/
ALFA_CTPIN    -  a  NBI hardware contribution to ATLAS ALFA_CTPIN    -  a  NBI hardware contribution to ATLAS

ALFA_CTPIN - a NBI hardware contribution to ATLAS - PowerPoint Presentation

camstarmy
camstarmy . @camstarmy
Follow
342 views
Uploaded On 2020-10-22

ALFA_CTPIN - a NBI hardware contribution to ATLAS - PPT Presentation

Sune Jakobsen on behalf of ATLASALFA Seminar at NBI 22062015 Trigger sources of latency in ALFA 2012 trigger system Total 2157 ns lt 2175 ns Time of Flight 800 ns Scintillator 3 ns ID: 815724

ctpin alfa nbi latency alfa ctpin latency nbi atlas module timing data delay sune jakobsen final early revision sources

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "ALFA_CTPIN - a NBI hardware contrib..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

ALFA_CTPIN

- a NBI hardware contribution to ATLAS

Sune Jakobsen on behalf of ATLAS-ALFA

Seminar at NBI 22-06-2015

Slide2

Trigger – sources of latency in ALFA

2012 trigger system

Total: 2157 ns

< 2175 ns

Time of Flight

800 ns

Scintillator

3 ns

Photomultiplier

6 ns

LEMO-cables (tunnel)

25 ns

MAROC2 (analog FE)

13 ns

Digital Front End

50 ns

LEMO-cables (USA15)

16 ns

MD/OD separation

60 ns

NIM_to_LVDS

5 ns

Air-core-cable

1030 ns

CTPIN logic

25 ns

CTP functionality

125 ns

Run2 without upgrade

Total: 2253 ns

> 2175 ns

Time of Flight

800 ns

Scintillator

3 ns

Photomultiplier

6 ns

LEMO-cables (tunnel)

25 ns

MAROC2 (analog FE)

13 ns

Digital Front End

50 ns

LEMO-cables (USA15)

16 ns

MD/OD separation

60 ns

NIM_to_LVDS

5 ns

CTP

PITbus

upgrade

Air-core-cable

1030 ns

CTPIN logic

25 ns

50 ns

CTP functionality

125 ns

New position of station

CTP OUT upgrade

25 ns

21 ns

Maximum latency for full ATLAS readout is:

87 BC = 2175 ns.

Upgrade needed for ALFA to trigger on level1! At least:

78 ns + margin

Latency sources

ALFA_CTPIN concept Early tests First module Revision 2 Timing Final latency First data Budget Thanks

237 m ATLAS IP

Cost in latency: 21 ns (

ToF

+ additional cable)

The B stations (furthers from ATLAS) have been move ~4 m away from the IP

Seminar at NBI 22-06-2015

ALFA_CTPIN - a

NBI hardware contribution to ATLAS

Sune Jakobsen

2

/26

Slide3

Run2 with upgrades

Total: 2118 ns

< 2175 nsTime of Flight

800 ns

Scintillator

3 ns

Photomultiplier

6 ns

LEMO-cables (tunnel)

10 ns

MAROC2 (analog FE)

13 ns

Digital Front End

37.5 ns

LEMO-cables

(

USA15)

10 ns

ALFA_CTPIN

37.5 ns

Air-core-cable

1030 ns

CTP functionality

125 ns

New position of station

CTP OUT upgrade

25 ns

21 ns

Trigger – sources of latency in

ALFA with ALFA_CTPIN

2012 trigger system

Total: 2157 ns

< 2175 ns

Time of Flight

800 ns

Scintillator

3 ns

Photomultiplier

6 ns

LEMO-cables (tunnel)

25 ns

MAROC2 (analog FE)

13 ns

Digital Front End

50 ns

LEMO-cables (USA15)

16 ns

MD/OD separation

60 ns

NIM_to_LVDS

5 ns

Air-core-cable

1030 ns

CTPIN logic

25 ns

CTP functionality

125 ns

Run2 without upgrade

Total: 2253 ns

> 2175 ns

Time of Flight

800 ns

Scintillator

3 ns

Photomultiplier

6 ns

LEMO-cables (tunnel)

25 ns

MAROC2 (analog FE)

13 ns

Digital Front End

50 ns

LEMO-cables (USA15)

16 ns

MD/OD separation

60 ns

NIM_to_LVDS

5 ns

CTP

PITbus

upgrade

Air-core-cable

1030 ns

CTPIN logic

25 ns

50 ns

CTP functionality

125 ns

New position of station

CTP OUT upgrade

25 ns21 ns

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

Sune Jakobsen

3

/26

Latency sources

ALFA_CTPIN concept Early tests First module Revision 2 Timing Final latency First data Budget Thanks

