H Bartosik G Iadarola G Rumolo LHC Performance Workshop Chamonix 2014 22 9 2014 Many thanks to G Arduini T Argyropoulos T Bohl K Cornelis H ID: 620447
Download Presentation The PPT/PDF document "SPS scrubbing run in 2014" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
SPS scrubbing run in 2014
H. Bartosik, G. Iadarola, G. Rumolo
LHC Performance Workshop (Chamonix 2014), 22/9/2014
Many thanks to:
G.
Arduini
, T
.
Argyropoulos
, T.
Bohl
, K.
Cornelis
, H
.
Damerau
,
J
. Esteban
Müller, B. Goddard, S
. Hancock, W.
Höfle
,
L.
Kopylov
,
H
.
Neupert
,
Y
.
Papaphilippou
, G.
Papotti
, E.
Shaposhnikova
, M.
Taborelli
and the SPS operator crewSlide2
Outline
Introduction
The 2014 SPS scrubbing run
Possible cycles
Scrubbing stages
Possible
supercycle composition
The doublet scrubbing beam
Motivation
Production scheme
Experience in 2012-13 MDs
Scrubbing preparation
Beams from the PS
SPS setup
MeasurementsSlide3
Outline
Introduction
The 2014 SPS scrubbing run
Possible cycles
Scrubbing stages
Possible
supercycle composition
The doublet scrubbing beam
Motivation
Production scheme
Experience in 2012-13 MDs
Scrubbing preparation
Beams from the PS
SPS setup
MeasurementsSlide4
Electron cloud in the SPS and scrubbing
Strong limitation due to e-cloud in the past
Instabilities at injection + incoherent effects
Emittance
blow-up along the batch
High chromaticity needed for beam stability
Pressure rise around the machine
Situation improved gradually due to scrubbing
Requires days of dedicated running in high electron cloud
conditions
Secondary
Electron Yield reduction by the e-cloud
itself
Scrubbing runs since 2002
Performed at 26
GeV
in cycling mode (~40 s cycle length)
Typically limited by heating and/or outgassing
~1-2 weeks periods
SPS scrubbing history
43.2 s
2002
(14d)
2003
(8d)
2004
(10d)
2006
(5d)
2007
(7d)
2008
(2.5d)
2012
(5d)
2009
(1.5d)
Shutdown
400%
2000
(48 b. - 0.8x10
11
p/b
@inj.)
3.5
μmSlide5
SPS scrubbing run 2014
Goals for 2014:
Q
ualify the loss of conditioning
due to LS1
Recover 2012 performance
with 25 ns beamsQ
uantify
amount of beam/time
needed
Test “doublet” scrubbing beam
to be used in the LHC in 2015
Qualification criterion
beam quality measurements
Ideally,
achieve by the end of the allocated scrubbing time:
25 ns, 4 batches, up to 1.3e11ppb,
emittances
below nominal, no blowup along the
train
as in 2012
basis for LIU strategy on e-cloud mitigation – coating vs scrubbingSlide6
From 2014 injector schedule (current version)Slide7
From 2014 injector schedule (current version)
S
crubbing originally foreseen in two consecutive weeks (W39-40), before the start-up of the NA physics. Then split between Weeks 39 and 45
F
inally
spread over Week 45 plus an additional two-day mini-block in Week 50
Several reasons for splitting the scrubbing run into two blocks
(requested by LIU-SPS)
:
Gives
time to
analyze
the first
block’s
results
and
adapt accordingly
Untangling scrubbing from the
machine commissioning, NA setup
and
vacuum
conditioning of all the newly-installed or vented equipment
Allows
setting up scrubbing beams before
the 2nd scrubbing
block
the “doublet” beam
– its potential
to scrub the SPS can be explored already in 2014 (also in view of LHC scrubbing in 2015)Slide8
Pre-scrubbing cycles
Over weeks 41 – 44
some experience will be already gained during the available parallel and dedicated MD time
Both single bunch and 25 ns beam (1 batch) on short
f
lat
bottom cycle (6BP) should
be
already set up
Work on
recovery performance for nominal 25 ns beam
might have already started
(
with the consequent scrubbing
)
6 BPs (7.2 s)
Inj.
