/
NYX Insertion Device & Front End NYX Insertion Device & Front End

NYX Insertion Device & Front End - PowerPoint Presentation

aaron
aaron . @aaron
Follow
354 views
Uploaded On 2018-11-03

NYX Insertion Device & Front End - PPT Presentation

Overview for IRR Gregory Fries Accelerator Division Project Engineer NYX Insertion Device amp Front End IRR November 8 2016 Outline Scope Machine Status amp Operating Schedule Source Specs Layouts Installation amp Readiness ID: 712886

commissioning amp ivu front amp commissioning front ivu safety beam device nsls photon installed radiation nyx collimator complete design

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "NYX Insertion Device & Front End" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

NYX Insertion Device & Front End Overview for IRR

Gregory Fries, Accelerator Division Project EngineerNYX Insertion Device & Front End IRRNovember 8, 2016Slide2

Outline

ScopeMachine Status & Operating ScheduleSource Specs, Layouts, Installation & ReadinessInsertion Device (ID) Safety FeaturesFront End (FE) DetailsFront End Layout, Installation & ReadinessRadiation SafetySource & FE Commissioning PlanConclusionSlide3

Scope

NYX (19-ID) I

nsertion Device & Straight

S

ection:

One IVU18 taken from X-25 beamline at NSLS

Canting magnets & power supplies

RF BPMs

NYX F

ront End:

One insertion device (ID) front end

Does not contain slits

Power limiting apertures & slits located in the beamline

Same design as previous ID front ends

The

photon & safety shutters

are wired into PPS & EPSSlide4

Machine Status & Shutdown Schedule

Installation, testing & commissioning

dependent upon operating schedule

NSLS-Il beamline operations in process

Three machine shutdowns per year (4-6 weeks each)

Dec/Jan

April/May

Aug/Sept

Typically a

two-day

maintenance period every other week

& a studies period every week during

operations

Minor

installation & testing during maintenance days

Installation completed

during

Sept. ‘16

shutdown

Commissioning scheduled for mid-Nov. ‘16Slide5

Operating Schedule

Shifts of Commissioning Time Scheduled for NYX ID & FE in mid-Nov.Slide6

Insertion Device Specifications Comparison

Beam

Line

Project

Type

Design

Beamport

Length

[m]

Period

[mm]

Peak

Field

[T]

K

max

Mag

Gap [mm] FEAper Total Power[kW]  CSX1/CSX2 NSLS-II EPU49 PPM Low-βx 4 (2×2) 49 0.57 (heli) 0.94 (Lin) 0.72 (vlin) 0.41 (45d)  2.6 (heli) 4.3 (Lin) 3.2 (vlin) 1.8 (45d) 11.5 0.6 x 0.6 7.3 (heli) 9.9 (Lin) 5.5 (vlin) 1.7 (45d) SRX NSLS-II IVU21 Hybrid Low-βx 1.521 0.90 1.79 6.4 0.5 x 0.3 3.6 CHXNSLS-II IVU20Hybrid Low-βx 3201.031.835.20.5 x 0.38.0XPD NSLS-II DW100 Hybrid High-βx 6.8 (2×3.4) 100 1.8 ~16.5 15.0 1.1 x 0.15 64.5 FMX/AMX ABBIX IVU21 Hybrid Low-βx 1.5 21 0.90 1.79 6.4 0.5 x 0.3 3.6 ISRNEXT IVU23 Hybrid High-βx 2.8 23 0.952.05 6.2 0.5 x 0.3 7.2SMI NEXT IVU23 Hybrid High-βx 2.8 23 0.952.05 6.2 0.5 x 0.3 7.2ISSNEXT DW100 Hybrid High-βx 6.8 (2×3.4) 100 1.8~16.5 15.0 1.1 x 0.15 64.5 NYXPartnerIVU17HybridLow-βx1.09180.951.555.60.5 x 0.32.4Slide7

NYX ID Straight Layout at 19-ID

RF BPMs

X25 IVU

Beam

Spool Piece

Canting Magnets

Courtesy of B.

KosciukSlide8

IVU Refurbishment Details

IVU was built in 2005 by ADC and was installed in NSLS until its shutdown

IVU was transported to bldg. 832 for refurbishment

A new control system was designed & built to meet NSLS-II standards

New flexible tapered transitions were designed & built to mate with the NSLS-II vacuum chamber

Design review held in Jan. ‘16

A new plinth was required to bring the IVU

to the proper beam height

Correction coils were added

Stretched new foil over magnet arrays

New RTDs, encoders, switches,

& magic fingers added

Magnetic measurement & shimming

Pressure tested

L

eak checked & baked

Courtesy of B.

KosciukSlide9

Cooling in the IVU straight

The

canting magnets & tapers are cooled from the standard cooling

circuit

T

he

IVU is cooled from an independent chiller

circuit

Due to low pressure requirement (originally designed for

cryo

cooling)

Same model chiller as SRX IVU

There is a small

internal leak from the IVU cooling circuit to the beam vacuum through the insulating vacuumBeing mitigated by pumping on the insulating vacuumBurst disk has been added to insulating vacuumAdequate vacuum is being maintained & commissioning can commence

Planning to repair leak during upcoming shutdown (post-start)Slide10

ID/Accelerator Components Installation

June-August ‘16 Maintenance Days

Prepping for

installing rack & pulling cables

Survey & tunnel floor prep

Sept. ‘16 Shutdown

Installed IVU into SR tunnel

Finished installing IVU

rack & electronics

Pulled & terminated remaining cables

Installed RF BPMs

Installed canting magnets & power

supplies

Installed correction coil power supplies

Baked & final surveyed IVU straight

Began testing IVU controls In-situ

Locked out IVU until IRR

approvalSlide11

NYX ID Straight

Actions

Specifications defined.