Slide4

ALFA_CTPIN board concept

Use electrical inputs on the new CTP_CORE+ (foreseen for topological triggers)

Intergrade the MD/OD separation

Integration near to the CTP

Add per bunch monitoring

Very low input/output time

Details in ATLAS note:

ATL-COM-LUM-2013-018

Add additional monitoring of rates

Latency sources

ALFA_CTPIN concept

Early tests First module Revision 2 Timing Final latency First data Budget Thanks

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

Sune Jakobsen

4

/26

Slide5

ALFA_CTPIN board layout

Latency sources

ALFA_CTPIN concept

Early tests First module Revision 2 Timing Final latency First data Budget Thanks

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

Sune Jakobsen

5

/26

Slide6

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

Sune Jakobsen

6

/26

2013: Forming of community for the ALFA_CTPIN

New manpower arriving at NBI (Jan) and good opportunity to immediately getting involved in a CERN project and establish connections to CERN.

Small, but highly important task with large visibility.

Agreement that NBI is responsible for the design, layout and production of the ALFA_CTPIN boards.

Niels Bohr Institute was already designing and producing the new ATLAS CTP_OUT modules (Henrik) and the design was used as a starting point for the ALFA_CTPIN board.

CERN is coordinating and testing.

A close collaboration is established with the ATLAS CTP group and in

particular the

engineer behind the CTP hardware.

Agreement made that ALFA_CTPIN is counted as an ATLAS upgrade and that the full cost (besides manpower which is counted as OTP class 3) count on the NBI contribution for phase 1 upgrade.

Shortly after the universities in Cracow committed to be responsible for the firmware, low level software and high level software.

Latency sources

ALFA_CTPIN concept

Early tests First module Revision 2 Timing Final latency First data Budget Thanks

Slide7

ALFA_CTPIN board - approval

E-mail from David Francis 23-11-2013:

TDAQ welcomes the proposal to design and build an "ALFA_CTPIN interface board".

The implementation of such a board will not impact the Level-1 trigger performance.

A review of the board should be

organised

as soon as possible.

If you agree, TDAQ can take the lead in

organising

such a review.

Latency sources

ALFA_CTPIN concept

Early tests First module Revision 2 Timing Final latency First data Budget Thanks

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

Sune Jakobsen

7

/26

Slide8

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

Sune Jakobsen

8

/26

2014: Early test

of small

parts of the design

at NBI - input

Test made on a LMH7322EVAL

board.

Measured delay 1.2

ns.

Datasheet delay: 0.700 ns.

Difference likely due to use of 200 MHz

oscilloscope.

Test of

LMH7322 to be used for converting the NIM signals to LVDS (FPGA in

).

Latency sources ALFA_CTPIN concept

Early tests

First module Revision 2 Timing Final latency First data Budget Thanks

Slide9

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

Sune Jakobsen

9

/26

Test

made on a small custom build test

board.

Delay ~ 0.6

ns.

Rise and fall time ~1.5

ns.

Test of

SY100ELT24 to be used for converting the TTL (FPGA out) signals to

NIM.

The measurement's are likely biased by use of 200 MHz

oscilloscope.

2014: Early test

of small

parts of the design

at NBI - output

Latency sources ALFA_CTPIN concept

Early tests

First module Revision 2 Timing Final latency First data Budget Thanks

Slide10

The conceptual design evolves

Latency sources ALFA_CTPIN concept

Early tests

First module Revision 2 Timing Final latency First data Budget Thanks

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

Sune Jakobsen

10

/26

Slide11

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

Sune Jakobsen

11

/26

Design and layout

Due to time constrains it is decided to involve the CERN PCB workshop for the board layout.

A very close collaboration between NBI and the CERN PCB workshop

was

established.

From the conceptual design NBI makes the real board design.

To accommodate all the front panel connectors etc., a design with one main board and two daughter boards are made.

Latency sources ALFA_CTPIN concept

Early tests

First module Revision 2 Timing Final latency First data Budget Thanks

Slide12

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

12/26

Production of the first ALFA_CTPIN module

Many parts

purchased though

CERN.

The production and mounting of the boards (fully organized by NBI) was

distributed to

3 companies:

Production a little delayed due to holiday period and problems at

HP

elektronik

montage

PCB3: PCB by

Printline

, mounting by NBI

PCB1 (main): C.B.

Svendsen

PCB2: PCB by

Printline

, mounting by

HP

elektronik

montage

Sune Jakobsen

2 modules produced.