DumpSlide9
Scrubbing cycles
We will need to accumulate dose and monitor the evolution of beam parameters for both coherent and incoherent effects
4 or more batches circulating in the
machine at 26 GeV
Acceleration to 450 GeV should
be
fully set up and used for scrubbing qualification
18 BPs (21.6 s)
33 BPs (39.6 s)
Inj.
Inj.
Inj.
Inj.
Dump
Inj.
Inj.
Inj.
Inj.
Inj.
Dump
Inj.
Inj.
Inj.
Inj.
19
BPs
(22.8
s)Slide10
Planning (to be steered on the fly)
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
Intensity ramp up at 26
GeV
on intermediate flat bottom cycle (21.6 s)
First
scrubbing
block
Intensity
ramp up
at 26
GeV
with 25 ns beams (ideally up to
5
injections –
try to push bunch intensity up
to 1.5x10
11
p/b?)
Inj.
Inj.
Inj.
Inj.
Dump
Possible
supercycle
(to be coordinated with
physics in the PS complex)
Inj.
Week 45Slide11
Planning (to be steered on the fly)
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
Intensity ramp up at 26
GeV
on intermediate flat
bottom cycle (21.6
s)
First
scrubbing
block
Intensity
ramp up
at 26
GeV
with 25 ns beams (ideally up to 5 injections – try to push bunch intensity up to 1.5x10
11
p/b?)
Study
residual electron cloud effects on beam lifetime and quality
for nominal beam (e.g.
emittance
growth, bunch shortening over long flat bottom
) while gradually lowering vertical chromaticity setting for
stability
Inj.
Dump
Inj.
Inj.
Inj.
Inj.
Possible
supercycle
Studies on long flat
bottom cycle (39.6 s)
Week 45Slide12
Planning (to be steered on the fly)
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
Intensity ramp up at 26
GeV
on intermediate flat
bottom cycle (21.6
s)
First
scrubbing
block
Intensity
ramp up
at 26
GeV
with 25 ns beams (ideally up to 5 injections – try to push bunch intensity up to 1.5x10
11
p/b?)
Study
residual electron cloud effects on beam lifetime and quality
for nominal beam (e.g.
emittance
growth, bunch shortening over long flat bottom) while gradually lowering vertical chromaticity setting for
stability
Acceleration
and
scrubbing qualification
Studies on long flat
bottom cycle (39.6 s)
Scrubbing qualification
(25 ns
std
and BCMS, up to 450
GeV
)
Possible
supercycle
for scrubbing + qualification
Week 45Slide13
Planning (to be steered on the fly)
MondayTuesday
Second
scrubbing
block
At this stage
doublet beam could be ready including acceleration
The goal is to
accumulate the largest possible electron dose on the beam chambers
The results of the tests with the doublet beam will be important for the LHC scrubbing in 2015
Wednesday
Week 50
Possible
supercycle
Scrubbing with doublet
(possibly with acceleration)
Dedicated MD (scrubbing)
18 BPs (21.6 s)
Inj.
Inj.
Inj.
Inj.
DumpSlide14
Outline
Introduction
The 2014 SPS scrubbing run
Possible cycles
Scrubbing stages
Possible
supercycle composition
The doublet scrubbing beam
Motivation
Production scheme
Experience in 2012-13 MDs
Scrubbing preparation
Beams from the PS
SPS setup
MeasurementsSlide15
“Doublet” scrubbing beam: introduction
Scrubbing with 25 ns
beam allowed to lower the SEY of the dipole chambers well below the multipacting threshold for 50 ns
e-cloud free operation with 50 ns beams
Can we go to lower bunch spacing to
scrub for 25 ns operation?