Design complete.

Design reviews completed and all actions resolved.

Devices under configuration management.

Magnetic fields measured.

Mechanical travel tested.

Water flow measured.

EPS tested.

Travelers developed and approved.

Travelers completed.Slide12

Safety Features of NSLS-II Insertion Devices

Various safety features have been implemented for all IDs:Brakes in motorsBrakes are on when there is no powerSelf-locking gearsGap will not close by attractive force onlyPilot lamp during gap/phase motionWarns people in the vicinity of the device that it is in motionLOTO procedures during maintenanceWritten procedure for each type of the device for lock-out and tag-outSlide13

EPS Switch For IVUA mechanical switch on the IVU independent from control system for “gap open” status is integrated into EPSSlide14

Front End Details

A front end delivers the photon beam to the beamline while controlling the sizes of both the synchrotron and bremsstrahlung radiation fans.

The

fixed mask

trims the synchrotron fan produced by the ID down to the synchrotron fan required by the beamline.

Lead

collimators trim

the Bremsstrahlung fan exiting to beamlines.

Photon shutter is used to stop the photon beam in order to protect the uncooled safety shutters.

The safety shutters block the bremsstrahlung radiation from exiting through the

ratchet wall collimator

chamber opening.

The photon shutter & safety shutters are locked out

. (Centrally controlled LOTO)Same safety shutter & ratchet wall collimator design as the recent bending magnet front endsOther components are the same design as NSLS-II Project, ABBIX, & NEXT front endsSlide15

NYX Front End Layout

Beam

Ratchet Wall

Collimator

Safety

Shutters

Fixed

Mask

Collimator 1

Photon Shutter

Fast Gate Valve

Collimator 2

Slow Gate Valve

Courtesy of C. Amundsen

BM Photon ShutterSlide16

Radiation Safety

Radiation safety components:

Exit absorber

Fixed mask

Burn through #1 & #2

Collimator #1 & #2 shielding

Safety shutter #1 & #2 shielding

Ratchet wall collimator shielding

Credited controls:

Shielding

Burn through devices

PPS

Removal

or

modification of any device under configuration control requires an approved PS safety system

work permit Slide17

Front End Installation

June-August ‘16 Maintenance Days

Survey & floor prep

Pulled cables

Installed initial front end components

Plumbed

DI water & compressed

air

Sept. ‘16 Shutdown

Installed ratchet wall

collimator

&

safety shuttersInstalled exit pipe (tie-in to SR vacuum)Installed remaining front end components

Terminated cables & made final connectionsTied-in front ends into EPSBaked & final surveyed front end

Tested subassemblies in-situLocked out shutters until IRR approvalSlide18

NYX Front End

Actions

Ray

tracings complete.

Design

drawings complete

.

Vacuum system complete.

Final survey

complete

.

Devices under configuration management.

Integrated testing complete.

Water flow measured.

Travelers complete.

Top-off analysis complete.

EPS verification.

PPS verification.Slide19

Commissioning Plan

Commissioning scheduled for mid-Nov ‘16

Beamline commissioning

time reserved

Commissioning effort will include staff from Operations, Physics, Insertion Device, Front End, and Diag. groups

Software controls & tools already developed and verified during NSLS-II beamline commissioning

Procedures released for ID & FE commissioning sequence and radiation survey plan

Same commissioning plan as other recently commissioned IDs & FEsSlide20

Insertion Device Commissioning

Beam current

below 2 mA

Verify orbit and characterize/correct lattice

Reduce ID

gap

Generate orbit correction feed-forward (lookup) table

Inject with ID gap closed, improve injection

efficiency

General radiation survey

Authorization

 proceed to FE

commissioningSlide21

Front End Commissioning

Verify active interlock functionality

Align ID BPMs with respect to

nearby regular BPMs

Center beam in the ID

Align the photon beam through the

FE by scanning the SR fan at 2mA

Condition vacuum

Radiation survey (fault study)

Courtesy of

S. Seletskiy

RF trip signalSlide22

Beam Current Increase Plan

Obtain authorization to increase current to 85 mA Close all ID gaps and lock out FE shuttersEvaluate and record current machine stateGradually increase current

Verify

active interlock system

being engaged

Monitor and verify orbit, tunes, lattice, vacuum, temperature

Hold Point – Radiation

survey

Phase

1

No Phase 2 since there are no FE slits

Phase 3 (fault studies)Beam conditioning

Repeat to allowable currentSlide23

Conclusion

NYX IVU & front end installed & tested

Radiation components under configuration control

Assembly drawings, ray tracings, procedures, & travelers are available

Photon shutter & safety shutters are locked in the down position

IVU is locked out until commissioning starts

IVU & front end are ready for commissioning

No self-identified pre-starts

IVU cooling circuit/insulating vacuum leak to be repaired (post-start)

Commissioning

experience

& prepared commissioning procedures from previously commissioned IDs & FEs