Latency sources ALFA_CTPIN concept Early tests

First module

Revision 2 Timing Final latency First data Budget Thanks

Slide13

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

13/26

Debugging for first module at

NBI

Several minor problems found and fixed in Copenhagen:

One major problem found: Not possible to program the FPGAs via the EPROM (used after power cuts).

Decision made to correct all known errors in the design and make new PCB layouts.

Termination of the compensator of the NIM inputs.

Termination of the NIM inputs.

Termination of the clock circuit.

Inversion of the clock outputs.

NBI committed to finance the new layout (at the CERN PCB workshop), the PCB production and mounting of components.

Important for commissioning: The first corrected module

could be

used for all tests.

Sune Jakobsen

Latency sources ALFA_CTPIN concept Early tests

First module

Revision 2 Timing Final latency First data Budget Thanks

Slide14

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

14/26

First test at CERN in the ALFA laboratory

A dedicated test setup have been build in B251.

Numerous test of software, hardware and firmware made.

Software/Readout:

After the electrical test the modules were transported to CERN for further testing (October 2014).

5 front panels produced and first one mounted.

The phase of the input is shown in online histograms.

Values read out from the board with low level VME commands

.

A dedicated partition (like the ALFA standalone partition for the detector system) has been build.

The FPGAs where successfully programmed via J-TAG.

Sune Jakobsen

Latency sources ALFA_CTPIN concept Early tests

First module

Revision 2 Timing Final latency First data Budget Thanks

Slide15

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

15/26

Early firmware

The work on the firmware started almost as the same time as the design.

Much work on optimization of internal timing.

Priority given to test of electrical parts of board (to check all before production of new boards).

MD/OD separation of signals.

Output of MD, OD and various internal signals for front

panel.

Measurement of the input phase using a 400 MHz clock (2.5 ns steep size).

Readout of values via VME bus.

The change of concepts is made to minimize input/output time and as to minimize the lines to the CTP (where before the number of LUTs in the CTP were minimized).

Input signal

FPGA interpret signal

MD output

OD output

Sune Jakobsen

Therefore the basic functionality was working only a few days after the first board arrived to CERN.

Latency sources ALFA_CTPIN concept Early tests

First module

Revision 2 Timing Final latency First data Budget Thanks

Slide16

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

16/26

First test

w

ith the CTP_CORE+

In addition the stability of the data was checked (32 bits at 80

MHz) (not foreseen and ALFA_CTPIN board not optimized for timing yet)

The ALFA_CTPIN board was moved to the CTP laboratory and installed in there setup. Input signals generated by a

LTPi

.

The primary goal of the test was to test the electrical.

The electrical connection was verified (the CTPCORE+ could see the signals being input on the ALFA CTPIN board).

Some instabilities seen

=>

optimization of the timing in the ALFA_CTPIN board.

CTP_CORE+

ALFA_CTPIN

LTPi

Sune Jakobsen

Latency sources ALFA_CTPIN concept Early tests

First module

Revision 2 Timing Final latency First data Budget Thanks

Slide17

Sune Jakobsen

Installation of revision 1 ALFA_CTPIN module in USA15

The connection to the CTP_CORE+ was established.

This

allowed for the next part of commissioning to start even without the final module.

While waiting for the revision 2 of the ALFA_CTPIN module to be produced, one of the revision 1 (prototype) was installed in USA15 and connected.

The old NIM crate was removed and the cables shorten and cables shorted and rerouted directly to the ALFA_CTPIN.

ALFA_CTPIN

CTP

First trigger signal passing though the ALFA_CTPIN from an ALFA detector to trigger ATLAS.

A first latency measurement without beam was made via the DAQ latency and

showed

~83 ± 1 BC, which was well below the hard cutoff of 87 BC.

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

17

/26

Latency sources ALFA_CTPIN concept Early tests

First module

Revision 2 Timing Final latency First data Budget Thanks

Slide18

Sune Jakobsen

ALFA_CTPIN revision 2

Final boards produced by NBI (Copenhagen).

Boards basic functionality tested at NBI and was working.

Transport to CERN (

by

retired professor) unfortunately damaged two of the boards.

Spare capacitors send from NBI and the boards were repaired

at CERN.

All functionality checked and worked on module #2.

Module #1 and #3 does not load data from the

eprom

.

The problem was the order the components on the board was powered (the

voltage

generated on the board delayed compared to the voltages coming

directly).

Module #1 and #3 was fixed at NBI by NOT using the direct 3.3 V from the crate,

but instead

the 3.0 V generated from the board.

Module #2 installed in USA15.

