/
Trinity Parkway Trinity Parkway Timeline Trinity Parkway Trinity Parkway Timeline

Trinity Parkway Trinity Parkway Timeline - PowerPoint Presentation

thesoysi
thesoysi . @thesoysi
Follow
342 views
Uploaded On 2020-06-19

Trinity Parkway Trinity Parkway Timeline - PPT Presentation

Early 1970s Freeway along the levee top first proposed Summer 1994 Trinity River Corridor Citizens Committee TRCCC begins work May 10 1995 Council Adopts TRCCC recommendation Road to go under bridges not over ID: 781355

parkway trinity council alternative trinity parkway alternative council alternatives timeline plan city usace cont

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "Trinity Parkway Trinity Parkway Timeline" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Trinity Parkway

Slide2

Trinity Parkway Timeline

Early 1970’s: Freeway along the levee top first proposedSummer 1994: Trinity River Corridor Citizen’s Committee (TRCCC) begins workMay 10, 1995: Council Adopts TRCCC recommendation –Road to go under bridges not over

Levee Couplet to be low-speed with wide outside lanes for bikes and left hand access roads to recreation area

March 1996

- April 1997: TxDOT conducts Major Transportation Study (MTIS). Report dated March 17, 1998

Slide3

Trinity Parkway Timeline

September 10,1997: City Council endorsed TxDOT’s Trinity Parkway Corridor MTIS Plan of ActionDecember 10, 1997: Council authorizes staff to negotiate ILA with NTTA and TxDot

May 2, 1998

:

City voters approved general obligation bonds ($84 million) to develop Trinity Parkway as a toll road

November 18, 1998: City Council authorized an ILA with NTTA to develop the Environmental Impact Statement (EIS) for the proposed Trinity Parkway and awarded a contract to develop the Master Implementation Plan

Slide4

Trinity Parkway Timeline

The EIS began in summer 1999 by Halff Associates and included a “No-Build” alternative in addition to 5 “Build” alternatives (2A-Industrial elevated, 2B-Industrial at-grade, 3A-Original Combined Parkway, 4A-Split Riverside, and 5-Split Landside). All alternatives were evaluated as: Controlled access toll road55 mph

8 lanes from SH183 to IH 30, and 6 lanes from IH 30 to US 175

August 25, 1999: Council Adopts Master Implementation Plan of recreational features

June 23, 1999: Council Adopts a policy related to signature bridges and aesthetic amenities for all bridges crossing the Trinity

2000

: City hires HNTB to prepare land use plan for the Trinity Corridor

Slide5

Trinity Parkway Timeline, Cont’d

Summer 2002: Mayor Miller and Chancellor Jackson raise private funds to commission the development of the Balanced Vision PlanProcess managed by the Dallas Plan, Dallas Institute of the Humanities, and AIA DallasStudy team includes: Chan Krieger – Urban Design, Hargreaves and Associates – Landscape Architecture, TDA, Inc. – Transportation Planning

Study recommended “Urban Design” Alternative, known as 3B (Combined Parkway-Modified)

October 8, 2003, City Council directed the inclusion of Alternative 3B in the EIS, and update Trinity Parkway as a 6-lane facility in the year 2025

Slide6

Trinity Parkway Timeline, Cont’d

December 8, 2003, Council adopted the Balanced Vision Plan (BVP)April 14, 2004, Council amended the BVPFebruary 2005, the Draft EIS (DEIS) was released which included the new Alternative 3B in addition to original alternatives. A Public Hearing was held March

2005

April 13, 2005

, City Council recommended Alternative 3B and requested the following :

Implement context sensitive urban design

Staged construction ( build initial 4 lanes to be widened in the median as traffic conditions warrant)

Pedestrian decks

Electronic tolling

Slide7

Trinity Parkway Timeline, Cont’d

October 6, 2006, USACE noted significant issues on Alternatives 3A, 3B, 4A and 5 in the Draft Supplemental Draft Environmental Impact Statement (Draft SDEIS)After October 2006, Alternatives 3C and 4B were developed following further interagency consultation to address O&M concerns by USACE

November 6, 2007: Voters reject referendum to cancel the project

October 2008: CH2MHill and Wallace, Roberts, Todd prepare the Landscape and Design Guidelines for the Parkway

February 2009, Supplemental DEIS (SDEIS) was released which included the remaining 4 build alternatives (

2A, 2B, 3C, and 4B

) in addition to the

No-Build

alternative. A Public Hearing was conducted in May

2009

Slide8

Trinity Parkway Timeline, Cont’d

April 1, 2009: Corps releases Periodic Inspection #9 failing the leveesMay 19, 2009: Trinity River Corridor Project Committee approved Alternative 3C as the Locally Preferred Alternative September 15,

2009:

USACE rejected Alternatives 3A, 3B, 4A and 5, as presented in the SDEIS, citing operational and maintenance concerns

FHWA continued to explore options to bring Alternative 5 to compliance with USACE’s

requirements and requires preparation of a Limited Scope Supplement to the Supplemental Draft EIS

November

3,

2010:

USACE determined Alternative 5 could not be further modified to meet USACE requirements

Slide9

Trinity Parkway Timeline, Cont’d

May 2012, Limited Scope Supplemental (LSS) to the SDEIS to: evaluate compatibility with levee remediation plans and practicability of Trinity Parkway alternatives pursuant to Executive Orders regarding floodplains and wetlands was published. A Public Hearing was held in May 2012April 2014, Final Environmental Impact Statement (FEIS) was published and a Public Hearing was held. Alternative 3C was recommended.

Early 2015: Record of Decisions are anticipated