/
The Sixth Regional Economic Cooperation Conference on Afgha The Sixth Regional Economic Cooperation Conference on Afgha

The Sixth Regional Economic Cooperation Conference on Afgha - PowerPoint Presentation

celsa-spraggs
celsa-spraggs . @celsa-spraggs
Follow
415 views
Uploaded On 2016-03-14

The Sixth Regional Economic Cooperation Conference on Afgha - PPT Presentation

Annotated Working Group Program Abdul Razique Samadi CEO DABS Afghanistan September 3 2015 Kabul Afghanistan 1 T he Government of Afghanistan corporatized the National Electricity Service Department ID: 254892

power afghanistan energy dabs afghanistan power dabs energy casa project 1000 electricity system transmission regional 500kv million 220kv pakistan

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "The Sixth Regional Economic Cooperation ..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

The Sixth Regional Economic Cooperation Conference on AfghanistanAnnotated Working Group Program

Abdul Razique “Samadi”CEO DABS Afghanistan

September 3, 2015Kabul Afghanistan

1Slide2

The Government of Afghanistan corporatized the National Electricity Service Department Da AFGHANISTAN BRESHNA MOSSASA (DABM) into an independent state owned utility as such, all assets, staff and other Rights and Obligations of (DABM) were transferred to DA AFGHANISTAN BRESHNA SHERKAT (DABS).

DABS is an independent and autonomous lOO% State-owned corporation, incorporated on 4th May 2008 (15 Saur 1387). DABS has been established under The Corporations and Limited Liabilities Law of the Islamic Republic of Afghanistan (IROA). DABS have sole authority to run its operations and appoint the required staff according to its legal framework (Articles of Incorporation, Bylaws)

Afghanistan Energy Sector2Slide3

Afghanistan Electricity Demand Forecast for 20 Years

As per Afghanistan Power Sector Master Plan

3Forecast Scenario 2032 Gross Demand Net DemandPeak LoadBase Case 18,409 GWh

15,900

GWh

3502 MW

High Scenario

22,534

GWh

19,474

GWh

4287 MW

Low Scenario13,701 GWh11,840 GWh2607 MWSlide4

Investment Required to Meet demand Supply Gap

4Overview on Investment typeSubtotal by project

Stage A Stage B Stage C

Stage

D

Generation development

$ 7,329.50

$ 327.60

$ 348.50

$ 981.50

$ 5,671.90

Major transmission projects

$ 1,725.90

$

595.00

$ 676.00

$ 212.90

$ 242.00

Transmission development within the provinces

$ 1,041.00

$ 291.10 $ 439.80 $ 215.10 $ 95.00 Total in Million USD $ 10,096.40 $ 1,213.70 $ 1,464.30 $ 1,409.50 $ 6,008.90

As per Afghanistan Power Sector Master PlanSlide5

5

Governmental Subsides

Figures in Million USD

2010

2009

2011

2012

2013

2014

With the lower cost of new power generation (including import) and improved distribution, billing and collections systems, DABS' revenues started increasing and subsidies decreased from 2009 (1388) onwards. In 1387 MoF budgeted 40 million US dollars for fuel subsidies to support thermal power generation, the MoF & DABS agreed based on the previous subsidy levels to the ceiling schedule shown in Graph.Slide6

Afghanistan Electricity Generation Potential Afghanistan has unique untapped potential to generate enormous amount of Electricity from Renewable Energy Resources:Solar Energy 222,000 MWWind Energy 67,000 MWHydro Energy 23,000 MW

With the Regional Energy and Natural Resources Cooperation this potential can be harnessed timely for the benefit of the entire region. Enabling Policies Regulatory Framework and Matching investments are the need of the hour. Slide7

Afghanistan on Grid Generation / Transmission Profile

7Slide8

DABS Electrical energy import from Neighboring Countries (Figures in million kWh) 8Slide9

Afghanistan Power Grid

Afghanistan Power Network consists of 4 isolated system:North East Power System; (NEPS) consisting of a grid linking 17 load centers (Kabul, Mazar-i-Shariff, Jalalabad, etc) with Uzbekistan and Tajikistan (HVTL 220kv, 110kv, 35kv)South East Power System (SEPS) consisting of

Khandar, etc linking Kajaki (HVTL 110kv)Herat system linking the Herat Zone with Islamic Republic of Iran and Republic of Turkmenistan (HVTL 132kv, 110kv)Turkmenistan system linking Herat, Faryab, JawzJan, Sar-e-Pul and Andkhoy

district. (HVTL 110kv)

