Cuyahoga County Airport Runway 6/24 Safety Area Improvement Program Cuyahoga County Airport Runway 6/24 Safety Area Improvement Program

Cuyahoga County Airport Runway 6/24 Safety Area Improvement Program - PowerPoint Presentation

camstarmy
camstarmy . @camstarmy
Follow
342 views
Uploaded On 2020-08-27

Cuyahoga County Airport Runway 6/24 Safety Area Improvement Program - PPT Presentation

OVERVIEW September 2015 MultiYear Program Overview Runway shift to the west Reconstruct 1239 of the Runway 6 end 1002 of the Runway 24 end Install new drainage amp grade RSA to standards 500000 CY of cut ID: 804675

amp runway emas package runway amp package emas existing rsa project year construction 2016 grades march reconstruct relocate compliant

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "Cuyahoga County Airport Runway 6/24 Safe..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Cuyahoga County Airport

Runway 6/24 Safety Area Improvement Program

OVERVIEW September 2015

Slide2

Multi-Year Program Overview

Runway “shift” to the west

Reconstruct 1,239’ of the Runway 6 end 1,002’ of the Runway 24 endInstall new drainage & grade RSA to standards (+/- 500,000 CY of cut)

Reconstruct southern half of existing Runway 6/24

Rehabilitate northern half of existing Runway 6/24

Edge Lights – Raise and Relocate

322’ EMAS bed on Runway 6 departure end

435’ EMAS bed on Runway 24 departure end

Relocate Runway 24 approach lights

Relocate Runway 24 Glideslope antenna & PAPI

Slide3

Why?

Non-compliant Runway Safety Area (RSA) off ends of the Runway 6/24

Runway lateral RSA grades not compliantGround within primary surface & Part 77 transitional surface

Inadequate pavement section

Non-complaint transverse grades on Runway (super elevated)

Non-complaint connector taxiway location (direct access from apron to runway w/o turn)

Slide4

Why?

Slide5

Why?

Slide6

What are the project limitations?

FAA Funding

Timing (normally do not issue grants until September)Discretionary Amount(s) Unknown

FY 15 is last year of the 4-year Reauthorization Bill

Can’t start on the runway ends first

Shorten existing runway

Profile issues

No work within the RSA when runway is open

FAA will not grant modifications to standards on runway transverse grades

Slide7

Overall Phasing Schedule

Package #1 – Earthwork & Drainage - $5 M

Received Bids - June 2015Grant Issued – September 2015

Construction – March 2016

Package

#2

Reconstruct/Rehabilitate Existing Runway 6/24 - $9.8M

Receive Bids – April 2016

Construction – August 2016 – November 2016

Package #3 – Runway 6 End Reconstruction/Shift/EMAS Installation - $10M

Construction – March 2017

Package #4 – Runway 24 End Reconstruction/Shift/EMAS Installation - $15M

Construction – March 2018

Slide8

Package #1 – Earthwork & Drainage

\

Slide9

Package #2 – Existing Runway 6/24 Rehabilitation/Reconstruction

Slide10

Project #3 – Runway 6 End Extension & EMAS

Slide11

Project #4 – Runway 24 End Relocation & EMAS

Slide12

Project Completion

Compliant RSA

Pavement Section // 20-year design lifeComplaint ROFA and Part 77 Primary Surface

Standard runway transverse grades

Compliant taxiway connector locations

Final Declared Distances

5,502’

Runway 24 LDA – 5,000’

Runway 6 LDA – 5,184’