8 th of September 2015 Project Office Activities R Vuillermet 08092015 R Vuillermet PHADOPO 1 Overview Resources Development for 2016 Yearly Technical Stop BMG Prepare the LS2 2019 ID: 781401
Download The PPT/PDF document "PH-ADO-PO Section meeting" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
PH-ADO-POSection meeting8th of September 2015
Project Office ActivitiesR. Vuillermet
08/09/2015
R. Vuillermet PH-ADO-PO
1
Slide2OverviewResourcesDevelopment for 2016 Yearly Technical Stop
BMGPrepare the LS2 (2019)nSW/nJD BIS7/8Prepare the LS3 (2024)
Muon BarrelITKLArg
End CapConclusions
08/09/2015
R. Vuillermet PH-ADO-PO
2
Slide3Resources in ATLAS Project Office
Raphaël Vuillermet Project office supervisor
Tatiana Klioutchnikova
Tomasz Piotr
Blaszczyk
Fellow since
01/09/2015
Gevorg
Akhperjanyan
Alexander Seletskiy
Julien Migne Wim Van EmdenMarco Ciapetti Fellow since 01/03/2014Vit Zahradnik Giancarlo Spigo RSOClaudio Bortolin ATLAS cooling activities Jamie Pinnel Workshop and design activitiesAugusto Sciuccati Fellow since 01/01/2015 – FEA specialist
08/09/2015
R. Vuillermet PH-ADO-PO
3
Slide4Development for 2016 Yearly Technical stop
08/09/2015R. Vuillermet PH-ADO-PO
4
Slide5Space for BMG chambers
BMG chambers
(between feet in sectors 12,14)
(
Wim
, Tatiana)
Done:
Layout and envelope of BMG chambers
Chamber support concept
Conceptual installation scenario
Conceptual tooling design
Ongoing study:Detail design of the installation toolPrepare installation procedure Total number: 12 chambers Small tube MDTInstallation foreseen: Q1 2017
Slide6BME
BMG
Brackets for BME chambers
BML
BMF
6
Slide7Development for LS2
08/09/2015R. Vuillermet PH-ADO-PO
7
Slide8nSW project
TC is in charge of the following task.The design, the procurement and the assembly of the nJD and nSW structures. (
Giancarlo, Marco, Julien,
Jamie, Augusto)Design of the movement system (Michel
,
Tomasz, Augusto)
Design of the transport and lifting system
(Raphael
,
Vit
, Augusto)
Envelop definition (Tatiana, Alexandre)Installation of the sectors on the nSW structureThe design is well advance and a technical design review will take place on 2d of November. After the review feedbacks, tendering and procurement process will start.
Slide9nJD/nSW08/09/2015
R. Vuillermet PH-ADO-PO
9
Particularities of this
nSW
/
nJD
is that the structure of the chamber support is connected with the structure of the JD for stiffness reasons.
Slide1008/09/2015
R. Vuillermet PH-ADO-PO10
New movement interface to cope with the new centrum of gravity
A-plate to stiffen the JD
Sectors are a package of
MicroMegas
and
sTGC
Chambers (that are going to be assembled in b180)
New alignment bar system
Slide1108/09/2015
R. Vuillermet PH-ADO-PO11
New Small Wheel Frame is not movable on the hub as it is for the current one but linked to the JD to reinforce it to have more precise geometrical supports for the sectors.
Slide1208/09/2015
R. Vuillermet PH-ADO-PO12
New JD is made of 40mm tick plate instead of 80 mm for the current one.
Assembly will be done vertically in b191.
Small windows to provide access to the chamber kinematical mounts
Slide1308/09/2015
R. Vuillermet PH-ADO-PO13
New Hub in copper.
Slide1408/09/2015
R. Vuillermet PH-ADO-PO14
Slide15nJD
/nSW movement system(Michel, Tomasz)
08/09/2015
R. Vuillermet PH-ADO-PO
15
Design the new movement system compatible with the new mass repartition of the JD/SW
Solution :
New blocking jacks system
One removable air pad
Slide16Transport and lifting toolDevelop the transport tools to move the
nJD/nSW from b191 to SX1 and from SX1 to UX15.Develop the transport procedure considering the time and space constrains in the buildings.New concept respect to the current transport frame
08/09/2015
R. Vuillermet PH-ADO-PO
16
Resting frame
Lifting tool
Slide17With this two tooling we can save the rotating operation on air pads in SX1(time and manpower consuming) as is can be done thanks to the crane hook
08/09/2015R. Vuillermet PH-ADO-PO
17
Slide18In parallel to the design, FEA simulation are on going to validate the design to end up with a realistic proposal
Slide19Done:BIS7/8 layout and envelope for standard sectors 2,4,6 discussed and agreed
Alignment conceptPreliminary installation scenario study
Ongoing study:
Layout and envelope drawing for standard sectorsCritical areas of envelope
Total number: 16 chambers Small tube MDT + RPC
BIS7/8 chambers
(SMDT + RPC)
(Alexandre,
Wim
, Tatiana)
Slide20BIS7/8 chamber
Slide21Development for LS3
08/09/2015R. Vuillermet PH-ADO-PO
21
Slide22End-Cap Calorimeter flange calculation (Augusto, Michel)
Verification of deformation and stresses inside the flange of the end-cap calorimeter for LS3 possible upgrade.New elastoplastic finite element model developed to control locally the material behavior.
08/09/2015
R. Vuillermet PH-ADO-PO
22
Slide23ITK (Augusto, Raphael, Michel)
Installation scenarioDefinition of the installation option Verification of the rail support option
Control of the bolted connection of the rail and bolted optionPropose a design for the interface between OC and rail
systemPrepare insertion test during LS2
Slide24BI layer MDT front end electronics replacement (RO side)RPC installation for BI layer of chambers ( BIS, BIL, BIM,
BIR)
Done:
Feasibility studyTime and manpower estimations for 2 scenarios
Ongoing activity:
Summary document
Total number: RPC and electronics for all BIS, BIL, BIM,
BIR
chambers
Installation foreseen:
LS3
BISBILBI project studies (Tatiana, Alexander)
Slide25MDT front-end electronics
New RPC chambers
Slide26BI
project sectors 11, 15
BIM2C11
BIM1C11
Slide27CAD models and layout drawings improvement
Update of Muon layout drawing with chambers installed during
LS1
: BOE and
BME
in sector 13
(Gevorg)
Correction of EIL4 models with position of movement mechanism. Creation of simplified models in run position and radial opening for all sectors
(Tomasz)
EEL, EES – creation of simplified models for integration study purpose (Gevorg)
Assembly drawings for LS1 EB and inner gap schaffolding (Gevorg)Update USA15 model with equipment installed during LS1 (Tomasz)JF lifting table model
BEE chambers on ECT simplified models
Z0 cable trays as-built update
Reverse Engineering
(Tatiana, Alexander,
Gevorg
,
Vit
, Tomasz,
Wim
)
Slide28Conclusion and activities
08/09/2015R. Vuillermet PH-ADO-PO
28
Slide29Conclusion
At the end of 2015 most of the engineering activities will concentrate on the BMG, BIS7&8 and nSW which are important milestone for ATLAS TC in the short term.Some of us will nevertheless continue the effort on for LS3 on ITK and BI which are also challenging project and demanding
to clarify several points to prepare TDR.
08/09/2015
R. Vuillermet PH-ADO-PO
29