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

18

/26

Latency sources ALFA_CTPIN concept Early tests First module

Revision 2

Timing Final latency First data Budget Thanks

Slide19

Sune Jakobsen

Timing – Phase of each detector

Interval without jitter MUCH larger than in Run1 (due to new trigger PMFs).

Optimized for all detectors in first collisions at injection energy

.

The phase of each detector needs to be optimized to the clock

. (If not done correctly the

air-core trigger signal jitter). The scan is done via the TTC system.

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

19

/26

Delay of 0 ns

Delay of 2.5 ns

Delay of 5 ns

Delay of 7.5 ns

Delay of 10 ns

Delay of 12.5 ns

Delay of 15 ns

Delay of 17.5 ns

Delay of 20 ns

Delay of 22.5 ns

Delay of 25 ns

The check if phase is also optimal for MAPMTs pending (need much more beam).

The optimal phase is loaded by the DAQ system at “CONFIGURATION

”.

In Run1 the noise level for MDs was sharp 0 Hz.

Measurement attempted with circulating beam, but made impossible due to a <1 Hz random noise level on all detectors.

Radiation, light leaks or ?

Noise is not from

PMTs.

Latency sources ALFA_CTPIN concept Early tests First module Revision 2

Timing

Final latency First data Budget Thanks

Slide20

Sune Jakobsen

Timing – Signal arriving time equalization

All signals

are

now arriving within

~1 ns.

The optimization was performed without beam, which was possible due to the synchronized LED system.

After the phase optimization the trigger the arrival time of the trigger signals to the ALFA_CTPIN module was equalized with cables delays.

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

20

/26

B7L1U

B7L1L

A

7L1U

A7L1L

A7R1U

A7R1L

B7R1U

B7R1L

10 ns

Latency sources ALFA_CTPIN concept Early tests First module Revision 2

Timing

Final latency First data Budget Thanks

Slide21

Sune Jakobsen

Timing – Phase of ALFA_CTPIN

However optimizing the phase can gains up to ~25 ns in latency.

The excellent timing in the ALFA_CTPIN (after

lots

of hard work

on the firmware side)

makes it almost immune jitter.

ALFA trigger and timing ALFA general meeting in Copenhagen 11-05-2015

21

/26

The scan was performed by adding LEMO cables to the clock input.

Minimal latency with delay of 15.5 ns.

19 ns used as final value to account for differences of channels and contingency.

Delay of 2 ns

Delay of 4 ns

Delay of 6 ns

Delay of 8 ns

Delay of 10 ns

Delay of 12 ns

Delay of 14 ns

Delay of 15 ns

Delay of 15.5 ns

Delay of 16 ns

Delay of 18 ns

Delay of 20 ns

Delay of 22 ns

Delay of 24 ns

Air-core

LEMO-out ALFA_CTPIN

Latency sources ALFA_CTPIN concept Early tests First module Revision 2

Timing

Final latency First data Budget Thanks

Slide22

Sune Jakobsen

Latency

The final latency was found with circulating beam in LHC: 84 BC (75 ns margin to the absolute limit).

The ALFA_CTPIN board was timed in with the CTP by sending a fixed pattern from memory on the ALFA_CTPIN board and see the pattern arrive correctly on the CTP_CORE+ (possible due to largely evolved firmware and software).

Shortest ATLAS latency without ALFA ~76

BC,

but L1topo

muon

are still not included.

From

A

TLAS weekly RC 28-04-2015 by Till

Eifert

:

Chocking first results from first complex

deadtime

settings: 5.5-11 % at 100

kHz, with the high number being with ALFA latency (plot missing as they are no yet pubic).

Likely ATLAS will run with the shorted possible latency to minimize dead time and only change to the ALFA latency for special runs.

ALFA trigger and timing ALFA general meeting in Copenhagen 11-05-2015

22

/26

Latency sources ALFA_CTPIN concept Early tests First module Revision 2 Timing

Final latency

First data Budget Thanks

Slide23

Sune Jakobsen

First data taking and outlook

From a trigger point of view all worked.

ALFA was part of the second week of LHC Run2, which was special physics with

LHCf

.

The ALFA_CTPIN module insured stable level 1 triggering and thereby the possibility to take unique data combining ATLAS-ALFA-

LHCf

.

Unfortunately the ALFA interlock system had problems and ALFA was forced to not move the Roman Pots in, so only ~2hours

af

data was taking (bugs in the interlock system is now fixed).

Outlook:

The hardware part of the ALFA_CTPIN are in it final version and have successfully taking real data.

The firmware for the second FPGA, which is for bunch by bunch is not operational yet.

