Cannon Falls Roundabout Modification Project Jai Kalsy Project Manager January 25 th 2017 Agenda Time Topic 5 mins Staff Introductions 5 mins Project PurposeNeeds 10 mins Project Description ID: 771708

staging 2017 curb stage 2017 staging stage curb plan project east traffic construction kalsy jai roundabout time trucks mid

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Cannon Falls Roundabout Modification Pro..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Cannon Falls Roundabout Modification Project Jai Kalsy | Project ManagerJanuary 25th, 2017

Agenda Time Topic 5 mins Staff Introductions5 minsProject Purpose/Needs10 minsProject Description20 minsConstruction Staging/Traffic Impacts5 minsSchedule & Next Steps15 minsQuestions & Answers 1/24/2017 2

Introductions Jai Kalsy – Project Manager/Plans EngineerPaul Schauer – Construction EngineerAdam Wellner Assistant Traffic EngineerGreg Paulson – Assistant District EngineerMike Dougherty – Public Affairs Coordinator 1/24/20173

Project Purpose/Need Trucks having trouble using east roundaboutNoticeable curb height at east ramp roundabout– issues with loads. Constructability issue.Trucks feeling pinched negotiating all roundaboutsPurpose Replace east ramp roundabout inside curb with updated curb design.Alleviate roundabout pinch points by moving island curb and signing back Construct with minimal traffic impacts, advanced planning and notice.1/24/2017 4

Staging Plan – Stage I 1/24/20175

Staging Plan – Stage II 1/24/2017 6

Staging Pan – Stage IIIa 1/24/2017 7

Staging Plan – Stage IIIb 1/24/2017 Optional Tagline Goes Here |  mndot.gov/8

Staging Plan – Stage IV 1/24/2017 9

Schedule Begin Construction – Mid April to Early May (weather permitting)Contract Time: 30 working days (weekend work not anticipated)End Construction: Mid June1/24/2017 10

Questions? Jai KalsyJai.Kalsy@state.mn.us507-286-75451/24/2017 11