ALTERNATIVE METHODS OF PROCUREMENT CAPACITY

ALTERNATIVE METHODS OF PROCUREMENT CAPACITY
1 / 1
ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 1 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 2 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 3 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 4 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 5 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 6 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 7 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 8 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 9 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 10 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 11 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 12 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 13 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 14 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 15 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 16 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 17 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 18 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 19 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 20 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 21 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 22 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 23 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 24 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 25 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 26 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 27 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 28 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 29 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 30 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 31 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 32 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 33 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 34 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 35 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 36 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 37 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 38 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 39 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 40 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 41 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 42 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 43 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 44 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 45 of 46 ALTERNATIVE METHODS OF PROCUREMENT CAPACITY - slide 46 of 46
ALTERNATIVE METHODS OF PROCUREMENT CAPACITY DEVELOPMENT DIVISION Government Procurement Policy Board Technical Support Office (GPPB-TSO) 1 PROCUREMENT STANDARD GENERAL RULE : Sec. 10 All procurement shall be done through competitive

Related Topics

Download this presentation From Below

"ALTERNATIVE METHODS OF PROCUREMENT CAPACITY" is the property of its rightful owner. Permission is granted to download and print the materials on this website for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.

Presentation Transcript

01
ALTERNATIVE METHODS OF PROCUREMENT CAPACITY DEVELOPMENT DIVISION
Government Procurement Policy Board
Technical Support Office (GPPB-TSO) 1<br>
02
PROCUREMENT STANDARD GENERAL RULE : Sec. 10

All procurement shall be done through competitive bidding, except as provided in Rule XVI of the IRR.

EXCEPTION

Alternative methods shall be resorted only:

In highly exceptional case
To promote economy and efficiency
Justified by the conditions specified in IRR
Prior approval of the HOPE
GPPB approval as required under EO 423, S. 2005 (as amended)
Most advantageous price for the Government 2<br>
03
ALTERNATIVE METHODS Limited Source Bidding
Direct Contracting
Repeat Order
Shopping
Negotiated Procurement 3<br>