Coffee & Construction Developer Meeting Coffee & Construction Developer Meeting

Coffee & Construction Developer Meeting - PowerPoint Presentation

tatiana-dople
tatiana-dople . @tatiana-dople
Follow
346 views
Uploaded On 2018-09-19

Coffee & Construction Developer Meeting - PPT Presentation

Details on Segment 1 29 th 40 th Construction Tuesday September 27 th 2016 Brighton Corridor Packages Map During Construction Approximately 18 months of construction Start in October ID: 671094

phase construction month duration construction phase duration month lane direction bicyclists brighton 2016 build cont

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Coffee & Construction Developer Meet..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Coffee & Construction Developer Meeting

Details on Segment 1, 29th -40th ConstructionTuesday, September 27th, 2016 Slide2

Brighton Corridor Packages MapSlide3

During Construction…

Approximately 18 months of construction

Start in OctoberAccess to businesses will be maintainedOne lane of traffic in each direction during constructionPedestrians and bicyclists will be accommodated at all timesLimited closures of some intersections

3 construction phasesSlide4

Brighton Boulevard, Segment 1, 29

th to 40th StreetSlide5

Construction Phase 1

Construction Area Phase 1 – Build temporary paving: Motorists, Bicyclists and pedestrians will be one lane in each direction on the west sideSlide6

Construction Phase 1 – Cont’d.Slide7

Construction Phase 2

Construction Area Phase 2 – Build new sidewalk, bike path, curb/gutter, planters, roadway, etc.: Motorists, bicyclists and pedestrians on east side; One lane in each directionSlide8

Construction Phase 2 – Cont’d.Slide9

Construction Phase 3

Construction Area Phase 3 – Build new sidewalk, bike path, curb/gutter, planters, roadway, etc.: Motorists, bicyclists and pedestrians on west side; One lane in each directionSlide10

Construction Phase 3 – Cont’d.Slide11

Summary

Construction Phase 1

Begin fall 2016 (2 month duration)

Construction Phase 2

Begin winter 2016 (6 month duration)

Construction Phase 3

Begin spring 2017 (6 month duration)

Landscaping

Begin spring 2018 (2 month duration)Slide12

Status of Other IC Contracts

Globeville

Landing Outfall

Phase

1A

Brighton Phase 2 and

GLO

Phase 2

Festival and 33rd streets

Globeville

Landing Outfall Phase

3Slide13

Please Join Us…

Brighton Corridor Redevelopment Project Ground-Breaking EventThursday, October 13, 2016Great Divide Brewery: 1812 35th St., Denver, CO 8021611 a.m. – 1 p.m.Slide14

How to Get Information

Continue attending Coffee & Construction MeetingsBe on the look-out for weekly construction updates via the following outlets:Construction update emailsSocial Media – text Construction information hotline 303 265-0211

Email brightonconstruction@Kiewit.comNDCC Website