9Slide10

DABS - Growth of Consumers

DABS Growth of Customers

Residential91.88%Commercial

6.72%

Holy places

0.73%

Government

0.55%

Industries

0.11%

443% Increase in 12 yearsSlide11

11

Regional Schematic

KGZ

PAK

AFG

TRM

UZB

TAJ

KGZ

500kv AC

AC/DC Convertor

HVDC Back to Back Convertor

DC/AC Convertors

500kV DC

220kV AC

500kV AC

220kV AC

500kV AC

Kabul

CASA

TUTAP

HVDC Back to Back Convertor

Pul-e-Khumri

l

Sangtuda

TAJ

PAK

AFG

TRM

UZBSlide12

ADB: AFG-TMK Regional Interconnection Project

ADB: AFG-TMK 500kVInterconnection

Pul-e-Khumri

ADB: Additional 500 kV Hindu

Kosh

Crossing (

Salang

Pass)

Resolve currently transmission capacity limitation

USAID,

USFOR-A and

ADB:

SEPS

– South East Power System

double circuit

only one to be strung

Khost

Bannu

CASA-1000 DC 500kV

Surkhan

Sangtuda

Legend

Exist 220kV

Future AC 500kV

CASA- 1000 DC

500kV

Future AC 220kV

SEPS’s 220kV Reinforcement to Pakistan

Interconnection with Pakistan reinforcing SEPS stringing the second circuit.

Afghanistan Transmission and Generation Expansion Plan - Possible Interconnection with Pakistan by Reinforcing SEPS’ 220 kV

Samangan

Bamian

Kajaki

HPP

100MW

Kajaki

Panjsher

Kunar

Sheberghan 600 MW within 6 years.

Enough natural gas to fire more than 1,000 MW

Hajigak

Coal TPP

Capacity: 800MW

Baghdara

HPP

Capacity: 210MW

Surobi2 HPP

Capacity: 180MW

Kunar

HPP

Capacity: 1089MW

12

https://www.dabs.afSlide13

CASA-1000 Project

13Slide14

14

CASA-1000 Project

Project Scope:Kyrgyzstan and Tajikistan exporters of electricity.Afghanistan and Pakistan as importers of electricity.A 500 kV HVAC transmission link between Kyrgyz Rep. and Tajikistan.

A 500 kV, 750 km HVDC transmission system between Tajikistan and Pakistan – 562 km are through Afghanistan.

A 300 MW DC to AC Converter Station at Afghanistan.

A 1000 MW DC to AC Converter Station at Pakistan

.

Creation of CASAREM - Central Asia South Asia Regional

Electricity Market .

CASAREM entails to the development of a Regional Market among the CASA-1000 countries. Working on:

Multiregional power trading agreements: Energy Price and transfer fees.

Legal Framework: laws, policies, acts and regulation to attract private investment. Slide15

CASA-1000 Project Financial Profile(Figures in million USD) Project Cost

AfghanistanPakistan

TajikistanKyrgyzstan

Total

Transmission Infrastructure

$ 242.00

$ 159.00

$ 240.00

$ 160.00

$ 801.00

Project Implementation Support

$ 8.00

$ 7.00

$ 8.00

$ 7.00

$ 30.00

Community support program (Construction Phase)

$ 40.00

$ 10.00

$ 10.00

$ 10.00

$ 70.00

Environmental and social cost

$ 13.00

$ 3.00

$ 3.00

$ 1.00

$ 20.00

Total base cost

$ 303.00

$ 179.00

$ 261.00

$ 178.00

$ 921.00

Contingencies

$ 61.00

$ 24.00

$ 36.00

$ 24.00

$ 145.00

taxes and IDC

$ 40.00

$ 29.00

$ 4.00

$ 31.00

$ 104.00

Total

$ 101.00

$ 53.00

$ 40.00

$ 55.00

$ 249.00

Total Project Cost

$ 404.00

$ 232.00

$ 301.00

$ 233.00

$ 1,170.00

Figures in million USD

15Slide16

Strengthen Legal And Institutional Capacity.Transit Fees and/or Electricity Off-takes.Synchronized Operation with Interconnected Power Systems.Expansion of The Afghan Power System & Grid.Private Sector Investors Confidence.

Energy Security for Sustainable Development and Growth. Political & Social Stability.16

RECCA Would Benefit AfghanistanSlide17

The strong Regional cooperation & mutual understanding of all the stakeholders resulted in success of CASA-1000 project.We are committed to repeat success story of CASA-1000 by optimum use of forum like RECCA.WE NEED TO MAKE A LEAP BEYOND OUR PAST LIMITATIONS, ELIMINATE BARRIERS OF OUR BORDERS, AND SECURE A REGIONAL POWER TRADE TO HELP CREATE PEACE AND PROSPERITY

FOR ALL. 17Slide18

Thank You!18