/
PH-ADO-PO Section meeting PH-ADO-PO Section meeting

PH-ADO-PO Section meeting - PowerPoint Presentation

criticanime
criticanime . @criticanime
Follow
342 views
Uploaded On 2020-06-19

PH-ADO-PO Section meeting - PPT Presentation

8 th of September 2015 Project Office Activities R Vuillermet 08092015 R Vuillermet PHADOPO 1 Overview Resources Development for 2016 Yearly Technical Stop BMG Prepare the LS2 2019 ID: 781401

ado vuillermet chambers 2015 vuillermet ado 2015 chambers design installation nsw sectors project system njd tatiana tomasz bmg movement

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "PH-ADO-PO Section meeting" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

PH-ADO-POSection meeting8th of September 2015

Project Office ActivitiesR. Vuillermet

08/09/2015

R. Vuillermet PH-ADO-PO

1

Slide2

OverviewResourcesDevelopment for 2016 Yearly Technical Stop

BMGPrepare the LS2 (2019)nSW/nJD BIS7/8Prepare the LS3 (2024)

Muon BarrelITKLArg

End CapConclusions

08/09/2015

R. Vuillermet PH-ADO-PO

2

Slide3

Resources in ATLAS Project Office

Raphaël Vuillermet Project office supervisor

Tatiana Klioutchnikova

Tomasz Piotr

Blaszczyk

Fellow since

01/09/2015

Gevorg

Akhperjanyan

Alexander Seletskiy

Julien Migne Wim Van EmdenMarco Ciapetti Fellow since 01/03/2014Vit Zahradnik Giancarlo Spigo RSOClaudio Bortolin ATLAS cooling activities Jamie Pinnel Workshop and design activitiesAugusto Sciuccati Fellow since 01/01/2015 – FEA specialist

08/09/2015

R. Vuillermet PH-ADO-PO

3

Slide4

Development for 2016 Yearly Technical stop

08/09/2015R. Vuillermet PH-ADO-PO

4

Slide5

Space for BMG chambers

BMG chambers

(between feet in sectors 12,14)

(

Wim

, Tatiana)

Done:

Layout and envelope of BMG chambers

Chamber support concept

Conceptual installation scenario

Conceptual tooling design

Ongoing study:Detail design of the installation toolPrepare installation procedure Total number: 12 chambers Small tube MDTInstallation foreseen: Q1 2017

Slide6

BME

BMG

Brackets for BME chambers

BML

BMF

6

Slide7

Development for LS2

08/09/2015R. Vuillermet PH-ADO-PO

7

Slide8

nSW project

TC is in charge of the following task.The design, the procurement and the assembly of the nJD and nSW structures. (

Giancarlo, Marco, Julien,

Jamie, Augusto)Design of the movement system (Michel

,

Tomasz, Augusto)

Design of the transport and lifting system

(Raphael

,

Vit

, Augusto)

Envelop definition (Tatiana, Alexandre)Installation of the sectors on the nSW structureThe design is well advance and a technical design review will take place on 2d of November. After the review feedbacks, tendering and procurement process will start.

Slide9

nJD/nSW08/09/2015

R. Vuillermet PH-ADO-PO

9

Particularities of this

nSW

/

nJD

is that the structure of the chamber support is connected with the structure of the JD for stiffness reasons.

Slide10

08/09/2015

R. Vuillermet PH-ADO-PO10

New movement interface to cope with the new centrum of gravity

A-plate to stiffen the JD

Sectors are a package of

MicroMegas

and

sTGC

Chambers (that are going to be assembled in b180)

New alignment bar system

Slide11

08/09/2015

R. Vuillermet PH-ADO-PO11

New Small Wheel Frame is not movable on the hub as it is for the current one but linked to the JD to reinforce it to have more precise geometrical supports for the sectors.

Slide12

08/09/2015

R. Vuillermet PH-ADO-PO12

New JD is made of 40mm tick plate instead of 80 mm for the current one.

Assembly will be done vertically in b191.

