Download Presentation The PPT/PDF document "Coffee & Construction Developer Meet..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Coffee & Construction Developer Meeting
Details on Segment 1, 29th -40th ConstructionTuesday, September 27th, 2016 Slide2
Brighton Corridor Packages MapSlide3
During Construction…
Approximately 18 months of construction
Start in OctoberAccess to businesses will be maintainedOne lane of traffic in each direction during constructionPedestrians and bicyclists will be accommodated at all timesLimited closures of some intersections
3 construction phasesSlide4
Brighton Boulevard, Segment 1, 29
th to 40th StreetSlide5
Construction Phase 1
Construction Area Phase 1 – Build temporary paving: Motorists, Bicyclists and pedestrians will be one lane in each direction on the west sideSlide6
Construction Phase 1 – Cont’d.Slide7
Construction Phase 2
Construction Area Phase 2 – Build new sidewalk, bike path, curb/gutter, planters, roadway, etc.: Motorists, bicyclists and pedestrians on east side; One lane in each directionSlide8
Construction Phase 2 – Cont’d.Slide9
Construction Phase 3
Construction Area Phase 3 – Build new sidewalk, bike path, curb/gutter, planters, roadway, etc.: Motorists, bicyclists and pedestrians on west side; One lane in each directionSlide10
Construction Phase 3 – Cont’d.Slide11
Summary
Construction Phase 1
Begin fall 2016 (2 month duration)
Construction Phase 2
Begin winter 2016 (6 month duration)
Construction Phase 3
Begin spring 2017 (6 month duration)
Landscaping
Begin spring 2018 (2 month duration)Slide12
Status of Other IC Contracts
Globeville
Landing Outfall
Phase
1A
Brighton Phase 2 and
GLO
Phase 2
Festival and 33rd streets
Globeville
Landing Outfall Phase
3Slide13
Please Join Us…
Brighton Corridor Redevelopment Project Ground-Breaking EventThursday, October 13, 2016Great Divide Brewery: 1812 35th St., Denver, CO 8021611 a.m. – 1 p.m.Slide14
How to Get Information
Continue attending Coffee & Construction MeetingsBe on the look-out for weekly construction updates via the following outlets:Construction update emailsSocial Media – text Construction information hotline 303 265-0211