ALFA trigger and timing ALFA general meeting in Copenhagen 11-05-2015

23

/26

The software of both low and high level is still improving.

The board will be able to also monitor rates after logics, but software still in an early face.

Latency sources ALFA_CTPIN concept Early tests First module Revision 2 Timing Final latency

First data

Budget Thanks

Slide24

Sune Jakobsen

Budget

Final total cost: 306160

kr

(exact value depending on the evolving exchange rate of the DKK/CHF)

Original estimate at NBI: 50

kkr

.

So this should be the lessen for next project: Better estimate of total cost.

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

24

/26

Latency sources ALFA_CTPIN concept Early tests First module Revision 2 Timing Final latency First data

Budget

Thanks

Slide25

On behalf of ATLAS-ALFA I would like to say:

Thanks to NBI for this crucial hardware contribution that was finished in time for first data taking.

Seminar at NBI 22-06-2015 ALFA_CTPIN - a NBI hardware contribution to ATLAS

25

/26

Latency sources ALFA_CTPIN concept Early tests First module Revision 2 Timing Final latency First data Budget

Thanks

Sune Jakobsen

Slide26

37/66

NIELS BOHR INSTITUTE

UNIVERSITY OF

COPENHAGEN

 

Commissioning of the Absolute Luminosity For ATLAS detector at the LHC

Sune

Jakobsen

Backup

Trigger

system upgrade winter 2011-2012

Luminosity ATLAS at LHC ALFA Installation Triggering 2011 Analysis

Trigger upgrade

2012 Impedance heating Conclusion/Outlook

Slide27

Figure 22.2

Commissioning of the Absolute Luminosity For ATLAS detector at the LHC

NIELS BOHR INSTITUTE

UNIVERSITY OF COPENHAGEN

 

Situation in 2011

Sune Jakobsen

38/66

The OD signals arrive too late in USA15 to be used to trigger all of ATLAS => Can be used in ALFA standalone data taking only.

Fast coaxial cables were chosen over air-core cables due to price.

(

1 air-core cable is about 10000 CHF and 16 additional would have been needed).

Air-core cable signal

(Speed: 91 % of c)

Fast coaxial

cable

(

type

c-50-3-1. Speed: 83 % of c)

Fast coaxial

cable

(

type

c-50-3-1. Speed: 83 % of c)

Hit

Hit

Hit

Time

The rate of OD tracks in the 90 m run was much lower than expected. About 50 % of time used just for OD data taking.

Signal arriving in USA15

Luminosity ATLAS at LHC ALFA Installation Triggering 2011 Analysis

Trigger upgrade

2012 Impedance heating Conclusion/Outlook

Slide28

Figure 22.4

Commissioning of the Absolute Luminosity For ATLAS detector at the LHC

NIELS BOHR INSTITUTE

UNIVERSITY OF COPENHAGEN

 

Upgrade to trigger combined on OD signal

Sune Jakobsen

39/66

Using only the already installed air-core cable also for all OD signals in combined running.

All signals arrive to USA15 in time and it is possible to distinguish OD and MD signals.

Air-core cable signal

(Speed: 91 % of c)

Hit

Hit

Hit

Time

Signal arriving in USA15

Only requires firmware upgrade of the Front

End electronics

(trigger mezzanine).

Different signal duration: 50 ns for MD signals, 25 ns for OD signals.

Luminosity ATLAS at LHC ALFA Installation Triggering 2011 Analysis

Trigger upgrade

2012 Impedance heating Conclusion/Outlook

Slide29

Figure 22.6

Commissioning of the Absolute Luminosity For ATLAS detector at the LHC

NIELS BOHR INSTITUTE

UNIVERSITY OF COPENHAGEN

 

Distinguishing

MD and

OD signal

with standard

NIM electronics

Sune Jakobsen

40/66

Additional delay due to logic is 46 ns. From Front End firmware upgrade + CTP delay change: -50 ns.

Luminosity ATLAS at LHC ALFA Installation Triggering 2011 Analysis

Trigger upgrade

2012 Impedance heating Conclusion/Outlook

Slide30

Figure 22.6

and 22.11

NIELS BOHR INSTITUTE

UNIVERSITY OF COPENHAGEN

 

NIM crate for MD/OD separation in ATLAS CTP rack

Sune Jakobsen

Commissioning of the Absolute Luminosity For ATLAS detector at the LHC

41/66

8 x

=

Luminosity ATLAS at LHC ALFA Installation Triggering 2011 Analysis

Trigger upgrade

2012 Impedance heating Conclusion/Outlook