10 and

i

=12Think-Pair- Share

47

Engineering EconomicsSlide48

48

Engineering Economics

EXCEL Solution: IRR =

irr

(a1:a6)

= 10.16% per yearSlide49

Think-Pair- ShareAssuming that alternatives are replaced at the end of their useful life, determine the better alternative using annual cash flow analysis at an interest rate of 10%.

49

Engineering EconomicsSlide50

50

Engineering EconomicsSlide51

Analysis PeriodQuestion: If the MARR is 15% which machine shown below should be bought using the ΔIRR analysis comparison?

Machine 1

Machine 2

Initial

Cost

($300)

($700)

Uniform

Annual Benefits

$175

$200

End-of-useful-life

salvage value

$150

$250

Useful life

(years)

4

8

51

Engineering EconomicsSlide52

QUESTION CONTINUESYear

Machine 1

Machine 2

Mach2- Mach1

0

($300)

($700)

($400)

1

$175

$200

$25

2

$175

$200

$25

3

$175

$200

$25

4

$175

$200

$175

$150

($300)

5

$175

$200

$25

6

$175

$200

$25

7

$175

$200

$25

8

$175

$200

$25

$150

$250

$100

52

Machine 1

Machine 2

Initial

Cost

($300)

($700)

Uniform

Annual Benefits

$175

$200

End-of-useful-life

salvage value

$150

$250

Useful life

(years)

4

8

Engineering EconomicsSlide53

QUESTION CONTINUES

INTERPOLATION:

53

Engineering EconomicsSlide54

QUESTION CONTINUES

INTERPOLATION:

54

Engineering EconomicsSlide55

USING SPREADSHEETIRR = irr(b1:b9) = 2.36% per year

55

Engineering EconomicsSlide56

PW is a (polynomial) function of i, PW(i).Example

PW(

i

) = –400 + 25(P/A, i, 8) + 150(P/F, i, 4) +100(P/F, i, 8)

= –400 + 25i–1[1–(1+i)

–8

] + 150(1+i)

–4

+ 100(1+i)

–8

PW(

i

) = 0 may have multiple solutions for

i

.

56

Engineering Economics

Appendix 7ASlide57

End of Chapter 757Engineering Economics