Small windows to provide access to the chamber kinematical mounts

Slide13

08/09/2015

R. Vuillermet PH-ADO-PO13

New Hub in copper.

Slide14

08/09/2015

R. Vuillermet PH-ADO-PO14

Slide15

nJD

/nSW movement system(Michel, Tomasz)

08/09/2015

R. Vuillermet PH-ADO-PO

15

Design the new movement system compatible with the new mass repartition of the JD/SW

Solution :

New blocking jacks system

One removable air pad

Slide16

Transport and lifting toolDevelop the transport tools to move the

nJD/nSW from b191 to SX1 and from SX1 to UX15.Develop the transport procedure considering the time and space constrains in the buildings.New concept respect to the current transport frame

08/09/2015

R. Vuillermet PH-ADO-PO

16

Resting frame

Lifting tool

Slide17

With this two tooling we can save the rotating operation on air pads in SX1(time and manpower consuming) as is can be done thanks to the crane hook

08/09/2015R. Vuillermet PH-ADO-PO

17

Slide18

In parallel to the design, FEA simulation are on going to validate the design to end up with a realistic proposal

Slide19

Done:BIS7/8 layout and envelope for standard sectors 2,4,6 discussed and agreed

Alignment conceptPreliminary installation scenario study

Ongoing study:

Layout and envelope drawing for standard sectorsCritical areas of envelope

Total number: 16 chambers Small tube MDT + RPC

BIS7/8 chambers

(SMDT + RPC)

(Alexandre,

Wim

, Tatiana)

Slide20

BIS7/8 chamber

Slide21

Development for LS3

08/09/2015R. Vuillermet PH-ADO-PO

21

Slide22

End-Cap Calorimeter flange calculation (Augusto, Michel)

Verification of deformation and stresses inside the flange of the end-cap calorimeter for LS3 possible upgrade.New elastoplastic finite element model developed to control locally the material behavior.

08/09/2015

R. Vuillermet PH-ADO-PO

22

Slide23

ITK (Augusto, Raphael, Michel)

Installation scenarioDefinition of the installation option Verification of the rail support option

Control of the bolted connection of the rail and bolted optionPropose a design for the interface between OC and rail

systemPrepare insertion test during LS2

Slide24

BI layer MDT front end electronics replacement (RO side)RPC installation for BI layer of chambers ( BIS, BIL, BIM,

BIR)

Done:

Feasibility studyTime and manpower estimations for 2 scenarios

Ongoing activity:

Summary document

Total number: RPC and electronics for all BIS, BIL, BIM,

BIR

chambers

Installation foreseen:

LS3

BISBILBI project studies (Tatiana, Alexander)

Slide25

MDT front-end electronics

New RPC chambers

Slide26

BI

project sectors 11, 15

BIM2C11

BIM1C11

Slide27

CAD models and layout drawings improvement

Update of Muon layout drawing with chambers installed during

LS1

: BOE and

BME

in sector 13

(Gevorg)

Correction of EIL4 models with position of movement mechanism. Creation of simplified models in run position and radial opening for all sectors

(Tomasz)

EEL, EES – creation of simplified models for integration study purpose (Gevorg)

Assembly drawings for LS1 EB and inner gap schaffolding (Gevorg)Update USA15 model with equipment installed during LS1 (Tomasz)JF lifting table model

BEE chambers on ECT simplified models

Z0 cable trays as-built update

Reverse Engineering

(Tatiana, Alexander,

Gevorg

,

Vit

, Tomasz,

Wim

)

Slide28

Conclusion and activities

08/09/2015R. Vuillermet PH-ADO-PO

28

Slide29

Conclusion

At the end of 2015 most of the engineering activities will concentrate on the BMG, BIS7&8 and nSW which are important milestone for ATLAS TC in the short term.Some of us will nevertheless continue the effort on for LS3 on ITK and BI which are also challenging project and demanding

to clarify several points to prepare TDR.

08/09/2015

R. Vuillermet PH-ADO-PO

29