Construction  prodecure Construction  prodecure

Construction prodecure - PowerPoint Presentation

conchita-marotz
conchita-marotz . @conchita-marotz
Follow
367 views
Uploaded On 2018-02-20

Construction prodecure - PPT Presentation

of Building Sou Savita Nagesh Shalgar Katare Assistant Research officer Regional Laboratory Camp Pune Mobile No 9545277377 Email snshalgargmailcom 1 PWD MANUAL ID: 633320

amp construction parishad steps construction amp steps parishad zilla building work level district bill village proposal engineer sanctioning selection

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Construction prodecure" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Construction prodecure of Building

Sou.

Savita

Nagesh

Shalgar

(

Katare

),

Assistant Research officer,

Regional Laboratory,

Camp,

Pune

.

Mobile No. 9545277377

Email – snshalgar@gmail.comSlide2

1. P.W.D. MANUAL2. P.W.D.ACCOUNT CODE3. RED BOOK FOR SPECIFICATIONS4.ESTIMATING & COSTING IN CIVIL ENGINEERING ---THEORY & PRACTICE –by B.N.DATTA5. BUILDING CONSTRUCTION –By Bindra6. R.C.C.CONSTRUCTION ---1) Ramchandran 2) Shah & Karve

7.D.S.R. of our own Circle of P.W.D.& District in Maharashtra

8.For Zilla Parishad departmental working procedure Booklet by Government of MaharashtraGram Vikas v Jal Sandharan Vibhag For ----GUIDELINES for construction of Internal Road ,Gutter,Buildings.Z.P.WORKS MADE EASY.– By Er. Vishnu Palave,Executive Engineer,Nashik

Books to refer Slide3

1) Scheme sanctioning by Government.2) Proposal sanctioning letter from District level i.e. Zilla Parishad to BDO i.e. Taluka

level.

3) Call of Meeting c by BDO for site selection for which village it needs.4) Proposal & requirement from village level to Taluka level.Steps Of Construction In Building In Zilla ParishadSlide4

5) Proposal to send at District level.6) Verification by District technical unit7) Needs of paper veritication.8) Sanctioning of proposal by giving adminisitrative

approval

Steps Of Construction In Building In Zilla ParishadSlide5

9) Letter to BDO then to village level10) Actual preparation of Estimate 11) Tender calling – tenders publishing on websites & newspaper12) Submission of Tenders

Steps Of Construction In Building In

Zilla ParishadSlide6

13) Minimum 3 tenders needs for competition.14) Selection of tender which is lowest.15) Letter of sanction i.e. work order 16) Actual work procedureSteps Of Construction In Building In

Zilla

ParishadSlide7

Planning Selection of site/place Lineout of Layout plan Roads Open spaces & Civic amenities Size of plots & Area of land

Steps Of Construction In Building In

Zilla ParishadSlide8

* House design & General arrangements Living House Cattle shed Toilet Water supply Disposal of sewage

CONSTRUCTION STEPS:Slide9

1) Foundation 2) Foundation & plinth 3) Antitermite treatment for foundation 4) Super structure 5) Lintel

6) Roof

7) Flooring 8) Plastering & Finishing 9) Doors & Windows10) Sanitary- waterseal sanitary pit latrines CONSTRUCTION STEPS:Slide10

1) Plinth 1. Excavation 2. Line-out 3. P.C.C. 4. Re-filling 5. Soiling 6. Plinth Beam

CONSTRUCTION STEPS:Slide11

2) Masonry 1. Brick Masonry 2. Stone Masonry 3. External Plaster 4. Internal Plaster 5. Waterproofing

CONSTRUCTION STEPS:Slide12

3) R.C.C.work 1. Form Work 2. Reinforcement 3. Initial Testing 4. Concreting 5. Curing

6. Hacking

7. Final Testing CONSTRUCTION STEPS:Slide13

4) Windows & Grills 5) Electrical Work 6) Plumbing & Drainage 7) Tiling

8) Wood Work

CONSTRUCTION STEPS:Slide14

9) Painting 10) Possession11) Harmony12) Satisfaction

CONSTRUCTION STEPS:Slide15

Measurement of construction by Site Engineer with contractor Preparation of Running Bill in Measurement book i.e. Form No.52Submission Of bill to Village Panchayat after scrutiny by Deputy Engineer.

5% checking by Executive Engineer

Checking by Account Section.CONSTRUCTION STEPS:Slide16

Payment of bill Red Cross mark in M.B. by Account SectionCompletion CertificateFinal bill preparation after completion of total construction

CONSTRUCTION STEPS: