Bad Moon Rising in ERCOT PowerPoint Presentation

Bad Moon Rising in ERCOT PowerPoint Presentation

2017-05-14 67K 67 0 0

Description

RMR. 1. “So . you're going to be talking in a . minute about . an RMR contract in Houston, and that should concern . you.” . “…what other . RTOs also have that ERCOT does not have is . a recognition . ID: 548171

Embed code:

Download this presentation



DownloadNote - The PPT/PDF document "Bad Moon Rising in ERCOT" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.

Presentations text content in Bad Moon Rising in ERCOT

Slide1

Bad Moon Rising in ERCOT

RMR

1

Slide2

“So you're going to be talking in a minute about an RMR contract in Houston, and that should concern you.” “…what other RTOs also have that ERCOT does not have is a recognition of a need in local areas like Houston.”“You can either just keep building transmission and building transmission to make sure you never have areas like that that, but in the case of Houston now you have an RMR contract with a generator that's premised I think largely on this sort of need, and the reality is that transmission is not always the cheapest answer. In fact, it's often not the cheapest answer.”- Dr. David Patton, Potomac Economics (from the June 14th ERCOT Board of Directors Meeting)

2

Slide3

Our Future?

What is likely to transpire under the current rules.Units that are uneconomic given the current pricing environment and future environmental regulations will choose to mothball or retire. The departure of capacity from the market will likely come in chunks (not all at once).ERCOT will study each mothball request and make a determination if the unit is required to remain on “RMR for transmission.” ERCOT’s RMR study does not consider resource adequacy or “emergency procurement” (i.e. RMR for capacity).As more capacity departs, the more likely ERCOT’s RMR studies will conclude that departing units will be “needed for transmission.” Each RMR contract must have an exit plan which will likely result in transmission infrastructure construction. Alternatives are possible but unlikely.Locational price signals will be defeated by the presence of RMR units (or MRA) and the eventual construction of transmission. This will lead to more RMR and more transmission. Where does this take us as a market?

3

Slide4

Concerns with RMR in ERCOT

The current RMR process poses a threat to market principles both from a locational aspect and a resource adequacy aspect and will result in a historically inefficient deployment of capital if left unchanged.RMR impacts price signal and shifts significant cost from the market to loads (i.e. avoidable costs to unavoidable costs).Retaining uneconomic, end-of-life generation on RMR defeats locational price signal.Load pockets with insufficient generation likely to be deemed non-competitive. NPRR784 provides a short-term solution.RMR will likely result in more and more transmission which is economically inefficient for loads (residential load bears a higher proportion of transmission cost which impacts the retail market).What is the policy trigger for “emergency procurement”? Anticipated emergency?RMR will inject new capital into the most uneconomic generation assets in ERCOT and those costs will be funded by loads.The “All-In” energy price for consumers will go up for the wrong reasons.

4

Slide5

Potential RMR Reforms?

Short-termRevisit the notice period for suspending operation of generation resource.Revisit the treatment of capital costs for “RMR for transmission”.Improve process for stakeholder comment on RMR studies, proposed RMR contracts, and MRA.Reform the MRA/RFP process.Long-termReform RMR study inputs such as load forecast assumptions.Establish study criteria to distinguish between a transmission issue and a resource adequacy (Emergency Procurement/RMR for capacity) issue.Eliminate the requirement to construct new transmission (i.e. exit plan).Let the unit suspend operation.Establish a new type of RMR that minimizes costs to loads.Pursue a reliability exemption to avoid environmental compliance costs.Revisit RMR cost allocation.

5

Slide6


About DocSlides
DocSlides allows users to easily upload and share presentations, PDF documents, and images.Share your documents with the world , watch,share and upload any time you want. How can you benefit from using DocSlides? DocSlides consists documents from individuals and organizations on topics ranging from technology and business to travel, health, and education. Find and search for what interests you, and learn from people and more. You can also download DocSlides to read or reference later.