Due to RF limitations in the PS it is impossible to inject bunch-to-bucket into the SPS with spacing shorter than 25 ns
An alternative is to inject
long bunches into
the SPS
and capturing each bunch in two neighboring buckets
obtaining a
(5+20
)
ns “hybrid” spacing
Non adiabatic splitting at SPS injectionSlide16
“Doublet” scrubbing
beam: introduction
Non adiabatic splitting at SPS injection
20 ns
5 ns
Scrubbing with 25 ns
beam allowed to lower the SEY of the dipole chambers
well below the
multipacting
threshold for 50 ns
e-cloud free operation with 50 ns beams
Can we go to lower bunch spacing
to
scrub for 25 ns operation?
Due to RF limitations in the PS it is impossible to inject bunch-to-bucket into the SPS with spacing shorter than 25 ns
An alternative is to inject
long bunches into
the SPS
and capturing each bunch in two neighboring buckets
obtaining a
(5+20
)
ns “hybrid” spacingSlide17
“Doublet” scrubbing beam: introduction
Close to the threshold
all the electrons produced after a bunch passage are absorbed before the next one
small accumulation
over subsequent bunch passages
PyECLOUD simulation
Std
25 ns beam
e-cloud enhancement
mechanism:Slide18
More e
- production and shorter e- decay
accumulation possible
PyECLOUD simulation
Std
25 ns beam
Doublet beam
e-cloud enhancement
mechanism:
“Doublet” scrubbing
beam: introductionSlide19
“Doublet” scrubbing
beam:
SPS simulation resultsMBA dipole magnet
MBB dipole magnet
Significantly lower
multipacting
threshold
for large enough intensity per doubletSlide20
“Doublet” scrubbing
beam:
SPS simulation resultsSignificantly lower
multipacting
threshold for large enough intensity per doublet
Beam orbit modulation
needs to be applied to condition a wide enough area of the chamber
MBB - 26GeV
Intensity per bunch of the doublet (
b.l
. 4 ns
)
(
b.l
. 3 ns)Slide21
First machine tests
have been conducted at the SPS at the end of 2012-13 run in order to validate the production scheme and obtain first indications about the e-cloud enhancementThe production scheme has been successfully tested for a train of (2x)72 bunches with
1.7e11 p per doublet
4
2
6
6
0
1
2
3
Time [
ms
]
200 MHz RF Voltage [MV]
4
-1
0
1
st
inj.
Measurements by to
T.
Argyropoulos
and
J. Esteban Muller
“Doublet” scrubbing
beam:
first test at the SPSSlide22
“Doublet” scrubbing
beam:
first test at the SPS
4
2
3604
3600
3602
3598
3596
3594
6
6
3592
3590
0
1
2
3
Time [
ms
]
200 MHz RF Voltage [MV]
4
-1
0
1
st
inj.
2
nd
inj.
Profile of the first doublet
First machine tests
have been conducted at the SPS at the end of 2012-13 run in order to
validate the production scheme
and obtain first indications about the e-cloud enhancement
The production scheme has been
successfully tested
for a train of (2x)72 bunches with
1.7e11 p per doublet
The
possibility of injecting a second batch
without degrading the circulating
beam
has also been shownSlide23
“Doublet” scrubbing
beam:
first test at the SPS
Measurement
Simulation
First results looked very encouraging
,
e-cloud enhancement confirmed by:
Measurements
with the
electron cloud detectors
(agreement with measured cloud profile gives an
important validation for our simulation model
and code)Slide24
25ns std. (1.6e11p/bunch
)
(
1.6e11p/doublet)
25ns “doublet”
“Doublet” scrubbing
beam:
first test at the SPS
First results looked very encouraging
,
e-cloud enhancement confirmed by:
Measurements
with the
electron cloud detectors
(agreement with measured cloud profile gives an
important validation for our simulation model
and code)
Dynamic pressure measurements
observed in the SPS arcsSlide25
First results looked very encouraging
,
e-cloud enhancement confirmed by:
Measurements
with the
electron cloud detectors
(agreement with measured cloud profile gives an
important validation for our simulation model
and code)
Dynamic pressure measurements
observed in the SPS arcs
“Doublet” scrubbing
beam:
first test at the SPS
Provided that we can produce and preserve a good quality (multiple batches, large bunch intensity),
this beam will be used during the two-day mini-scrubbing run at the end of the 2014 run
Acquired
experience
will be very important for the definition of
the LIU-SPS strategy
with respect to e-cloud and scrubbing and
for
the LHC scrubbing in 2015
To be noted
Need to commission the new transverse damper for doublets at injection
SPS BQM software was updated for doublet beamsSlide26
Outline
Introduction
The 2014 SPS scrubbing run
Possible cycles
Scrubbing stages
Possible
supercycle composition
The doublet scrubbing beam
Motivation
Production scheme
Experience in 2012-13 MDs
Scrubbing preparation
Beams from the PS
SPS setup
MeasurementsSlide27
Beam requirements
From the PS:
Before first scrubbing week (W45):
25 ns beam
(std. production scheme and BCMS, 72 b., up to 1.5e11 ppb)
50 ns beam (std. production scheme, 36 b., up to 1.7e11 ppb
) – as backupIn addition, before second scrubbing block
(
W50):
25 ns
beam
for doublet production
(>1.5e11 ppb, long bunches at extraction)
From earlier SPS setup and MDs:
Before
first scrubbing week (
W45):
Basic setup
(injection, orbit, working point, RF, damper) of
26
GeV
flat bottom cycle
(with 25 or 50 ns beams, Q20)
Setup
of
25 ns
LHC filling
cycle
Before second block (W50):
Setup of “doublet” beam at 26GeV
(capture of multiple batches, orbit, working point, RF, damper) and possibly accelerationSlide28
Measurements
Tests which compromise the scrubbing efficiency should be kept to the minimum possible
Collect as much data as possible to learn about
ecloud
effects and scrubbing in the SPS
BCT/FBCT (to estimate beam dose)
Longitudinal parameters (BQM,
mountain range, faraday cage scope)
Beam transverse oscillations
BBQ, LHC BPMs,
Headtail
monitor, fast pickup from HBWD
feedback setup, new digitizers on BPW exponential pickups
Beam transverse size
Wirescanners
(bunch by bunch), BGI
(?)
Pressure
along the ring (1 Hz
rate
)
Special attention to the a-C coated magnets
Dedicated e-cloud equipment
Electron cloud monitors (MBA
StSt
, MBB
StSt
, MBB a-C, MBB copper)Shielded pickup
In situ SEY measurement (if available)
Removable
StSt sample (for lab SEY measurement)
COLDEX Slide29
Summary and conclusions
In the past, SPS was strongly limited by e-cloud
Scrubbing proved to be an effective
mitigation for 25 ns beams up
to nominal intensity
25 ns
beams delivered to LHC in
2012 were well
within design report
specs
Scrubbing
run 2014
To recondition SPS after LS1, since
large
parts
of
the SPS
were vented
1
st
block: 7 days (week 45)
Qualify the loss of conditioning
due to LS1
Recover 2012 performance
with 25 ns beams
2
nd
block: 2(3) days (week 50)Test scrubbing with doublet (also in view of LHC in 2015)
Experience gained will be
needed for LIU decision about SPS coating Need to prepare beams from the PS and test instrumentation in SPSSlide30
Thanks for your attention!Slide31
No additional impedance heating
is expected with the doublet beam (same total intensity)Beam power spectrum is modulated with cos
2 functionLines in the spectrum can only be weakened by the modulation
“Doublet” beam: beam induced heating
Thanks to
C.
Zannini